Cornerstones of Cost Management (Cornerstones Series)
Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN: 9781305970663
Author: Don R. Hansen, Maryanne M. Mowen
Publisher: Cengage Learning
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 20, Problem 30P

Bountiful Manufacturing produces two types of bike frames (Frame X and Frame Y). Frame X passes through four processes: cutting, welding, polishing, and painting. Frame Y uses three of the same processes: cutting, welding, and painting. Each of the four processes employs 10 workers who work eight hours each day. Frame X sells for $40 per unit, and Frame Y sells for $55 per unit. Materials is the only unit-level variable expense. The materials cost for Frame X is $20 per unit, and the materials cost for Frame Y is $25 per unit. Bountiful’s accounting system has provided the following additional information about its operations and products:

Chapter 20, Problem 30P, Bountiful Manufacturing produces two types of bike frames (Frame X and Frame Y). Frame X passes

Bountiful’s management has determined that any production interruptions can be corrected within two days.

Required:

  1. 1. Assuming that Bountiful can meet daily market demand, compute the potential daily profit. Now, compute the minutes needed for each process to meet the daily market demand. Can Bountiful meet daily market demand? If not, where is the bottleneck? Can you derive an optimal mix without using a graphical solution? If so, explain how.
  2. 2. Identify the objective function and the constraints. Then, graph the constraints facing Bountiful. Determine the optimal mix and the maximum daily contribution margin (throughput).
  3. 3. Explain how a drum-buffer-rope system would work for Bountiful.
  4. 4. Suppose that the Engineering Department has proposed a process design change that will increase the polishing time for Frame X from 15 to 23 minutes per unit and decrease the welding time from 15 minutes to 10 minutes per unit (for Frame X). The cost of process redesign would be $10,000. Evaluate this proposed change. What step in the TOC process does this proposal represent?

1.

Expert Solution
Check Mark
To determine

Ascertain the potential daily profit and calculate the minutes of each process needed to meet the daily market demand. Explain whether Company B could meet the daily market demand and if not state the bottleneck that is placed and derive an optimal mix without using a graphical solution and explain the manner in which it is derived.

Explanation of Solution

Theory of constraint: Making money in the future by managing constraints is the main goal of the theory of constraints. The theory of constraints (TOC) recognizes the performance of origination with constraints volume and it develops a specific approach to focus the system level effects of the continuous improvement.

Ascertain the potential daily profit:

ParticularsFrame XFrame Y
Sales $40$55
Materials2025
Contribution margin per unit (a) $20$30
Market demand (b)200100
Daily profit (a×b)$4,000$3,000
Total potential daily profit$7,000($4,000+$3,000)

Table (1)

Calculate the minutes of each process needed to meet the daily market demand. Explain whether Company B could meet the daily market demand and if not state the bottleneck that is placed and derive an optimal mix without using a graphical solution and explain the manner in which it is derived:

ProcessResource DemandsResource Supply
Cutting:  
For Frame X(15×200=3,000) 
For Frame Y(10×100=1,000) 
 4,0004,800
   
Welding:  
For Frame X(15×200=3,000) 
For Frame Y(30×100=3,000) 
 6,0004,800
Polishing:  
For Frame X(15×200=3,000)4,800
   
Painting:(10×200=2,000) 
 (15×100=1,500) 
 3,5004,800

Table (2)

Company B cannot meet daily demand. Even though all other processes have excess capacity, the welding process has a low capacity and it requires 6,000 minutes however only 4,800 is available. Thus, welding is the bottleneck. The contribution margin per unit of welding resource (minutes) for each product is computed as follows:

For Frame X:

Contibution margin per minutes=Contibution margin per unitusage per unit=$2015=$1.33per minute

For Frame Y:

Contibution margin per minutes=Contibution margin per unitusage per unit=$3030=$1.00per minute

From this calculation it is understood that the company should produce Frame X first. Therefore, out of 4,800 minutes, 3,000 minutes (15×200) of welding will be allocated to Frame X and the remaining 1,800 minutes are used to produce Frame Y, in which it could produce 60 units of Frame Y (1,80030). Therefore, the optimal mix for Frame X is 200 units and for Frame Y is 60 units, and this as a result would produce a daily contribution of $5,800($20×200)+($30×60).

2.

Expert Solution
Check Mark
To determine

Identify the objective function and the constraints and then draw a graph for the constraints. Ascertain the optimal mix and the maximum daily contribution margin (throughput).

Explanation of Solution

Contribution margin: Contribution margin is a measurement of performance where only revenue and variable costs are taken into consideration. Hence, this measurement is useful in the evaluation of the probable outcomes of decisions including pricing decisions and other marketing strategies that affect primarily revenue and variable costs.

Identify the objective function and the constraints and then draw a graph for the constraints. Ascertain the optimal mix and the maximum daily contribution margin (throughput):

Cornerstones of Cost Management (Cornerstones Series), Chapter 20, Problem 30P

Figure (1)

Corner pointXYZ=$20X+$30Y
A00$0
B0100$3,000
C120100$5,400
D20060$5,800
E2000$4,000

Table (3)

Objective function:

Max Z=$20X+$30Y

Subject to:

15X+10Y<4,800 15X+30Y<4,800           15X<4,800 10X+15Y<4,800 

             X<200              Y<100             X>0             Y>0

3.

Expert Solution
Check Mark
To determine

Explain the manner in which a drum-buffer-rope system would work for company B.

Explanation of Solution

The welding process is the drummer in this case and, for the entire plant the drummer sets the production rate. As per the optimal mix, the plant should produce 200 units of Frame X and 60 units of Frame Y each day. In order to ensure that these rates are not exceeded by the cutting process, the release of materials is tied to the maximum production rate of the welding process. Finally, in front of the welding process, a time buffer is set up to protect throughput. Thus, this buffer would contain of 400 cut units of Frame X and 200 cut units of Frame Y for two days.

