Introduction To Managerial Accounting
Introduction To Managerial Accounting
8th Edition
ISBN: 9781259917066
Author: BREWER, Peter C., Garrison, Ray H., Noreen, Eric W.
Publisher: Mcgraw-hill Education,
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 4, Problem 17P

Contrast Activity-Based Costing and Conventional Product Costing L04−
2, L04−3. L04−4
Puet World, Inc., Manufactures two models of television sets, the N 800 XL model and the N 500 model.
Data regarding the two products follow:
Chapter 4, Problem 17P, Contrast Activity-Based Costing and Conventional Product Costing L04 2, L043. L044 Puet World, Inc., , example  1
Additional information about the company follows:
a. Model N 800 XL requires $75 in direct materials per unit, and Model N 500 requires $25.
b. The direct labor wage rate is $18 per hour.
c. The company has always used direct labor-hours as the base for applying manufacturing overhead cost to products.
d. Model N 800 XL is more complex to manufacture than Model N 500 and requires the use of special equipment. Consequently, the company is considering the use of activity-basedcosting to assign manufacturing overhead cost to products. Three activity cost pools havebeen identified as follows:
Chapter 4, Problem 17P, Contrast Activity-Based Costing and Conventional Product Costing L04 2, L043. L044 Puet World, Inc., , example  2
Required:
1. Assume that the company continues to use direct labor-hours as the base for applying overhead cost to products.
a. Compute the predetermined overhead rate.
b. Compute the unit product cost of each model.
2. Assume that the company decides to use activity-based costing to assign manufacturing overhead costto products.
a. Compute the activity rate for each activity cost pool and determine the amount of overhead costthat would be assigned to each model using the activity-based costing system.
b. Compute the unit product cost of each model.
3. Explain why manufacturing overhead cost shifts from Model N 500 to Model N 800 XL underactivity-based costing.

1

Expert Solution
Check Mark
To determine

Predetermined overhead rate

It is a rate that a company determines to allocate its total manufacturing overhead cost to products manufactured. This rate uses estimated amount of cost and hours for its calculation.

Unit product cost

Unit product cost represents the total costincurred by a company to produce one unit. It can be calculated by the division of total cost and total number of units manufactured or by adding per unit direct material cost, per unit direct labor cost and per unit overhead cost.

To calculate: Predetermined overhead rate and unit product cost by using the predetermined overhead rate.

Answer to Problem 17P

Predetermined overhead rate is $85 per DLH.

Unit product cost for model N 800 XL is $384 and for model N 500 is $128.

Explanation of Solution

Part a

Predetermined overhead rate is calculated as:

  Predetermined overhead rate = Estimated manufacturing ovreheadsDirect labor hours 

Here, total manufacturing cost is given as $1,785,000 and total direct labor hours are 21,000. So, the predetermined rate will be calculated as:

  Predetermined overhead rate = Estimated manufacturing ovreheadsDirect labor hours                                               = $1,785,00021,000                                              = $85 per DLH

Therefore, predetermined overhead rate is $85 per direct labor hour.

Part b

Unit product cost will be calculated by adding per unit cost of direct material, labor and overheads.

So, unit product cost will be calculated as follows:

    ParticularsModel N 800 XL (in $)Model N 500 (in $)
    Direct material (per unit)7525
    Direct labor (per unit)54 (18*3)18 (18*1)
    Manufacturing overheads (per unit)255 (85*3)85 (85*1)
    Unit product cost 384128

Therefore, unit product cost for Model N 800 XL is $384 and unit product cost for Model N 500 is $128.

2

Expert Solution
Check Mark
To determine

Activity rates

Activity rates are used in the ABC system, these rates help in allocating manufacturing cost to products and are calculated by dividing estimated manufacturing cost of each cost poolby total estimated activity.

Manufacturing overhead

It includes all the costs that are indirectly related to a product and does not include costs related to direct materials and direct labors.

To compute: Activity cost rates for the pools, manufacturing cost that will be assigned to each model and unit product cost for each model.

Answer to Problem 17P

Activity rates are:

    Machine setups$1200 per setup
    Special processing $10 per MH
    General factory $60 per DLH

Overhead cost that will be allocated to model N 800 XL is $825,000 and cost that will be assigned to model N 500 is $960,000.

Unit product of model N 800 XL is $404 and of model N 500 is 123.

Explanation of Solution

Part a

Activity rates will be calculated as follows:

    Cost poolsActivity measureEstimated overhead cost (in $) (A)Estimated activity (B)Activity rates (A/B) (in $)
    Machine setups Number of setups 360,0003001200 per setup
    Special processingMachine hours165,00016,50010 per MH
    General factory Direct labor hours 1,260,00021,00060 per DLH

So, activity rate for machine setups is $1200 per setup, for special processing is $10 per machine hour and for general factory is $60 per DLH.

