Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
bartleby

Concept explainers

Question
Book Icon
Chapter 15, Problem 7P

a)

Summary Introduction

To solve: The given information by using the assignment method.

Introduction: The assignment method is one of the methods available in the process of optimization. Here, the jobs are assigned to every available resource.

a)

Expert Solution
Check Mark

Answer to Problem 7P

The problem has been solved by using the assignment method.

Explanation of Solution

Given information:

Squad Case
A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 8

Assign cases to respective squads:

Row minimum:

Squad Case Row minimum
A B C D E
1 14 7 3 7 27 3
2 20 7 12 6 30 6
3 10 3 4 5 21 3
4 8 12 7 12 21 7
5 13 25 24 26 8 8

Table after the row subtraction is given below:

The row minimum value mentioned in the above table should be subtracted from each value of the row.

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 5 17 16 18 0

Column minimum:

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 5 17 16 18 0
Column minimum 1 0 0 0 0

Table after the column subtraction is given below:

The column minimum value mentioned in the above table should be subtracted from each value of the column.

Squad Case
A B C D E
1 10 4 0 4 24
2 13 1 6 0 24
3 6 0 1 2 18
4 0 5 0 5 14
5 4 17 16 18 0

Assigning squads to the cases:

Step 1: The first row must be checked for the zero. As there is only one zero in the first row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  1

Step 2: As only one zero is available in the second row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  2

Step 3: As only one zero is available in the third row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  3

Step 4: As only one zero is available in the fourth row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  4

Step 5: As only one zero is available in the fourth row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  5

Step 5: All the zeroes in the table have been striked out. The marked zeroes help to assign the cases to the squads.

Calculate the total person-days that are projected by using the assignment method:

The value has been taken in the given information where, the zeroes have been marked in the final answer.

Squad Case Value
1 C 3
2 D 6
3 B 3
4 A 8
5 E 8
Total 28
Conclusion

According to the table, Squad 1 should be assigned to Case C, Squad 2 should be assigned to Case D, Squad 3 should be assigned to Case B, Squad 4 should be assigned to Case A, and Squad 5 should be assigned to Case E. The total person days are 28 days.

b)

Summary Introduction

To solve: The given information by using assignment method.

Introduction: The assignment method is one of the methods available in the process of optimization. Here, the jobs are assigned to every available resource.

b)

Expert Solution
Check Mark

Answer to Problem 7P

The problem has been solved by using the assignment method.

Explanation of Solution

Given information:

Squad Case
A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 8

It is given that the squad 5 cannot work on Case 5 because of the conflict.

Modified given information:

It is given that the squad 5 cannot work on Case 5 because of the conflict. Thus, the value should be modified from 8 to any other higher values. It is taken as 50 here.

Squad Case
A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 50

Assign cases to respective squads:

Row minimum:

Squad Case Row minimum
A B C D E
1 14 7 3 7 27 3
2 20 7 12 6 30 6
3 10 3 4 5 21 3
4 8 12 7 12 21 7
5 13 25 24 26 50 13

Table after the row subtraction is given below:

The row minimum value mentioned in the above table should be subtracted from each value of the row.

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 0 12 11 13 37

Column minimum:

Squad Case
A B C D E
1 11 4 0 4 24
2 14 1 6 0 24
3 7 0 1 2 18
4 1 5 0 5 14
5 0 12 11 13 37
Column minimum 0 0 0 0 14

Table after the column subtraction is given below:

The column minimum value mentioned in the above table should be subtracted from each value of the column.

Squad Case
A B C D E
1 11 4 0 4 10
2 14 1 6 0 10
3 7 0 1 2 4
4 1 5 0 5 0
5 0 12 11 13 23

Assigning squads to the cases:

Step 1: The first row must be checked for the zero. As there is only one zero in the first row, it must be marked and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  6

Step 2: As only one zero is available in the second row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  7

Step 3: As only one zero is available in the third row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  8

Step 4: As only one zero is available in the fourth row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  9

Step 5: As only one zero is available in the fifth row, it must be marked, and the entire column should be striked out.

Principles Of Operations Management, Chapter 15, Problem 7P , additional homework tip  10

Step 5: All the zeroes in the table have been strikedout. The marked zeroes help to assign the cases to the squads.

Calculate the total person days that are projected by using the assignment method:

The value has been taken in the given information where, the zeroes have been marked in the final answer.

Squad Case Value
1 C 3
2 D 6
3 B 3
4 E 21
5 A 13
Total 46
Conclusion

According to the table, Squad 1should be assigned to Case C, Squad 2 should be assigned to Case D, Squad 3 should be assigned to Case B, Squad 4 should be assigned to Case E, and Squad 5 should be assigned to Case A. The total person days are 46 days.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (ii) Illustrate the flow (throughput) times to complete the baking and decorating on atimeline chart.
Question: Consider the following linear program:   Max Z = 2*x + 3*y subject to 3*x + 4*y >= 12 3*x + 2*y >= 9 y>= 1 x,y >= 0    The number of feasible corner points is:   0   1   2   3   None of the other answers are correct.
17.17. The Blue Plate Special restaurant, famous for its slow-cooked stews and meats, serves one meal a day family style. Sous Chef Lisle marinates the meat, fish, and vegetables for the five different dishes on the menu, while Chef Graham handles the cooking. The time required for marinating and cooking can vary, depending on the complexity of the dish and the spiciness desired, as shown below. Assuming only one dish can be marinating and one dish cooking at a time, determine in what order the dishes should be fixed to
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.