Explanation of Solution
Difference between resource loading and resource leveling:
Resource loading | Resource levelling |
Resource loading is the amount of individual resources an existing schedule requires for a specific time period. | Resource leveling is a technique used for solving the resource conflicts by delaying tasks. |
Resource loading helps the project manager to develop a general understanding of the demands a project will make the organization's resources, and individual resources be well scheduled. | The main use of resource leveling is to have a good distribution of resource usage... |
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Find the five essential factors that need to be considered when formulating a
policy for the scheduling of processes, and list them below.
Can you explain the connection between task information and dependencies?
There are several different types of resource record. Which resource record do you think is most important and why?
Chapter 9 Solutions
Information Technology Project Management
Knowledge Booster
Similar questions
- Code using PThreads semaphore API to do the following: a) Create a semaphore sem with the initial value of 1. Do error checking to make sure the semaphore was created successfully. b) Use sem to protect a critical section that contains the statement a = a + 1; c) Resource clean up.arrow_forwardIs the following statement true or false AND explain your answer, which supports the false, or true ? When a set of real-time tasks scheduled as RMA AND share critical resources using the PCP resource management, it is possible that a task may be denied access to a critical resource even when the resource is not used or required by another task.arrow_forwardExplain the differences between slipstream upgrades, patches, releases, and versions as they pertain to system upkeep.arrow_forward
- Q) Analyze the change control process to be applied as part of software configuration management? first explain what is change control activity? if you are going to do a project and you have been assigned the role of a configuration manager, how are you going to control the changes? what procedures you will be proposing for change control? how the customer is going to propose a change? any procedure to be followedhow the team is going to approve /reject the change request? any procedure to be followedarrow_forwardonline Application Design in ppt The main "point" that has to be made with application design is that application design can be a performance issue. That is right, the way that your front-end and back-end interact can change how good the efficiency of your system is the biggest thing is that we need to make sure that our front end has spaces for each one of these fields. the front end is the way your user interacts with your database....period. If there isn't a screen to enter grades, then that student is not going to be entering a grade. On the flip side, you can't see that your system is going to generate a schedule for a student and not have the fields in the back end, it just doesn't work. Thinking about an application is very much an HCI (human computer interaction) way of thinking. Make sure you include a "clean" page of the screen you are designing as well as a "marked up" version that shows which field the text field (or other thing) is related to as well as a description…arrow_forwardAt Riverside Financial, where you work as a project manager, you have been asked to conduct user training sessions during the implementation phase for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): First, you need to send an e-mail message to all department managers announcing the training sessions (3 days). After the e-mail message goes out, two tasks can begin at the same time: You can develop the training material (7 days) and confirm arrangements for the training facility you plan to use (15 days). As soon as the training material is complete, you can work on two tasks at once: Arrange to have copies of handout material printed (7 days) and develop a set of PowerPoint slides (8 days). When the PowerPoint slides are ready, you conduct a practice training session with the instructor who will assist you (3 days). Finally, when the practice session is over, the handout material is ready, and…arrow_forward
- Select from the following four choices all that apply. The reason a Configuration Items List could be useful, because.... With each distribution of the list, you are able to recognize, if an important item was added or deleted It documents your decision, which items are controlled and which items are not controlled It gives you the key information about which versions are the latest Forget about version numbers for a minute. What is most important that CI list documents everything you need to deliver. Without such a list, I am sure, something is bound to be missed.arrow_forward5. Describe the resources automatically set up for new users. Next, summarize how you would modify each of the resources you listed.arrow_forwardDefine the response time for each task in the selected set of tasks.arrow_forward
- Give some examples of how software designed specifically for managing projects might help with scheduling. In answer to my question, could you please explain it to me?arrow_forwardThere are several different types of resource record. Which resource record do you think is most important and why? What would fail if that resource record was incorrect?arrow_forwarddraw state diagram that describes the system functionality dynamic management of resources if ? example high request database sizearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781305627482Author:Carlos Coronel, Steven MorrisPublisher:Cengage LearningFundamentals of Information SystemsComputer ScienceISBN:9781305082168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning