Question
Book Icon
Chapter 7, Problem 32P

a

Summary Introduction

Interpretation:

Expected completion time of project.

Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

a

Expert Solution
Check Mark

Explanation of Solution

Calculate the estimated task time:

    TaskImmediate predecessorsOptimistic timeMost likely timePessimistic timeEstimated task timeVariance
    ANone12320.11
    BA24640.44
    CNone24640.44
    DB and C12931.78

Calculate the estimated task time for task A:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskA=Optimistic+(4×Mostlikely)+Pessimistic6=1hour+(4×2hours)+3hour6=12hours6=2hours

Hence, the estimated task time for task A is 2 hours.

Calculate the estimated task time for task B:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskB=Optimistic+(4×Mostlikely)+Pessimistic6=2hour+(4×4hours)+6hour6=24hours6=4hours

Hence, the estimated task time for task B is 4 hours.

Calculation of estimated task time for Task C:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskC=Optimistic+(4×Mostlikely)+Pessimistic6=2hour+(4×4hours)+6hour6=24hours6=4 hours

Hence, the estimated task time for Task C is 4 hours.

Calculate the estimated task time for Task D:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskD=Optimistic+(4×Mostlikely)+Pessimistic6=1hour+(4×2hours)+9hours6=18hours6=3hours

Hence, the estimated task time for task D is 3 hours.

Calculate the variance for Task A:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskA=(PessimisticOptimistic6)2

  VarianceofTaskA=(3hour1hour6)2=(2hour6)2=0.11

Calculate the variance for Task B:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskB=(PessimisticOptimistic6)2

  VarianceofTaskD=(6hour2hour6)2=(4hour6)2=0.44

Hence, the variance for task B is 0.44

Calculate the variance for Task C:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskD=(6hour2hour6)2=(4hour6)2=0.44

Hence, the variance for Task C is 0.44

Calculate the variance for Task D:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskD=(PessimisticOptimistic6)2

  VarianceofTaskD=(9hour1hour6)2=(8hour6)2=1.78

Hence, the variance for Task D is 1.78

Project network diagram for given information:

The below image shows the project network with the early start, early finish, late start and late finish:

  Practical Operations Management, Chapter 7, Problem 32P

A

The critical path in the project network:

The paths in the given project network are as follows:

A-B-D

C-D

There are two paths in the project network.

Out of the above-mentioned path, the path has the equal early start and late start at the same time early finish and late finish are the critical path.

Hence, the critical path is A-B-D and the project completion time is 9 days.

b

Summary Introduction

Interpretation:

Time duration in the beginning of reconfiguration.

Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.

b

Expert Solution
Check Mark

Explanation of Solution

The late start time for activity C:

According to the project network, the late start time for activity C is 2 day.

c

Summary Introduction

Interpretation:

Probability that warehouse will finish the project.

Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.

c

Expert Solution
Check Mark

Explanation of Solution

The probability to finish the operation, which started at 1:00 a.m. and finished at 11:00 a.m. on the same day:

The value of Z should be calculated to find the probability to find the operation.

It is calculated by dividing the value attained by subtracting the completion time from the time (time gap from 1:00 a.m. to 11:00 a.m.) with the square root of the variance of critical path (sum of the variance of critical path).

  Z=Time-CompletiontimeVarianceofcriticalpath

  Z=10hour-9hour0.11+0.44+1.78=1hour2.33=0.6551

Hence, the value of Z is 0.6551

For Z= 0.6551, the normal distribution table value is 0.7422. Thus, the probability is 74%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Make a list of the tasks that is necessary to build a duplex house (around 3000 sft) for you. Develop a table showing each task, its duration, preceding event(s), and expected duration. Develop a Network diagram for these tasks.  Highlight the critical path on your Network diagram and find out slack of all activities.
Draw the PDM network diagram for the following project, calculate the earliest and latest starting and finishing times for all activities, and hence calculate the total float, free float for each activity.   Activity IPA Duration (WEEKS) WORKERS REQUIRED PER WEEK EQUIPMENT REQUIRED (hrs/WEEK) H ---- 10 5 8 I H 8 4 2 J H 6 8 6 K J 4 2 1 L J 2 6 2 M J 4 3 2 N I 4 2 0 O I 5 5 0 P I, J 5 6 6 Q L 5 2 0 R M 5 0 4 S N 3 0 4 T Q 3 0 0 U O, S 1 9 8 V K, R 5 14 8 W U 2 6 8 X V 3 6 8 Y P,W,X,T 8 14 8 Z Y 6 5 8   If there is a limit of 15 workers per week, smooth the workers loading using ES and LS histogram. Based on the proposed scheduling, plot the equipment loading histogram for the project. Independently of the above resource leveling, schedule the…
We are the project manager for an IT project in our company. We identified the following top-level project tasks and estimated durations to standup a small test lab for the project: Identify test lab building/space requirements and possible locations(8days) Select best location for lab (1day) Once the best location is selected, immediately start the next two tasks: Prepare lab space with power and cabling (3days) Identify/procure required specialized test lab hardware/software(5) Once the lab space is prepared, install/check out available infrastructure hardware/software(1day). Once the specialized software/hardware is received and the infrastructure hardware/software is installed/checked out, install/checkout specialized software/hardware (2days) Once all tasks are completed, conduct the final inspection (1 day). Let's create a PERT/CPM chart for this project and identify the overall project duration and critical path.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY