Question
Book Icon
Chapter 9, Problem 40AP
Summary Introduction

Interpretation: The sequence of the work which is required for the minimization of the total time required for all six clients is to be determined.

Concept Introduction:

Tardiness is used to calculate the difference between the actual completion time and the required due date of the job. Any tardy jobs get completed after the due date of the job.

Blurred answer
Students have asked these similar questions
An independent accountant is planning to prepare tax returns for six of her clients.Prior to her actually preparing each return, her secretary checks the client’s file to besure all the necessary documentation is there and obtains all the tax forms needed forthe preparation of the return. Based on past experience with the clients, her secretaryestimates that the following times (in hours) are required for preparation of the returnand for the accountant to complete the necessary paperwork prior to filing each return:Client Secretary Time Accountant Time1 1.2 2.52 1.6 4.53 2.0 2.04 1.5 6.05 3.1 5.06 0.5 1.5In what order should the work be completed in order to minimize the total timerequired for all six clients?
Opening and closing the office involves a set of procedures that are crucial to the management of the office including financial tasks such as balancing the cash drawer, tidying the reception areas, preparing for the day, starting up the computers and equipment, and at the close of the day, repeating some of these same tasks and securing the premises at the close of business. Of these duties, please describe daily financial management of the ambulatory medical office outlining the tasks completed at the opening and at the closing the office.
A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. Activity Time (minutes) A. Property survey 24 B. Credit report 19 C. Title search 18 D. Final decision 20 The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. Under this setting, what would be the maximum number of loan applications the office can process per day? Numbers only, keep three decimals if not exact, either round up or down is ok
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,