Question
Chapter 2, Problem 46P
a)
To determine
The calculation of cost per square foot.
b)
To determine
The calculation of cost per square foot.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A construction crew (that is currently unemployed and receiving $10/hr. in benefits) to fix a road. The cement is purchased from a rip-off monopolist that charges $10/bag more than anyone else. The Follow-up maintenance will be done after 1 year, using a different crew that we will assume is not unemployed. We will also assume the interest rate is 7%. The cost estimate provided by the contractor’s accountant is given in the table below:
ITEM
Quantity
Wage
Price
Total
Labor
1,000 hours
$20/hour
$20,000
Cement
500
$50
$25,000
Follow up maint.
500
$20/hr
$10,000
Project Total
$55,000
The opportunity cost of the project is
Group of answer choices
$55,000
$41,000
$39,000
$33,000
The total design and construction cost for a sand filter machine to handle a flow rate of 0.7 million
gallons per day (MGD) was $1.9 million in 2010. Estimate the cost today for a flow rate of 2.4 MGD.
The cost index in 2010 of 161 has been updated to 285 for this year.
Component/System/Plant Size Range
Exponent
Activated sludge plant
Aerobic digester
Clarifier
Centrifuge
Sand filter
Heat exchanger
Cyclone separator
1 to 100 MGD
0.2 to 40 MGD
0.1 to 100 MGD
40 to 60 in
0.84
0.14
0.98
0.71
0.14
500 to 3000 ft?
20 to 8000 ft/min
0.55
0.64
Estimate the cost of expanding a planned new clinic by 25,000 ft2. The appropriate capacity exponent is 0.62, and the budget estimate for 185,000 ft2 was $17 million.
Chapter 2 Solutions
ENGR.ECONOMIC ANALYSIS
Ch. 2 - Prob. 1QTCCh. 2 - Prob. 2QTCCh. 2 - Prob. 3QTCCh. 2 - Prob. 4QTCCh. 2 - Prob. 1PCh. 2 - Prob. 2PCh. 2 - Prob. 3PCh. 2 - Prob. 4PCh. 2 - Prob. 5PCh. 2 - Prob. 6P
Ch. 2 - Prob. 7PCh. 2 - Prob. 8PCh. 2 - Prob. 9PCh. 2 - Prob. 10PCh. 2 - Prob. 11PCh. 2 - Prob. 12PCh. 2 - Prob. 13PCh. 2 - Prob. 14PCh. 2 - Prob. 15PCh. 2 - Prob. 16PCh. 2 - Prob. 17PCh. 2 - Prob. 18PCh. 2 - Prob. 19PCh. 2 - Prob. 20PCh. 2 - Prob. 21PCh. 2 - Prob. 22PCh. 2 - Prob. 23PCh. 2 - Prob. 24PCh. 2 - Prob. 25PCh. 2 - Prob. 26PCh. 2 - Prob. 27PCh. 2 - Prob. 28PCh. 2 - Prob. 29PCh. 2 - Prob. 30PCh. 2 - Prob. 31PCh. 2 - Prob. 32PCh. 2 - Prob. 33PCh. 2 - Prob. 34PCh. 2 - Prob. 35PCh. 2 - Prob. 36PCh. 2 - Prob. 37PCh. 2 - Prob. 38PCh. 2 - Prob. 39PCh. 2 - Prob. 40PCh. 2 - Prob. 41PCh. 2 - Prob. 42PCh. 2 - Prob. 43PCh. 2 - Prob. 44PCh. 2 - Prob. 45PCh. 2 - Prob. 46PCh. 2 - Prob. 47PCh. 2 - Prob. 48PCh. 2 - Prob. 49PCh. 2 - Prob. 50PCh. 2 - Prob. 51PCh. 2 - Prob. 52PCh. 2 - Prob. 53PCh. 2 - Prob. 54PCh. 2 - Prob. 55PCh. 2 - Prob. 56PCh. 2 - Prob. 57PCh. 2 - Prob. 58PCh. 2 - Prob. 59PCh. 2 - Prob. 60PCh. 2 - Prob. 61PCh. 2 - Prob. 62PCh. 2 - Prob. 63PCh. 2 - Prob. 64PCh. 2 - Prob. 65PCh. 2 - Prob. 66PCh. 2 - Prob. 67PCh. 2 - Prob. 68PCh. 2 - Prob. 69PCh. 2 - Prob. 70PCh. 2 - Prob. 71PCh. 2 - Prob. 72PCh. 2 - Prob. 73PCh. 2 - Prob. 74PCh. 2 - Prob. 75PCh. 2 - Prob. 76PCh. 2 - Prob. 77PCh. 2 - Prob. 78PCh. 2 - Prob. 79PCh. 2 - Prob. 81P
Knowledge Booster
Similar questions
- Estimate the cost of a 0.75 million gallon per day (MGD) induced-draft packed tower for air-stripping trihalomethanes from drinking water if the cost for a 2.9- MGD tower is $153,200. The exponent in the cost- capacity equation is 0.47. The cost of a 0.75 million gallon per day induced-draft packed tower is $arrow_forwardEstimate the cost of a 0.75 million gallon per day (MGD) induced-draft packed tower for air-stripping trihalomethanes from drinking water if the cost for a 2-MGD tower is $153,200. The exponent in the cost capacity equation is 0.58.arrow_forwardAn architect-engineering firm is planning a parking lot to accommodate 500 vehicles. Each parking space will be 8.5 feet × 15 feet. It has been estimated that the space required for aisles will be 80% of the space required for parking. A local paving company charges $10 per square foot for paving and a flat fee of $12,000 for marking and painting the individual parking spaces. Based on this information, what is the estimated cost of paving and marking this parking lot?arrow_forward
- Oscar has owned a Ford automobile dealership for over 25 years. Since he has been heavily involved in the sales of cars, Oscar believes that there are 3 different types of customers with the following willingness to pays: Sunroof Navigation System Customer A $3,000 $1,200 Customer B $1,800 $600 Customer C $150 $1,800 Although not realistic, assume that incremental costs are $0. As the owner of the dealerships, Oscar has the final say on pricing for each customer. Suppose that Oscar knows the willingness to pay of Customer A, B and C as soon as he meets them. What price should Oscar charge to each customer to maximize profits? What is the total amount of profits for the 3 customers and what is the total amount of consumer surplus for the 3 customers? Show your calculations.arrow_forwardThe equipment cost for removing arsenic from a well that delivers 800 gallons per minute is $1.8 million. If the overall cost factor for this type system is 2.25, what is the total plant cost expected to be?arrow_forwardThe preliminary cost for a 50,000 ft2 aircraft hangar must be estimated. (a) The first unit estimate was $98.23 per square foot. Estimate the cost of the hangar. (b) The budget limit came in at $4 million. Perform two analyses: determine the maximum allowed size to be within budget at the first estimated unit cost, and determine the maximum unit cost to stay within budget and maintain the 50,000 ft2 size.arrow_forward
- The estimated cost for a multitube cyclone system with a capacity of 60,000 cubic feet per minute is $450,000. (a) If the $200,000 actual cost for a 35,000 cubic feet per minute system was used in the cost-capacity equation, what was the value of the exponent? (b) What can be concluded about the economy of scale of the costs between the two systems?arrow_forwardIf the cost of an 8000-operation-per-second assembly line robot is $80,000 and the cost for one with twice the capacity is $120,000, the value of the exponent in the cost-capacity equation is closest to:a. 0.51b. 0.58c. 0.62d. 0.69arrow_forwardA marginal cost fiction C'(q) is given in the figure below. If the fixed costs are $10,000, estimate: a) the total cost to produce 20 units (use left and right hand sums) b) the additional cost if the company increased production from 20 to 40 unitsarrow_forward
- The equipment for applying specialty coatings that provide a high angle of skid for the paperboard and corrugated box industries has a delivered cost of $390,000. If the overall cost factor for the complete system is 3.96, the total plant cost is approximately: (a) $955,500 (b) $1,054,400 (c) $1,154,400 (d) $1,544,400arrow_forwardGH is preparing its maintenance budget for the next period. Based on previous experience it has found that there is a linear relationship between production volume and maintenance costs. The following cost information has been obtained: Production volume (units) Cost £ 1,600 23,200 2,500 25,000 The production cost for a production volume of 2,700 units would be:arrow_forwardA study of 86 savings and loan associations in six northwestern states yielded the following cost function. C = 3.12 - 0.006768Q + 0.000005359Q2 +21.1X1 (3.12) (2.61) (2.89) (2.96) where C = average operating expense ratio, expressed as a percentage and defined as total operating expense ($ million) divided by total assets ($ million) times 100 percent. Q = output; measured by total assets ($ million) X1 = ratio of the number of branches to total assets ($ million) Note: The number in parentheses below each coefficient is its respective t-statistic. Holding constant the effects of bank branching (X1), what is the level of total assets that minimizes the average operating expense ratio? $1,262.92 million $1,558.81 million $631.46 million $460.99 million What is the average operating expense ratio for a savings and loan association with the level of total assets determined in the previous part and 1 branch? 1.17% 3.15% 1.02% 5.63% What is the ratio with 10 branches instead? 5.93% 1.47%…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics: Applications, Strategies an...EconomicsISBN:9781305506381Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. HarrisPublisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics: Applications, Strategies an...
Economics
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:Cengage Learning