In the ABC system, allocation of manufacturing overhead costs to all the products is done according to the ratio in which products use different activities. That ratio will be calculated as:

    ParticularsModel N 800 XLModel N 500RatioN 800 XL: N 500
    Machine setups (setups)1002001:2
    Special processing (MHs)16:500016,500:0
    General factory (DLHs)9,00012,0009:12 or 3:4

Now, allocation of overhead cost will be done as follows:

    Activity cost poolOverhead expense(in $)Ratio Model N 800 XL (in $)Model N 500 (in $)
    Machine setups360,0001:2120,000240,000
    Special processing 165,00016,500:0165,0000
    General factory 1,260,0003:4540,000720,000
    Total overhead cost 825,000960,000

So, total overhead cost that will be allocated to model N 800 XL is $825,000 and overhead cost that will be allocated to model N 500 is $960,000.

Part b

Unit product cost will be calculated by adding per unit cost of direct material, labor and overheads. Here, per unit cost of direct material and labor is given. Per unit cost of manufacturing overheads will be calculated as follows:

    ParticularsModel N 800 XLModel N 500
    Total manufacturing overhead cost 825,000960,000
    Total units 3,00012,000
    Manufacturing cost per unit $275$80

Now, Unit product cost will be calculated as follows:

    ParticularsModel N 800 XL (in $)Model N 500 (in $)
    Direct material (per unit)7525
    Direct labor (per unit)54 (18*3)18 (18*1)
    Manufacturing overheads 27580
    Unit product cost 404123

Unit product cost for model N 800 XL is $404 and model N 500 is $123.

4

Expert Solution
Check Mark
To determine

Activity based costing

ABC system is used in cost accounting, this system identifies certain activities, build a relationship among product, activities and cost and assign manufacturing cost to all the products accordingly. Manufacturing cost are first assigned to activities and then to products.

To explain: Under ABC system, why manufacturing costs shift from model N 500 to model N 800 Xl.

Explanation of Solution

ABC system identifies certain activities, assign costs first to activities and then to products. In this system, manufacturing costs are assigned to products in the ratio in which each product consumes the activity. Machine setups are used by models N 800 Xl and Model N 500 in the ratio 1:2, therefore, total overhead cost is allocated in this ratio only. General factory activity is used in the ratio 3:4, therefore, total overhead cost is allocated in 3:4 ratio only and it is given that special processing activity is not used by model N 500 (used by model N 800 XL only), therefore, this cost is only allocated to model N 800 Xl and no amount is transferred to model N 500.

Manufacturing overhead cost is allocated based on consumption ratio and then per unit manufacturing overhead cost is calculated by dividing the total cost by the total number of units.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Moistner, Inc., manufactures and sells two products: Product E6 and Product W9. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:     Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product E6 700 7.0 4,900 Product W9 100 5.0 500 Total direct labor-hours     5,400     The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:       Estimated Expected Activity Activity Cost Pools Activity Measures Overhead Cost Product E6 Product W9 Total Labor-related DLHs $ 233,604 4,900 500 5,400 Machine setups setups   30,942 500 400 900 Order size MHs   712,045 4,200 4,300 8,500     $ 976,591           If the company allocates all of its overhead based on direct labor-hours using its traditional costing method, the overhead assigned to each unit of…
SIM Power Ltd., manufactures and sells two products: Product K1 and Product S6. Data concerning the expected production of each product and the expected total direct labour-hours (DLHs) required to produce that output appear below:    Expected Production Direct Labour-Hours Per Unit Total DirectLabour-Hours Product K1 500 8.0 4,000 Product S6 100 5.0   500 Total direct labour-hours      4,500  The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:       Estimated Expected Activity  Activity Cost Pools Activity Measures  Overhead Cost Product K1 Product S6 Total Labour-related    DLHs  $127,485 4,000 500 4,500 Production orders            orders  27,820 400 600 1,000 General factory            MHs 452,868 4,000 3,800 7,800     $608,173        The total overhead cost assigned to of Product S6 under activity-based costing is closest to: Question 11 options:…
Windhoek Manufacturers produces two products, Amber and Black. The following cost estimates have been prepared using the traditional absorption costing approach. Selling price per unit Production costs per unit: Material costs Direct labour costs Manufacturing overhead cost Profit per unit Additional information. Estimates sales demand Machine hours per unit Required 1.1 1.2 Amber N$ Amber 69 27 6 12 24 9 000 0.75 Calculate the return per machine hour for each product if through put accounting approach is used. Calculate the profit for the period, using a throughput accounting approach, assuming the company priorities Black Black N$ Black 93 24 15 18 36 12 000 1.20 TIOLE.(

Chapter 4 Solutions

Introduction To Managerial Accounting

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Cost Accounting - Definition, Purpose, Types, How it Works?; Author: WallStreetMojo;https://www.youtube.com/watch?v=AwrwUf8vYEY;License: Standard YouTube License, CC-BY