Chapter 13, Problem 13.24E
To determine
Concept Introduction:
Direct labor variances:
Direct labor variances refer to the difference between the standard direct labor cost and actual direct labor cost incurred. Direct labor cost variances are categorized into following categories:
- Direct labor Rate variance: this variance shows the difference of standard rate and actual rate of labor. The formula to calculate this variance is as follows:
- Direct labor efficiency variance: this variance shows the difference of standard usage and actual usage of labor. The formula to calculate this variance is as follows:
- Direct labor cost variance: this variance shows the difference of
standard cost and actual cost of labor. The formula to calculate this variance is as follows:
Or
Direct Labor cost variance = Actual Labor cost − Standard Labor Cost
Requirement-1:
To Calculate:
The Direct Labor Rate and Time variances
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Calculating the Variable Overhead Spending and Efficiency Variances
Standish Company manufactures consumer products and provided the following information for the month of February:
Direct Labor Variances
Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are available:
Quantity of direct labor used
Actual rate for direct labor
Bicycles completed in October
Standard direct labor per bicycle
6.0 hrs.
Standard rate for direct labor
$24.00 per hr.
a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct Labor Rate Variance
Direct Labor Time Variance
Total Direct Labor Cost Variance
5,000 hrs.
$22.75 per hr.
800 bicycles
b. How much direct labor should be debited to Work in Process?
Chapter 13 Solutions
Survey of Accounting (Accounting I)
Ch. 13 - Static budgets are often used: A.By production...Ch. 13 - The total estimated sales for the coming year is...Ch. 13 - Dixon Company expects $650,000 of credit sales in...Ch. 13 - The actual and standard direct materials costs for...Ch. 13 - Bower Company produced 4,000 units of product. The...Ch. 13 - Prob. 1CDQCh. 13 - What is the manager’s role in a responsibility...Ch. 13 - Briefly describe the type of human behavior...Ch. 13 - Give an example of budgetary slack.Ch. 13 - What behavioral problems are associated with...
Ch. 13 - Prob. 6CDQCh. 13 - Prob. 7CDQCh. 13 - Under what circumstances would a static budget be...Ch. 13 - How do computerized budgeting systems aid firms in...Ch. 13 - What is the first step in preparing a master...Ch. 13 - Why should the production requirements set forth...Ch. 13 - Why should the timing of direct materials...Ch. 13 - Prob. 13CDQCh. 13 - Prob. 14CDQCh. 13 - Prob. 15CDQCh. 13 - Prob. 16CDQCh. 13 - Prob. 17CDQCh. 13 - Prob. 18CDQCh. 13 - What is meant by reporting by the "principle of...Ch. 13 - Prob. 20CDQCh. 13 - How are standards used in budgetary performance...Ch. 13 - a. What are the two variances between the actual...Ch. 13 - Prob. 23CDQCh. 13 - Prob. 24CDQCh. 13 - Prob. 25CDQCh. 13 - Prob. 26CDQCh. 13 - Flexible budget for selling and administrative...Ch. 13 - Static budget vs. flexible budget The production...Ch. 13 - Flexible budget for Fabrication Department...Ch. 13 - Sales and production budgets Ultimate Audio...Ch. 13 - Professional fees earned budget Day & Spieth,...Ch. 13 - Professional labor cost budget Based on the data...Ch. 13 - Direct materials purchases budget Zippy's Frozen...Ch. 13 - Prob. 13.8ECh. 13 - Prob. 13.9ECh. 13 - Production and direct labor cost budgets Levi...Ch. 13 - Factory overhead cost budget Nutty Candy Company...Ch. 13 - Cost of goods sold budget The controller of Pueblo...Ch. 13 - Prob. 13.13ECh. 13 - Schedule of cash collections of accounts...Ch. 13 - Schedule of cash payments Tadpole Learning Systems...Ch. 13 - Schedule of cash payments Organic Physical Therapy...Ch. 13 - Capital expenditures budget On August 1, 20Y4. the...Ch. 13 - Standard product cost Sorrento Furniture Company...Ch. 13 - Prob. 13.19ECh. 13 - Direct materials variances The following data...Ch. 13 - Standard direct materials cost per unit from...Ch. 13 - Standard product cost, direct materials variance...Ch. 13 - Direct labor variances The following data relate...Ch. 13 - Prob. 13.24ECh. 13 - Direct materials and direct labor variances At the...Ch. 13 - Prob. 13.26ECh. 13 - Factory overhead cost variances The following data...Ch. 13 - Prob. 13.28ECh. 13 - Factory overhead variance corrections The data...Ch. 13 - Prob. 13.30ECh. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Sales, production, direct materials purchases, and...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Prob. 13.2.7PCh. 13 - Budgeted income statement and supporting budgets...Ch. 13 - Cash budget The controller of Shoe Mart Inc. asks...Ch. 13 - Cash budget The controller of Shoe Mart Inc. asks...Ch. 13 - Direct materials and direct labor variance...Ch. 13 - Direct materials and direct labor, variance...Ch. 13 - Prob. 13.6.1PCh. 13 - Prob. 13.6.2PCh. 13 - Prob. 13.6.3PCh. 13 - Prob. 13.6.4PCh. 13 - Prob. 13.6.5PCh. 13 - Standards for nonmanufacturing expenses The...Ch. 13 - Prob. 13.7PCh. 13 - Prob. 13.1.1MBACh. 