Capital expenditures budget

On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016-2019. The following interviews helped the controller collect the necessary information for the capital expenditures budget:

Director of Facilities: A construction contract was signed in late 2015 for the construction of a new factory building at a contract cost of $10,000,000. The construction is scheduled to begin in 2016 and be completed in 2017.

Vice President of Manufacturing Once the new factory budding is finished, we plan to purchase $1.5 million in equipment in late 2017.1 expect that an additional 5200.000 will be needed early in the following year (20181 to test and install the equipment before we can begin production If sates continue to grow. I expect we'll need to invest another $1,000,000 in equipment in 2019.

Chief Operating Officer: We have really been growing lately I wouldn't be surprised if we need to expand the size of our new factory building m 2019 by at least 35%. Fortunately, we expect inflation to have minimal impact on construction costs over the next four years. Additionally, I would expect the cost of the expansion to be proportional to the size of the expansion

Director of Information Systems: We need to upgrade our information systems to wireless network technology. It doesn't make sense to do this until after the new factory building is completed and producing product. During 2018, once the factory is up and running, we should equip the whole facility with wireless technology. I think it would cost us $800,000 today to install the technology. However, prices have been dropping by 25% per year, so it should be less expensive at a later date.

Chief Financial Officer: I am excited about our long-term prospects. My only short-term concern is managing our cash flow while we expend the $4,000,000 of construction costs on the portion of the new factory building scheduled to be completed in 2016.

Use this interview information to prepare a capital expenditures budget for Omicron Inc. for the years 2016-2019.

Blurred answer
Students have asked these similar questions
< On August 1, 20Y4, the controller of Handy Dan Tools Inc. is planning capital expenditures for the years 2015-20Y8. The controller interviewed several Handy Dan executives to collect the necessary information for the capital expenditures budget. Excerpts of the interviews are as follows: Director of Facilities: A construction contract was signed in May 20Y4 for the construction of a new factory building at a contract cost of $11,500,000. The construction is scheduled to begin in 20Y5 and completed in 20Y6. Vice President of Manufacturing: Once the new factory building is finished, we plan to purchase $5.8 million in equipment in late 20Y6. I expect that an additional $870,000 will be needed early in the following year (20Y7) to test and install the equipment before we can begin production. If sales continue to grow, I expect we'll need to invest another 500,000 in equipment in 20Y8. Vice President of Marketing: We have really been growing lately. I wouldn't be surprised if we need to…
On January 1, 20Y6, the controller of Omicron Inc. is planning capital expenditures for the years 20Y6–20Y9. The following interviews helped the controller collect the necessary information for the capital expenditures budget:Director of Facilities: A construction contract was signed in late 20Y5 for the construction of a new factory building at a contract cost of $10,000,000. The construction is scheduled to begin in 20Y6 and be completed in 20Y9.Vice President of Manufacturing: Once the new factory building is finished, we plan to purchase $1.5 million in equipment in late 20Y7. I expect that an additional $200,000 will be needed early in the following year (20Y8) to test and install the equipment before we can begin production. If sales continue to grow, I expect we’ll need to invest another $1,000,000 in equipment in 20Y9.Chief Operating Officer: We have really been growing lately. I wouldn’t be surprised if we need to expand the size of our new factory building in 20Y9 by at…
On January 1, 20Y2, the controller of Omicron Inc. is planning capital expenditures for the years 20Y2-20Y5. The following interviews helped the controller collect the necessary information for the capital expenditures budget: Director of Facilities: A construction contract was signed in late 20Y1 for the construction of a new factory building at a contract cost of $10,000,000. The construction is scheduled to begin in 20Y2 and be completed in 20Y3. Vice President of Manufacturing: Once the new factory building is finished, we plan to purchase $1.5 million in equipment in late 2OY3. I expect that an additional $200,000 will be needed early in the following year (20Y4) to test and install the equipment before we can begin production. If sales continue to grow, I expect we'll need to invest another $1,000,000 in equipment in 20Y5. Chief Operating Officer: We have really been growing lately. I wouldn't be surprised if we need to expand the size of our new factory building in 20Y5 by at…

Chapter 21 Solutions

Financial & Managerial Accounting

Ch. 21 - Flexible budgeting At the beginning of the period,...Ch. 21 - Prob. 21.1BPECh. 21 - Prob. 21.2APECh. 21 - Prob. 21.2BPECh. 21 - Direct materials purchases budget My Life...Ch. 21 - Prob. 21.3BPECh. 21 - Direct labor cost budget MyLife Chronicles Inc....Ch. 21 - Prob. 21.4BPECh. 21 - Prob. 21.5APECh. 21 - Prob. 21.5BPECh. 21 - Prob. 21.6APECh. 21 - Prob. 21.6BPECh. 21 - Personal budget At the beginning of the 2016...Ch. 21 - Flexible budget for selling and administrative...Ch. 21 - Static budget versus flexible budget The...Ch. 21 - Prob. 21.4EXCh. 21 - Prob. 21.5EXCh. 21 - Prob. 21.6EXCh. 21 - Prob. 21.7EXCh. 21 - Prob. 21.8EXCh. 21 - Direct materials purchases budget Romano's Frozen...Ch. 21 - Prob. 21.10EXCh. 21 - Prob. 21.11EXCh. 21 - Direct labor cost budget Ace Racket Company...Ch. 21 - Prob. 21.13EXCh. 21 - Production and direct labor cost budgets Levi...Ch. 21 - Prob. 21.15EXCh. 21 - Cost of goods sold budget Delaware Chemical...Ch. 21 - Cost of goods sold budget The controller of...Ch. 21 - Schedule of cash collections of accounts...Ch. 21 - Schedule of cash collections of accounts...Ch. 21 - Schedule of cash payments for a service company...Ch. 21 - Schedule of cash payments for a service company...Ch. 21 - Capital expenditures budget On January 1, 2016,...Ch. 21 - Forecast sales volume and sales budget For 2016,...Ch. 21 - Sales, production, direct materials purchases, and...Ch. 21 - Budgeted income statement and supporting budgets...Ch. 21 - Cash budget The controller of Sonoma Housewares...Ch. 21 - Budgeted income statement and balance sheet As a...Ch. 21 - Prob. 21.1BPRCh. 21 - Sales, production, direct materials purchases, and...Ch. 21 - Budgeted income statement and supporting budgets...Ch. 21 - Cash budget The controller of Mercury Shoes Inc....Ch. 21 - Prob. 21.5BPRCh. 21 - Prob. 21.1CPCh. 21 - Prob. 21.2CPCh. 21 - Static budget for a service company A bank manager...Ch. 21 - Objectives of the master budget Dominos Pizza LLC....Ch. 21 - Integrity and evaluating budgeting systems The...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Responsibility Accounting| Responsibility Centers and Segments| US CMA Part 1| US CMA course; Master Budget and Responsibility Accounting-Intro to Managerial Accounting- Su. 2013-Prof. Gershberg; Author: Mera Skill; Rutgers Accounting Web;https://www.youtube.com/watch?v=SYQ4u1BP24g;License: Standard YouTube License, CC-BY