4.

Expert Solution
Check Mark
To determine

Evaluate the given proposed change and define the steps in the theory of constrains (TOC) process that is represented by the given proposal.

Explanation of Solution

ProcessResource DemandsResource Supply
Cutting:  
For Frame X(15×200=3,000) 
For Frame Y(10×100=1,000) 
 4,0004,800
   
Welding:  
For Frame X(10×200=2,000) 
For Frame Y(30×100=3,000) 
 5,0004,800
Polishing:  
For Frame X(23×200=4,600)4,800
   
Painting:(10×200=2,000) 
 (15×100=1,500) 
 3,5004,800

Table (4)

In this case, the redesigning process would reduce the welding time of Frame X from 3,000 minutes to 2,000 minutes and also it increases the polishing time of Frame X from 3,000 minutes to 4,600 minutes. Thus, this decreases the excess capacity of polishing process as well as releases 1,000 minutes of scarce resource in welding process. Thus these 1,000 minutes of scarce resource could be used to produce an additional 33 units of Frame Y (1,00030), and this as a result would produce a daily contribution margin of $900. To recover the $10,000 needed for redesign, the company would take 10.1 workdays ($10,000$990).

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:     DirectLabor-Hours per Unit AnnualProduction Hubs 0.70 11,000 units Sprockets 0.30 45,000 units     Additional information about the company follows:   Hubs require $25 in direct materials per unit, and Sprockets require $19. The direct labor wage rate is $15 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools:     Estimated Activity Activity Cost Pool (Activity Measure) Overhead Cost Hubs Sprockets Total Machine setups (number of setups) $ 16,200 100 80 180 Special processing (machine-hours) $ 188,000 4,700 0 4,700 General factory (organization-sustaining) $ 196,700 NA NA NA    Determine the unit product cost of each product according to the ABC system.                                  HUBS                               SPROCKETS Direct Materials…
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow: Direct Labor-Hours Annual per unit Production Rims 0.60 26,000 units Posts 0.60 84,000 units Additional information about the company follows: 1. Rims require $17 in direct materials per unit, and Posts require $14. 2. The direct labor wage rate is $20 per hour. 3. Rims are more complex to manufacture than Posts and they require special equipment. 4. The ABC system has the following activity cost pools: 5. Estimated Activity Estimated Overhead Activity Cost Pool Activity Measure Cost Rims Posts Total Machine setups Number of setups $ 39,480 80 320 400 Special processing Machine-hours $ 146,160 3,000 3,000 General factory $ 1,092,000 Direct labor-hours 5,000 73,000 78,000 Compute the activity rate for each activity cost pool. Machine Setups Special Processing General factory per setup per MH per DLH
Atlanta Systems produces two different products, Product A, which sells for $650 per unit, and Product B, which sells for $1,200 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Machining, which uses machine hours as an activity driver; and Inspection, which uses number of batches as an activity driver. The cost of each activity and usage of the activity drivers are as follows: Usage by Product A Usage by Product B Design (Engineering Hours) Machining (Machine Hours) Inspection (Batches) Cost $ 230,000 $2,600,000 $ 240,000 116 134 2,320 2,680 34 46 Atlanta manufactures 12,500 units of Product A and 10,172 units of Product B per month. Each unit of Product A uses $100 of direct materials and $45 of direct labor, while each unit of Product B uses $140 of direct materials and $75 of direct labor. Required: a. Calculate the activity rate for design. Rate for Design per hour b. Calculate the activity rate for machining. Rate for…

Chapter 20 Solutions

Cornerstones of Cost Management (Cornerstones Series)

Ch. 20 - What is a constraint? An internal constraint? An...Ch. 20 - Prob. 12DQCh. 20 - Prob. 13DQCh. 20 - Explain how lowering inventory produces better...Ch. 20 - Prob. 15DQCh. 20 - Thomas Corporation produces heating units. The...Ch. 20 - Sterling Corporation has an EOQ of 5,000 units....Ch. 20 - Patz Company produces two types of machine parts:...Ch. 20 - Prob. 4CECh. 20 - See Cornerstone Exercise 20.4. Fisher Company has...Ch. 20 - Ottis, Inc., uses 640,000 plastic housing units...Ch. 20 - Ottis, Inc., uses 640,000 plastic housing units...Ch. 20 - Melchar Company uses 78,125 pounds of oats each...Ch. 20 - Prob. 9ECh. 20 - Morrison Manufacturing produces casings for sewing...Ch. 20 - Morrison Manufacturing produces casings for sewing...Ch. 20 - Refer to Exercise 20.10. Assume the economic lot...Ch. 20 - Eyring Manufacturing produces a component used in...Ch. 20 - Hales Company produces a product that requires two...Ch. 20 - Many companies have viewed JIT as a panaceaa...Ch. 20 - Prob. 16ECh. 20 - Prob. 17ECh. 20 - Which of the following describes the economic...Ch. 20 - The economic order quantity (EOQ) for Part X15 is...Ch. 20 - A JIT inventory management system maintains which...Ch. 20 - For the theory of constraints, which of the...Ch. 20 - A dedicated pharmaceutical plant uses the theory...Ch. 20 - Prob. 23PCh. 20 - Burnett Company produces two types of gears: Model...Ch. 20 - Taylor Company produces two industrial cleansers...Ch. 20 - Prob. 26PCh. 20 - Calen Company manufactures and sells three...Ch. 20 - Confer Company produces two different metal...Ch. 20 - Pratt Company produces two replacement parts for a...Ch. 20 - Bountiful Manufacturing produces two types of bike...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License