13 - Prob. 13.1.2MBACh. 13 - Prob. 13.1.3MBACh. 13 - Prob. 13.1.4MBACh. 13 - Prob. 13.1.5MBACh. 13 - Prob. 13.1.6MBACh. 13 - Prob. 13.2.1MBACh. 13 - Prob. 13.2.2MBACh. 13 - Prob. 13.2.3MBACh. 13 - Prob. 13.2.4MBACh. 13 - Process yield Hendrick Motorsports sponsors cars...Ch. 13 - Prob. 13.3.1MBACh. 13 - Prob. 13.3.2MBACh. 13 - Prob. 13.3.3MBACh. 13 - Prob. 13.3.4MBACh. 13 - Prob. 13.4.1MBACh. 13 - Prob. 13.4.2MBACh. 13 - Prob. 13.4.3MBACh. 13 - Prob. 13.4.4MBACh. 13 - Prob. 13.5.1MBACh. 13 - Prob. 13.5.2MBACh. 13 - Prob. 13.5.3MBACh. 13 - Prob. 13.5.4MBACh. 13 - Utilization rate Delta Air Lines (DAL) reported...Ch. 13 - Prob. 13.6.2MBACh. 13 - Prob. 13.6.3MBACh. 13 - Prob. 13.7.1MBACh. 13 - Prob. 13.7.2MBACh. 13 - Prob. 13.7.3MBACh. 13 - Ethics and professional conduct in business The...Ch. 13 - Prob. 13.2.1CCh. 13 - Prob. 13.2.2CCh. 13 - Prob. 13.3.1CCh. 13 - Prob. 13.3.2CCh. 13 - Objectives of the master budget Domino's Pizza LLC...Ch. 13 - Prob. 13.5.1CCh. 13 - Prob. 13.5.2CCh. 13 - Prob. 13.6CCh. 13 - Prob. 13.7C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- ThingOne Company has the following information available for the past year. They use machine hours to allocate overhead. What is the variable overhead efficiency variance?arrow_forwardDirect materials and direct labor variance analysis Lenni Clothing Co. manufactures clothing in a small manufacturing facility. Manufacturing has 25 employees. Each employee presently provides 40 hours of productive labor per week. Information about a production week is as follows: Instructions Determine (A) the standard cost per unit for direct materials and direct labor; (B) the price variance, quantity variance, and total direct materials cost variance; and (C) the rate variance, time variance, and total direct labor cost variance.arrow_forwardStandard direct materials cost per unit from variance data The following data relating to direct materials cost for October of the current year are taken from the records of Good Clean Fun Inc., a manufacturer of organic toys: Determine the standard direct materials cost per unit of finished product, assuming that there was no inventory of work in process at either the beginning or the end of the month.arrow_forward
- Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are available: a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. b. How much direct labor should be debited to Work in Process?arrow_forwardRath Company showed the following information for the year: Required: 1. Calculate the standard direct labor hours for actual production. 2. Calculate the applied variable overhead. 3. Calculate the total variable overhead variance.arrow_forwardRibcos labor cost information for making its only product for March is as follows: A. What is the direct labor rate variance? B. What is the direct labor time variance? C. What is the total direct labor variance?arrow_forward
- Mulliner Company showed the following information for the year: Required: 1. Calculate the standard direct labor hours for actual production. 2. Calculate the applied variable overhead. 3. Calculate the total variable overhead variance.arrow_forwardIncome statement indicating standard cost variances The following data were taken from the records of Griggs Company for December: Prepare an income statement for presentation to management.arrow_forwardComputing materials variances D-List Calendar Co. specializes in manufacturing calendars that depict obscure comedians. The company uses a standard cost system to control its costs. During one month of operations, the direct materials costs and the quantities of paper used showed the following: Calculate the following: 1. Total cost of purchases for the month 2. Materials purchase price variance 3. Materials quantity variance 4. Net materials variancearrow_forward
- Kamen Manufacturing Co. estimates the following labor and overhead costs for the period: Required: Use the four-variance method for overhead analysis. Calculate the variances for direct labor and overhead. Prove that the overhead variances equal over- or underapplied factory overhead for the period.arrow_forwardPower Co.s labor information for June is as follows: A. What was the actual labor rate per hour? B. What was the standard labor rate per hour? C. What was the total standard labor cost for units produced in June? D. What was the direct labor time variance for June?arrow_forwardMaking journal entries Assume that during the month of April the production report of Algonquin Adhesives Inc. in E8-10 revealed the following information: Make journal entries to charge materials (use the materials purchase price variance) and labor to Work in Process. (Remember to retrieve the standard costs from E8-10 before solving this exercise.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY