Sommers Company uses the following rule to determine whether materials usage variances should be investigated: A materials usage variance will be investigated anytime the amount exceeds the lesser of $12,000 or 10% of the
Required:
- 1. Using the rule provided, identify the cases that will be investigated.
- 2. CONCEPTUAL CONNECTION Suppose investigation reveals that the cause of an unfavorable materials usage variance is the use of lower-quality materials than are normally used. Who is responsible? What corrective action would likely be taken?
- 3. CONCEPTUAL CONNECTION Suppose investigation reveals that the cause of a significant unfavorable materials usage variance is attributable to a new approach to manufacturing that takes less labor time but causes more material waste. Examination of the labor efficiency variance reveals that it is favorable and larger than the unfavorable materials usage variance. Who is responsible? What action should be taken?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
1. For direct materials:
a. Compute the price and quantity variances.
b. The materials were purchased from a new supplier who is anxious to enter into a long-
term purchase contract. Would you recommend that the company sign the contract?
Explain.
2. For labor employed in the production of Fruta:
a. Compute the rate and efficiency variances.
b. In the past, the 10 persons employed in the production of Fruta consisted of 4 senior
workers and 6 assistants. During June, the company experimented with 5 senior workers
and 5 assistants. Would you recommend that the new labor mix be continued? Explain.
3. Compute the variable overhead rate and efficiency variances. What relation can you see
between this efficiency variance and the labor efficiency variance?
Please do not give solution in image formate thanku.
The following five unrelated situations affect one or more standard cost variances for materials, labor (assembly), and overhead:
1. At the beginning of the month, a supplier of a component used in our product notified us that, because of a minor design improvement, the price will be increased by 15 percent above the current standard price of $100 per unit. As a result of the improved design, we expect the number of defective components to decrease by 80 units per month. On average, 1,200 units of the component are purchased each month. Defective units are identified prior to use and are not returnable.
2. In an effort to meet a deadline on a rush order in Department A, the plant manager reassigned several higher-skilled workers from Department B, for a total of 300 labor hours. The average salary of the Department B workers was $2.05 more than the standard $7.25 per hour rate of the Department A workers. Since they were not…
Setting Standards, Materials and Labor Variances
Tom Belford and Tony Sorrentino own a small business devoted to kitchen and bath granite installations. Recently, building contractors have insisted on up-front bid prices for a house
rather than the cost-plus system that Tom and Tony had been using. They worry because natural flaws in the granite make it impossible to tell in advance exactly how much granite will be
used on a particular job. In addition, granite can be easily broken, meaning that Tom or Tony could ruin a slab and would need to start over with a new one. Sometimes the improperly cut
pieces could be used for smaller installations, sometimes not. All their accounting is done by a local certified public accounting firm headed by Charlene Davenport. Charlene listened to
their concerns and suggested that it might be time to implement tighter controls by setting up a standard costing system.
Charlene reviewed the invoices pertaining to a number of Tom and Tony's previous jobs…
Chapter 10 Solutions
Managerial Accounting: The Cornerstone of Business Decision-Making
Ch. 10 - Discuss the dirrerence between budgets and...Ch. 10 - Describe the relationship that unit standards have...Ch. 10 - Why is historical experience often a poor basis...Ch. 10 - Prob. 4DQCh. 10 - Explain why standard costing systems adopted.Ch. 10 - How does standard costing improve the control...Ch. 10 - Discuss the differences among actual costing,...Ch. 10 - Prob. 8DQCh. 10 - The budget variance for variable production costs...Ch. 10 - When should a standard cost variance be...
Ch. 10 - What are control limits, and how are they set?Ch. 10 - Explain why the materials price variance is often...Ch. 10 - The materials usage variance is always the...Ch. 10 - The labor rate variance is never controllable. Do...Ch. 10 - Prob. 15DQCh. 10 - What is kaizen costing? On which part of the value...Ch. 10 - What is target costing? Describe how costs are...Ch. 10 - Prob. 18DQCh. 10 - The variable overhead efficiency variance has...Ch. 10 - Describe the difference between the variable...Ch. 10 - What is the cause of an unfavorable volume...Ch. 10 - Does the volume variance convey any meaningful...Ch. 10 - Which do you think is more important for control...Ch. 10 - Prob. 1MCQCh. 10 - A currently attainable standard is one that a....Ch. 10 - An ideal standard is one that a. uses only...Ch. 10 - The underlying details for the standard cost per...Ch. 10 - The standard quantity of materials allowed is...Ch. 10 - The standard direct labor hours allowed is...Ch. 10 - Investigating variances from standard is a. always...Ch. 10 - Prob. 8MCQCh. 10 - The materials price variance is usually computed...Ch. 10 - Responsibility for the materials usage variance is...Ch. 10 - Responsibility for the labor rate variance...Ch. 10 - Responsibility for the labor efficiency variance...Ch. 10 - (Appendix 10A) Which of the following items...Ch. 10 - (Appendix 10A) Which of the following is true...Ch. 10 - The total variable overhead variance is the...Ch. 10 - A variable overhead spending variance can occur...Ch. 10 - The total variable overhead variance can be...Ch. 10 - The total fixed overhead variance is a. the...Ch. 10 - The total fixed overhead variance can be expressed...Ch. 10 - An unfavorable volume variance can occur because...Ch. 10 - Prob. 21BEACh. 