PRIN.OF CORPORATE FINANCE
PRIN.OF CORPORATE FINANCE
13th Edition
ISBN: 9781260013900
Author: BREALEY
Publisher: RENT MCG
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 11, Problem 22PS

a)

Summary Introduction

To determine: Net present value (NPV).

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Annual output is 100,000 tons

Operating cost are $0.90 per ton

Sale price is $1 per ton.

Cost of capital is 10%.

Calculation of net present value:

Net present value of such plant is probably going to zero, as a result of industry is competitive and, after two years no company would enjoy the technical benefits.

The present value of each of these plants would be $100,000 the cost is $100,000 and net present value is zero.

b)

Summary Introduction

To determine: Price of polysyllabic acid in 3 year and beyond

b)

Expert Solution
Check Mark

Explanation of Solution

Calculation of price by using net present value of new plant:

 Present value=(100,000×(Price0.85)0.10)$100,000=(500,000×(Price0.85)0.10)Price=$0.95

Therefore, the price of polysyllabic acid is $0.95

c)

Summary Introduction

To determine: Present value when the scrap value is $40,000 and $80,000 in 2 year.

c)

Expert Solution
Check Mark

Explanation of Solution

Calculation of net present value at year 2:

  PV=(100,000tons×(Pricecost)0.10)=(100,000×($0.95$0.90)0.10)=$50,000

Therefore, when the existing plant can be scrapped at t=2 as long as the value of scrap at that point exceeds $50,000 that it’s expected to be.

d)

Summary Introduction

To discuss: Whether company U operate plants profitably after year 2 when plant is fully depreciated.

d)

Expert Solution
Check Mark

Explanation of Solution

Person X views that, company doesn’t operate them in profitably because book value is irrelevant and the net present value of the existing plant is negative after the second year.

e)

Summary Introduction

To discuss: Whether company scrap the new plant in year 2

e)

Expert Solution
Check Mark

Explanation of Solution

Person X views that, company should scrap the newly purchased plant in year 2 because sunk costs are irrelevant and the net present value of the existing plant is negative after the second year.

f)

Summary Introduction

To determine: Net present value.

f)

Expert Solution
Check Mark

Explanation of Solution

Company P’s project causes temporary excess capacity. Therefore the price for future 2 years should be specified the prevailing plant owners are indifferent between scrapping currently and scrapping at the end of 2 year.

Scrap value is $60,000 and also it is equal to present values of future cash flows. Therefore,

Calculation of net present value:

                             Present value=Cashflows(1+r)n$60,000=(100,000×(Price$.90)1.10)+(100,000×(Price$.90)1.102)+$57,9001.102Price=$0.97

By using this value of price we can calculate the present value of new plant,

Calculation of present value of new plant:

             Present value=Cashflows(1+r)n$60,000={100,000×[($0.970.851.10)+($0.970.851.102)+($0.950.85)(0.10×1.102)]}$100,000Present value={100,000×[0.10909+0.09917+0.82644]}$100,000=$103,470$100,000=$3,470

Therefore present value of new plant is $3,470.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Chocoholics Anonymous wants to modernize its production machinery. The company's sales are $9.22 million per year, and the choice of machine won't impact that amount. The required return is 10 percent and the tax rate is 35 percent. Both machines will be depreciated on a straight-line basis. Machine Amaretto costs $1,950,000 and will last for 5 years. Variable costs are 39 percent of sales, and fixed costs are $131,000 per year. Machine Baileys costs $4,610,000 and will last for 7 years. Variable costs for this machine are 31 percent of sales and fixed costs are $103,000 per year. Required: (a)If the company plans to replace the machine when it wears out on a perpetual basis, what is the EAC for machine Amaretto? (Do not round your intermediate calculations.) HINT: In EAC problems you first need to find the NPV. Using this NPV you can then calculate the annuity (annual cost) that has the same present value/cost. The lecture videos include a detailed example of this calculation.…
.  Myers Corporation is attempting to develop and market a new garden tractor.  Fixed cost  to develop and produce the new tractor are estimated to $10,000,000 per year.  The variable cost to make each tractor has been estimated at $2000.  The marketing department has recommended a price of $4000 per tractor.             What is the breakeven level of output for the new tractor.   2. What if management expects to generate a target profit (EBIT) of $2,000,000, how many tractors must be sold.
Asgone plc is considering an investment to increase its manufacturing capacity from 10,000 units per annum to 15,000 units. The current output is sold at a price of $12.50 per unit but market research suggests the higher level of output could be sold at a price of $10 per unit. As the existing plant is due to be replaced this year it is a good time to consider the possibility of expansion. The variable cost per unit of the larger plant is $3.50 whereas it is $5.00 for the smaller plant. The larger plant will cost $60,000 and the smaller plant $25,000. Both plants would be depreciated on a straight-line basis for tax purposes over a five-year life, and this also constitutes the expected working life of the plant. All other costs would remain unchanged. The relevant tax rate is 20%. Is the investment in the larger plant worthwhile if the required rate of return is 10%? Use excel to solve this question
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License