Contemporary Engineering Economics (6th Edition)
6th Edition
ISBN: 9780134105598
Author: Chan S. Park
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Question
Chapter 5, Problem 57P
To determine
Calculate the present worth.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
5-S2 A new recycling sorting and processing line is proposed to serve a medium size city. The
installed cost of the new line is $2,400,000. The residual value after ten years is estimated at
$480,000. The unit would produce recycled material ready for resale at a rate of $0.15/pound,
and would run for ten years. How much recyclable material must be generated every year to
justify the project (i.e., for the present value of the project to be positive). Use an interest rate
of 9%.
A)Two options of feed-water storage installation are being considered to serve over 20 years
of useful life:
Option 1: Build a 20,000-gallon tank on a tower. The cost of installing the tank and tower
is estimated to be $170,000. The annual operating and maintenance cost after tax
adjustment is estimated to be $2,000. The salvage value is estimated to be negligible.
Option 2: Place a 20,000-gallon tank of equal capacity on a hill near the refinery. The cost
of installing the tank on the hill, including the extra length of service lines, is estimated to
be $120,000 with negligible salvage value. The annual operating and maintenance cost of
the water tank is estimated to be $1,500 after tax adjustment. Because of the location, an
additional investment of 13,000 in pumping equipment is required. The pumping
equipment is expected to have a service life of 10 years with a salvage value of $2,000 at
the end of that time. The annual operating and maintenance cost (including any incometax…
Steve Company is considering replacing one of its machines. The available new model has a cost of $220,000, a 16-year life, and an AOC of $2,000. The machine must also be serviced every 4 years at a cost of $10,000. The machine can be salvaged at $45, 000. The MARR is 12%
How much annual net income must be realized from the machine to recover the capital investment?
Chapter 5 Solutions
Contemporary Engineering Economics (6th Edition)
Ch. 5 - Prob. 1PCh. 5 - Prob. 2PCh. 5 - If a project costs 100,000 and is expected to...Ch. 5 - Refer to Problem 5.2, and answer the following...Ch. 5 - Prob. 5PCh. 5 - Prob. 6PCh. 5 - Prob. 7PCh. 5 - Prob. 8PCh. 5 - Consider the cash flows from an investment...Ch. 5 - Prob. 10P
Ch. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Consider the project balances in Table P5.19 for a...Ch. 5 - Your RD group has developed and tested a computer...Ch. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Geo-Star Manufacturing Company is considering a...Ch. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Two methods of carrying away surface runoff water...Ch. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 1STCh. 5 - Prob. 2ST
Knowledge Booster
Similar questions
- Compute the AW (annual worth) of The Bella. Remember to include your calculations in your supporting work. Round your answer to the nearest dollar.arrow_forwardA contractor has purchased a wheel loader for $115,000 and plans to use it for 2,000 hours per day. The cost of one set of tires is $25,000. At this usage rate, the contractor anticipates disposing of the loader after using it for 10 years and realizing a salvage value of $35,000. The flywheel horsepower rating of the loader's diesel engine is 105 horsepower. The interest rate is 10%. The loader operator will earn $34.00 per hour including fringe benefits, and diesel fuel costs $1.20 per gallon. How much is the contractor's hourly ownership cost for the loader if using time value money analysis?arrow_forwardThe following cost and benefit information has been estimated for a pump that has a 10-year useful life. Purchase Cost = $2,400 Annual Operating Cost = $1,200 Annual Maintenance Cost = $300Annual Benefits = $2,000Salvage Value = $200Interest rate specified = 9% or 0.09 Find the capital recovery cost for this pump.arrow_forward
- The following data applies for example problems 8.1 through 8.3. A company is considering the purchase of either machine A or machine B. machine A machine B initial cost $80,000 20 years $20,000 $18,000 per year $100,000 25 years $25,000 $15,000 per year for the first 15 years $20,000 per year for the next 10 years estimated life salvage value other costs The interest rate is 10%, and all cash flows may be treated as end-of-year cash flows. Assume that equivalent annual cost is the value of the constant annuity equal to the total cost of a project. The equivalent annual cost of machine B is most nearly (A) $21,000 (B) $21,500 (C) $23,000 (D) $26,500arrow_forwardYou are weighing the economics of installing a triple-glazed energy efficient window system in your building. The following life cycle costs and savings are provided. The study period is 25 years, and the discount rate is 10%. Is this an economically viable approach based on the Savings-to-Investment Ratio (SIR)? Triple- Glazed Energy Efficient Windows: Window Quantity takeoff: 10000 sf Initial Cost: $100/sf Annual Operating Costs: $2.5/sf Annual Energy Saving: $10/sfarrow_forwardA bridge is to be constructed now as part of a new road. Engineers have determined that current traffic volume on the new road will justify a two-lane road and a bridge at the present time. Because of the uncertainty regarding future traffic, the time at which the additional two lanes will be required is currently being studied. Two alternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $397,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $190,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $190,000 plus an extra $23,000 for every year that widening is delayed. For example, if future widening is done at the end of year 7, the cost of widening at that time will be equal to $190,000 + 7x($23,000) = $351,000. The following estimates have been made of when widening to a four-lane bridge will be required: Pessimistic…arrow_forward
- A California utility firm is considering building a 50-megawatt geothermalplant that generates electricity from naturally occurring underground heal. The binary geothermal system will cost $85 million to build and $6 million (including any income-tax effect) to operate per year. (Unlike a conventional fossil fuel plant, this system will require virtually no fuel costs.) The geothermal plant is to last 25 years. At the end of that time, the expected salvage value will be about the same as the cost to remove the plant. The plant will be in operation for 70% (the plant-utilization factor) of the year (or 70% of 8,760 hours per year). If the firm's MARR is 14% per year, determine the cost of generating electricity per kilowatt-hour.arrow_forwardK CB Electronix needs to expand its capacity. It has two feasible alternatives under consideration. Both alternatives will have essentially infinite lives. Alternative 1: Construct a new building of 20,000 square metres now. The first cost will be $2,300,000. Annual maintenance costs will be $7,000. In addition, the building will need to be painted every 15 years (starting in 15 years) at a cost of $11,000. Alternative 2: Construct a new building of 12,500 square metres now and an additional 7,500 square metres in 9 years. The first cost of the 12,500-square-metre building will be $1,350,000. The annual maintenance costs will be $3,000 for the first 9 years (i.e., until the addition is built). The 7,500-square-metre addition will have a first cost of $1,300,000. Annual maintenance costs of the renovated building (the original building and the addition) will be $9,000. The renovated building will cost $11,000 to repaint every 15 years (starting 15 years after the addition is done).…arrow_forwardA car is needed for three years. Plans A and B for acquiring the car are being evaluated. An effective annual interest rate of 10% is to be used. Which plan is economically superior? Plan A: Lease the car for $0.25/mile (all inclusive) Plan B: Purchase the car for $30,000. Keep the car for three years. Sell the car after three years for $7200. Pay $0.14 per mile for oil and gas. Pay other costs of $500 per year.arrow_forward
- The following pair of assets differ only in the MARR. The problem asks you to determine the effect of this difference on the economic life and to explain the result. All assets decline in value by 20 percent of current value each year. Installation costs are zero for all assets. Further data concerning the four pairs of assets are given in the table that follows. Q Asset A B First Cost $130,000 $130,000 Initial Operating Cost $30,000 $30,000 Rate of Operating Cost Increase 11.5%/year 11.5% / year MARR 5% 25% a. Determine the economic lives for assets A and B. b. Create a diagram showing the EAC(capital), the EAC(operating), and the EAC (total) for assets A and B. c. Explain the difference in economic life between A and B. Click the icon to view the table of compound interest factors for discrete compounding periods when i=5%. a. The economic life of asset A is years, and the economic life of asset B is years.arrow_forwardA bridge is to be constructed now as part of a new road. Engineers have determined that current traffic volume on the new road will justify a two-lane road and a bridge at the present time. Because of the uncertainty regarding future traffic, the time at which the additional two lanes will be required is currently being studied. Two alternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $360,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $170,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $170,000 plus an extra $23,000 for every year that widening is delayed. For example, if future widening is done at the end of year 7, the cost of widening at that time will be equal to $170,000 + 7x($23,000) = $331,000. The following estimates have been made of when widening to a four-lane bridge will be required: Pessimistic…arrow_forwardThe Delta firm intends to buy a device called machine X. Machine X would cost $25,000 and have little salvage value after 10 years of use. The machine is anticipated to bring around $10,000 annually. Do the simple payback period calculation.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education