10 - Control Limits During the last 6 weeks, the actual...Ch. 10 - Use the following information to complete Brief...Ch. 10 - Use the following information to complete Brief...Ch. 10 - Use the following information to complete Brief...Ch. 10 - Use the following information to complete Brief...Ch. 10 - Rath Company showed the following information for...Ch. 10 - Variable Overhead Spending and Efficiency...Ch. 10 - Performance Report for Variable Variances Humo...Ch. 10 - Total Fixed Overhead Variance Bradshaw Company...Ch. 10 - Fixed Overhead Spending and Volume Variances,...Ch. 10 - Prob. 32BEBCh. 10 - Control Limits During the last 6 weeks, the actual...Ch. 10 - Prob. 34BEBCh. 10 - Use the following information to complete Brief...Ch. 10 - Use the following information to complete Brief...Ch. 10 - Use the following information to complete Brief...Ch. 10 - Mulliner Company showed the following information...Ch. 10 - Variable Overhead Spending and Efficiency...Ch. 10 - Performance Report for Variable Variances Potter...Ch. 10 - Bulger Company provided the following data:...Ch. 10 - Fixed Overhead Spending and Volume Variances,...Ch. 10 - Standard Quantities of Labor and Materials...Ch. 10 - Sommers Company uses the following rule to...Ch. 10 - Use the following information for Exercises 10-45...Ch. 10 - Refer to the information for Cinturon Corporation...Ch. 10 - Refer to the information for Cinturon Corporation...Ch. 10 - Materials Variances Manzana Company produces apple...Ch. 10 - Labor Variances Verde Company produces wheels for...Ch. 10 - At the beginning of the year, Craig Company had...Ch. 10 - Jackie Iverson was furious. She was about ready to...Ch. 10 - 10-52 Materials and Labor Variances Refer to the...Ch. 10 - Refer to the information for Deporte Company...Ch. 10 - Esteban Products produces instructional aids,...Ch. 10 - Escuchar Products, a producer of DVD players, has...Ch. 10 - Use the following information for Exercises 10-56...Ch. 10 - Refer to the information for Rostand Inc. above....Ch. 10 - At the beginning of the year, Lopez Company had...Ch. 10 - Zepol Company is planning to produce 600,000 power...Ch. 10 - Last year, Gladner Company had planned to produce...Ch. 10 - Anker Company had the data below for its most...Ch. 10 - Cabanarama Inc. designs and manufactures...Ch. 10 - Basuras Waste Disposal Company has a long-term...Ch. 10 - Tom Belford and Tony Sorrentino own a small...Ch. 10 - Mantenga Company provides routine maintenance...Ch. 10 - Buenolorl Company produces a well-known cologne....Ch. 10 - The management of Golding Company has determined...Ch. 10 - Phono Company manufactures a plastic toy cell...Ch. 10 - Botella Company produces plastic bottles. The unit...Ch. 10 - The Lubbock plant of Morrils Small Motor Division...Ch. 10 - Moleno Company produces a single product and uses...Ch. 10 - The Lubbock plant of Morrils Small Motor Division...Ch. 10 - Extrim Company produces monitors. Extrims plant in...Ch. 10 - Lynwood Company produces surge protectors. To help...Ch. 10 - Shumaker Company manufactures a line of high-top...Ch. 10 - Paul Golding and his wife, Nancy, established...Ch. 10 - Prob. 79CCh. 10 - Prob. 1MTCCh. 10 - The Two Cost Systems Sacred Heart Hospital (SHH)...Ch. 10 - Prob. 3MTCCh. 10 - Prob. 4MTCCh. 10 - The Two Cost Systems Sacred Heart Hospital (SHH)...Ch. 10 - Prob. 6MTCCh. 10 - Prob. 7MTCCh. 10 - Prob. 8MTCCh. 10 - Prob. 9MTCCh. 10 - Sacred Heart Hospital (SHH) faces skyrocketing...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- The management of Golding Company has determined that the cost to investigate a variance produced by its standard cost system ranges from 2,000 to 3,000. If a problem is discovered, the average benefit from taking corrective action usually outweighs the cost of investigation. Past experience from the investigation of variances has revealed that corrective action is rarely needed for deviations within 8% of the standard cost. Golding produces a single product, which has the following standards for materials and labor: Actual production for the past 3 months follows, with the associated actual usage and costs for materials and labor. There were no beginning or ending raw materials inventories. Required: 1. What upper and lower control limits would you use for materials variances? For labor variances? 2. Compute the materials and labor variances for April, May, and June. Identify those that would require investigation by comparing each variance to the amount of the limit computed in Requirement 1. Compute the actual percentage deviation from standard. Round all unit costs to four decimal places. Round variances to the nearest dollar. Round variance rates to three decimal places so that percentages will show to one decimal place. 3. CONCEPTUAL CONNECTION Let the horizontal axis be time and the vertical axis be variances measured as a percentage deviation from standard. Draw horizontal lines that identify upper and lower control limits. Plot the labor and material variances for April, May, and June. Prepare a separate graph for each type of variance. Explain how you would use these graphs (called control charts) to assist your analysis of variances.arrow_forwardRefer to the information for Cinturon Corporation on the previous page. Required: 1. Break down the total variance for materials into a price variance and a usage variance using the columnar and formula approaches. 2. CONCEPTUAL CONNECTION Suppose the Boise plant manager investigates the materials variances and is told by the purchasing manager that a cheaper source of leather strips had been discovered and that this is the reason for the favorable materials price variance. Quite pleased, the purchasing manager suggests that the materials price standard be updated to reflect this new, less expensive source of leather strips. Should the plant manager update the materials price standard as suggested? Why or why not?arrow_forwardGigil Company has asked you to reconstruct their record after a fire. You were given the following variances: Favorable Spending variance, P400,000; Unfavorable varaible effieciency variance, P200,000; Favorable Volume variance P40,000. Total fixed overhead is P200,000 at normal capacity. The company's standard variable overhead is P40 per direct labor hour. In the given period, the company incurred a total overhead cost of P2,400,000. Compute for the standard factory overhead rate.arrow_forward
