Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:
- a. Determine the expected completion time and variance for each activity.
- b. Determine the total project completion time and the critical path for the project
- c. Determine ES, EF, LS, LF, and slack for each activity.
- d. What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Additional Business Textbook Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Intermediate Accounting (2nd Edition)
Principles Of Marketing
Horngren's Accounting (11th Edition)
- Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Time (days) Activity a 3 5 3 4 1 2 7 TH 3 10 10 ABCD E F G H I K 61 525DE5 13 m Activity A 3 7 11 15 9 This exercise contains only part a. a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) b 9 5 3 8 5 13 49127 13 Immediate Predecessor(s) Expected Time C B, D A, E A, E F G C H, I Variancearrow_forwardKelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Time (days) Immediate Activity Predecessor(s) a A 3 8 B 4. 5 3 D 7 8 6. В, D А, Е А, Е E 1 3 F 2 3 4 7 9 13 11 12 13 F 7 J 15 17 19 K 4 12 H, I This exercise contains only part a. a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) Activity Expected Time Variance Aarrow_forwardMOORE HOUSING CONTRACTORS Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new develop- ment. Countryside wants Moore Contractors to start in late winter or early spring, when the weather begins to moder- ate, and build on through the summer and into the fall. The summer months are an especially busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready, and maybe even before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The comple- tion time is so critical for Countryside Realtors that it is insisting that a project management network accompany the contractor's bid for the job, with an estimate of the comple- tion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. It wants each house to be completed within 45 days after it is started. Activity b C d f 8 h i j k…arrow_forward
- Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Time (days) Immediate Activity a m b Predecessor(s) A 4 6 8 — B 10 11 12 — C 1 2 3 — D 7 8 9 C E 1 3 5 B, D F 1 2 3 A, E G 6 10 13 A, E H 10 11 12 F I 4 6 8 G J 14 16 18 C K 5 9 13 H, I This…arrow_forwardHoosier Burger Juan Rodriquez has assigned you the task of requirements determination for the Hoosier Burger project. You are looking forward to this opportunity because it will allow you to meet and interact with Hoosier Burger employees. Besides interviewing Bob and Thelma Mellankamp, you decide to collect information from Hoosier Burger’s waiters, cooks, and customers. Mr. Rodriquez suggests that you formally interview Bob and Thelma Mellankamp and perhaps observe them performing their daily management tasks. You decide that the best way to collect requirements from the waiters and cooks is to interview and observe them. You realize that discussing the order-taking process with Hoosier Burger employees and then observing them in action will provide you with a better idea of where potential system improvements can be made. You also decide to prepare a questionnaire to distribute to Hoosier Burger customers. Because Hoosier Burger has a large customer base, it would be impossible to…arrow_forwardOmar has recently been hired as the HIM director at a large medical center. He realizes that he has a number of employees whose job duties would allow them to work from home. Because his boss has asked him for a space reduction proposal, he recognizes the need to implement a work-at-home program for his employees. What steps should Omar take in developing a security program for the employees who will work from home? Develop a checklist of considerations, along with a list of resources that would facilitate his security program.arrow_forward
- Please help me solve the following A contractor requests the execution of a project. The activities and resource estimation are summarized in the following table. The duration in days. Determine: A) Probability of completing the project at the end of 115 days B) The probability of completing the project if you are granted 15 days Additional Activity A B 8C D E F G H I J K Precedence to Tmtp 26 28 39 18 20 34 3 4 10 22 24 33 6 8 14 10 12 20 16 20 32 8 10 25 3 4 10 28 30 45 8 10 22 -- B A A C,D E E F,G F,G,H I,Jarrow_forwardExample: Undertaking by a contractor to implement a contracting for excavation works according to the scheme below, undertaking to complete the work within a period of 36 weeks with a probability of 99% between in light of the contractor's probability. The actual time period for the completion of the project within the PERT technology? Act. a b te u C.P 1-2 7 8. 6.33 1 1 *1,2 2-3 6. 9 6.33 0.66 0.443 *2 2-4 3 7 8. 6.5 0.83 .693 *1 2-5 4 6. 0.33 3-6 9. 10 8.66 0.66 0.443 *2 4-7 6. 8 11 8.166 0.83 .693 *1 5-7 4 7 5.83 0.5 6-8 7 10 7.16 0.83 .693 *2 7-8 4 8 7.5 0.83 .693 *1 8-9 4 7 9 6.83 0.83 .693 *1,2arrow_forwardAssuming that you are a project manager for a consulting firm that is planning a feasibility study for a new city centre scheme. The activities for the final phase of the study project have been identified. The logical relationships for the identified activities is as shown in the dependency table below. Table 3.2: Activities for the Final Phase of a Feasibility Study Activity Immediate /predecessor (s) Duration (weeks) No. of Staff Needed A 3 B 5 3 C 4 B D A 7 2 E B.C 8 2 F C 6 5 G EF B 3 H F 10 B D.G 6 5 Table 3.2: Dependency Table Based on the information provided in the table: i. Draw and analyze the network diagram; and ii. Indicate the type of dependency relationships.arrow_forward
- Project planners have sought the judgment of various knowledgeable engineers, vendors and foremen and have developed the time estimates for the plant construction project as shown in the table below. Activity Estimates Predecess Time (months) or Description Code A a 9 Design plant Select Site Select Personnel 11 8 None 16 B A 2 35 C A 1 4 5 Select Vendor D A 3 4 9. Project site Manufacture generator Prepare manual Install generator Train operators License E 12 20 F 15 18 28 8 E,F D,G 2 4 8 5 8 12 J H,I 5 14 a. Construct the PERT network for the project. b. Find the critical path and its standard deviation. c. Determine the slack time of all activities of the project.arrow_forwardJamison Day Consul tants has been entrusted with thetask of evaluating a business plan that has been divided into foursections- marketing, finance, operations, and human resources.Chris, Steve, Juana, and Rebecca form the evaluation team. Each of them has expertise in a certain field and tends to finish thatsection faster. The estimated times taken by each team memberfor each section have been outlined in the following table. Furtherinformation states that each of these individuals is paid $60/hour.a) Assign each member to a different section such that JamisonConsultants's overall cost is minimized.b) What is the total cost of these assignments?arrow_forwardRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. a) What is the expected (estimated) time for activity C?b) What is the variance for activity C?c) Based on the calculation of estimated times, what is the criticalpath?d) What is the estimated time of the critical path?e) What is the activity variance along the critical path?f) What is the probability of completion of the project before week 36?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.