The total cost required for completing this project on normal time = $ %3D

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question

Please answer part b

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology
firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Total Cost
Normal Time
Crash Time Normal
with
Immediate
Activity
(weeks)
(weeks)
Cost
Crashing Predecessor(s)
$2,000
$2,300
A
4
3
$2,700
2
1
$2,900
3
3
$500
$500
D
8
4
$2,500
$2,800
A
E
6
3
$800
$1,250
$3,200
$1,500
3
2
$4,600
G
4
$2,000
D, E
a) Based on the given information regarding the activities for the project, the project length =
weeks.
b) The total cost required for completing this project on normal time = S|
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
The cost of the project based on the first activity selected for crashing will increase by $
d) The maximum weeks by which the project can be reduced by crashing =
weeks.
Total cost of crashing the project to minimum (or maximum weeks possible) = S
Transcribed Image Text:Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Total Cost Normal Time Crash Time Normal with Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) $2,000 $2,300 A 4 3 $2,700 2 1 $2,900 3 3 $500 $500 D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250 $3,200 $1,500 3 2 $4,600 G 4 $2,000 D, E a) Based on the given information regarding the activities for the project, the project length = weeks. b) The total cost required for completing this project on normal time = S| c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ d) The maximum weeks by which the project can be reduced by crashing = weeks. Total cost of crashing the project to minimum (or maximum weeks possible) = S
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,