- [The following information applies to the questions displayed below.] Alvarez Company for the current period shows a $30,000 favorable volume variance and a $55,500 unfavorable controllable variance. Standard overhead applied for the period is $222,000. Alvarez records standard costs in its accounts. Prepare the journal entry to charge overhead costs to the Work in Process Inventory account and to record any variances. Journal entry worksheet A Record overhead applied to production and overhead variances. Note: Enter debits before credits. Transaction 1 Record entry General Journal Clear entry Debit Credit View general journalarrow_forwardA business is reporting on materials cost variances for the month. The report indicates a large favorable materials price variance and a large unfavorable materials quantity variance. Discuss reasons (or provide explanations) that might have caused these off-setting variances.arrow_forwardResset Co. provides the following results of April’s operations: F indicates favorable and U indicates unfavorable. In applying management by exception, the company investigates all variances of $400 or more. Which variances will the company investigate? Direct materials price variance . $ 300 F Direct labor efficiency variance . $2,200 F Direct materials quantity variance . 3,000 U Controllable overhead variance . 400 U Direct labor rate variance . 100 U Fixed overhead volume variance . 500 Farrow_forward
- Required information [The following information applies to the questions displayed below.] Alvarez Company for the current period shows a $22,000 favorable volume variance and a $59,000 unfavorable controllable variance. Standard overhead applied for the period is $233,000. (a) What is the actual total overhead cost incurred for the period? (b) What is the total overhead variance and is it favorable of unfavorable? a. Actual total overhead b. Total overhead variancearrow_forwardThe cost analyst for Sheffer Systems collected the following data concerning direct materials: Actual production 36,100 units Direct materials purchased (actual) Standard cost of materials purchased Standard direct materials costs per unit produced Standard price times actual amount of materials used Required: Compute the direct materials cost variances. Note: Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option. Direct Materials Price variance Efficiency variance Total direct materials cost variance $ 716,500 720,300 17 628,200 Farrow_forwardThink It Through: Don't "Skirt" the Issue E open You run a fabric store and order materials through a supplier. At the end of the month, you review your materials cost and discover that your direct materials price and quantity variances produced unfavorable results. What could be attributed to these unfavorable outcomes? How would these unfavorable outcomes impact the total direct materials variance?arrow_forward
- Required information [The following information applies to the questions dispiayed below] Alvarez Company for the current period shows a $22,000 favorable volume variance and a $59.000 unfavorable controllable variance. Standard overhead applied for the period is $233,000. Alvarez records standard costs in its accounts. Prepare the journal entry to charge overhead costs to the Work in Process Inventory account and to record any variances. View transaction list Journal entry worksheet A Record overhead applied to production and overhead variances. Note: Enter debits before credits. Transaction General Journal Debit Credit 1 Record entry Clear entry View general journalarrow_forward[The following information applies to the questions displayed below.] The director of cost management for Odessa Company uses a statistical control chart to help management determine when to investigate variances. The critical value is 1 standard deviation. The company incurred the following direct-labor efficiency variances during the first six months of the current year. January February March. April May June $ 250 F 800 U 700 U 908 U 1,050 U 1,200 U The standard direct-labor cost during each of these months was $19,000. The controller has estimated that the firm's monthly direct-labor variances have a standard deviation of $950. Required: 1-a. Draw a statistical control chart and plot the variance data given above. 1-b. Which variances will be investigated?arrow_forwardRequired information Use the following information for the Quick Study below. (Static) [The following information applies to the questions displayed below.] Alvarez Company for the current period shows a $20,000 favorable volume variance and a $60,400 unfavorable controllable variance. Standard overhead applied for the period is $225,000. QS 21-18A (Static) Preparing overhead entries LO P6 Alvarez records standard costs in its accounts. Prepare the journal entry to charge overhead costs to the Work in Process Inventory account and to record any variances View transaction list Journal entry worksheet Record overhead applied to production and overhead variances..arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubExcel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY