Chapter 3, Problem 23P
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4.
- a. What is the probability that the project will be completed in 17 months?
- b. What is the probability that the project will be completed in 20 months?
- c. What is the probability that the project will be completed in 23 months?
- d. What is the probability that the project will be completed in 25 months?
- e. What is the due date that yields a 95% chance of completion?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
A company is willing to develop their rocket before the end of current financial
year which is now 28 weeks away. The chief engineer of the company has
decided to use PERT technique in order to plan, schedule and control program
of development for the data given in table below.
What is the probability that the program will be completed by the end of the
current financial year? (all durations are in weeks).
(i) G)
Optimum Duration
Most likely duration
Pesimistic duration
1
2
3
8
13
3
2
8
4
3
8
10
4
7
10
3
6.
3
8
4
9
10
4
8.
4
9.
5
7
9.
12
6.
5
11
7
9.
14
8
4.
00
2.
Chapter 3 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. 3 - Prob. 1EDCh. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...
Ch. 3 - Describe how expected activity times and variances...Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 8PCh. 3 - Prob. 13PCh. 3 - Prob. 15PCh. 3 - Prob. 17PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 33PCh. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Kimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.arrow_forward1.) You have determined the following for a given project: Expected completion time of the project = 40 weeks Standard deviation of project completion time = 8 What is the probability of completing the project in more than 44 weeks? answer as a decimal and take it to four places.arrow_forward11. Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 4. Part 2 a) The probability that the project will be completed in 20 months = ______ (round your response to four decimal places)arrow_forward
- A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)arrow_forwardSuppose the due date of the project is 24 months and expected time of completion is 28 months, while the probability of completing it is 90%. What will be the standard deviation?arrow_forwardThe following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 36 weeks. Task A B C D E F Preceding Tasks to 4 4 2 None A B D, E tm 6 7 7 8 13 9 8 0 W CON 6 tp 8 10 12 18 15 10 Click the icon to view the table of standard normal probabilities. The probability that the project is completed within 36 weeks is. (Enter your response rounded to four decimal places.)arrow_forward
- Analyse the sensitivity analysis and summarise the implications of the analysis for the project, Property acquisition 50%, financing 70% and construction 50%.arrow_forwardStinnett Transmissions, Incorporated, has the following estimates for its new gear assembly project: Price $1,220 per unit; variable costs = $3.75 million; quantity = 90,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Pls don't copy answer i give up votearrow_forwardc. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Project completion time d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4 decimal places.) Probability 10 00 days 09994arrow_forward
- The following represents a project that should be scheduled using CPM: ACTIVITY ABCDEFGH А с IMMEDIATE PREDECESSORS IAABUDR C,D D,E F,G TIMES (DAYS) b a 1 1 3 - NTTTTE 1 1 1 1 2 m 5 WaNNASNU 2 5 4 2 2 6 3 ∞∞NWO3770 9 10 12 8arrow_forwardKimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table Total Cost with Crashing Immediate Predecessor(s) $2,050 $2,800 a) Based on the given information regarding the activities for the project, the project completion date = b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities: The first activity to crash is by 2 weeks at a per week crashing cost of Ned, one should crash activity dollars. Total cost of crashing the project to 7 weeks = and activity E by 1 week at a total per week crashing cost of dollars. dollars. weeks. dollars. dollars. Normal Activity Time (weeks) A TERSE Doo LU LỞ MATMARIATION percen 32 TON * Next one should crash activity D and activity by 2 weeks for an…arrow_forwarda) Explain with examples the differences between the following pairs of terminologies in project risk management:i.Proximity and Dormancy of a Riskii.Stakeholder Risk Threshold and Toleranceiii. iv.Variability Risk and Ambiguity RiskQualitative Risk Analysis and Quantitative Risk Analysis Risk Review and Risk Audit.b) During the execution of a project, a risk is identified by a team member. This newly identified risk is currently not in the risk register. As a project manager, list and briefly explain the steps you will take to manage this risk.c) As a project manager, you will be required to implement risk response plans for your projects. List and explain any five (5) typical outputs of this process.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY