Nuttʼs management is very concerned about the cost of overhead on its jobs. When jobs are complete, overhead costs should be between 15% and 20% of total costs. For example, the labor cost on Job 8958 is 25% of total costs, higher than the norm. Open Job 8961 and click the Chart sheet tab. A pie chart appears showing the cost components on that job. Record the labor cost percentage in the space provided. Repeat this for each of the jobs worked on in August.
Did Nutt maintain good cost control on all its jobs? Explain.
Worksheet. During September, Job 8963 required two additional material requisitions to complete the job. Open JOB8963 and modify the
Preview the printout to make sure it will print neatly on one page, and then print the worksheet. Save the completed worksheet as JOBT.
Chart. Open JOB8964 and click the Chart sheet tab. Prepare a bar chart for JOB8964 showing the amount of material, labor, and overhead required to complete the job. Use the Chart Data Table found in rows 42–46 as a basis for preparing the chart. Enter your name somewhere on the chart. Save the file again as J0B8964. Print the chart.
Want to see the full answer?
Check out a sample textbook solutionChapter 17 Solutions
Excel Applications for Accounting Principles
- Please use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: It estimates there will be five orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardPlease use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: Box Springs estimates there will be four orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardJob order cost sheets show the following costs assigned to each job: The company assigns overhead at twice the direct labor cost. What is the total cost for each job?arrow_forward
- Frary Corporation is a building contractor. Frary tracks product costs in its job cost system and uses board feet to apply overhead to jobs. Frary has calculated an overhead rate of $61.52 per board foot and they have recorded the following information for job number E4641: Direct labor hours: 45 Direct labor rate: $17.14 Direct material: $5,784.00 Total board feet: 243 The total cost of job number E4641 is: Select one: A. $20,733.36 B. $6,555.30 C. $5,862.66 D. $9,323.70 E. $21,504.66arrow_forwardIn a factory, a team of six maintenance staff are paid a guaranteed weekly wage. Which of the following is the most appropriate cost classification for their wages? Direct labour cost Indirect labour cost Semi-variable cost Variable overhead costarrow_forwardWhite Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours.At the beginning of the year, the company made the following estimates: Department Cutting FinishingDirect labor-hours . . . . . . . . . . . . . . . . . . . . . . . . . 6,000 30,000Machine-hours . . . . . . . . . . . . . . . . . . . . . . . . . . . .48,000 5,000Total fixed manufacturing overhead cost . . . . .$264,000 $366,000Variable manufacturing overhead per machine-hour . $2.00 —Variable manufacturing overhead per direct labor-hour . . — $4.00 Required:1.…arrow_forward
- In job-order costing, all of the following statements are correct with respect to labor time and cost except: Multiple Choice time tickets are kept by employees showing the amount of work on specific jobs. the job cost sheet for a job will contain all direct labor charges to that particular job. labor cost that can be traced to a job only with a great deal of effort is treated as part of manufacturing overhead. a machine operator performing routine annual maintenance work on a piece of equipment would charge the maintenance time to a specific job.arrow_forwardHager Inc. applies overhead based on direct labor cost using a job-order costing system. The company provided you with the following information: Estimated manufacturing overhead Estimated direct labor cost $42,000 $24,000 $45,500 $24,800 Actual manufacturing overhead Actual direct labor cost How much is the underapplied overhead?arrow_forwardCrow Design, Inc. is a Web site design and consulting firm. The firm uses a job order costing system in which each client is a different job. Crow Design assigns direct labor, licensing costs, and travel costs directly to each job. It allocates indirect costs to jobs based on a predetermined overhead allocation rate, computed as a percentage of direct labor costs. Requirements Compute Crow Design's direct labor rate and its predetermined overhead allocation rate for 2024. 1. 2. Compute the total cost of each job. 3. If Ginger wants to earn profits equal to 25% of service revenue, what fee should she charge each of these two clients? 4. Why does Crow Design assign costs to jobs? Data table Direct labor hours Software licensing costs Travel costs $ Tasty Coop 900 hours Root Chocolates 100 hours 100 0 4,000 $ 8,000 -X - X At the beginning of 2024, managing partner Erica Ginger prepared the following budget estimates: (Click the icon to view the prepared budget.) In November 2024, Crow…arrow_forward
- You Answered Correct Answers Harmony Inc. uses a job-costing system with two direct cost categories (direct materials and direct manufacturing labor) and one manufacturing overhead cost pool. Harmony allocates manufacturing overhead costs using direct labor costs. Harmony provides the following information: Overhead is allocated at $3/direct labor dollar. Question: How much overhead is allocated to jobs during 20X1? Budget for 20X1 Direct Materials Cost Direct Mfng Labor Cost Mfng Overhead Cost $3,120,000 2,900,000 $1,500,000 $4,500,000 Direct Mfng Labor Hours 40,000 4,350,000 (with margin: 0) Actual Results for 20X1 $1,900,000 $1,450,000 $3,355,000 50,000arrow_forwardUsing job order costing in a service company Bluebird Design, Inc. is a Web site design and consulting firm. The firm uses a job order costing system in which each client is a different job. Bluebird Design assigns direct labor, licensing costs, and travel costs directly to each job. It allocates indirect costs to jobs based on a predetermined overhead allocation rate, computed as a percentage of direct labor costs. At the beginning of 2018, managing partner Sally Simone prepared the following budget estimates: In November 2018, Bluebird Design served several clients. Records for two clients appear here: Requirements Compute Bluebird Designs direct labor rate and its predetermined overhead allocation rate for 2018. Compute the total cost of each job. If Simone wants to earn profits equal to 50% of service revenue, what fee should she charge each of these two clients? Why does Bluebird Design assign costs to jobs?arrow_forwardHahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 directlabor-hours, and Job Omega. The job cost sheets for these two jobs are shown below: Required:1. Calculate the plantwide predetermined overhead rate.2. Complete the job cost sheet for Job Alpha.arrow_forward
- Excel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College