Robin Is trying to figure out how much extra of boxes of imported chocolate to keep. During the past year, the demand per week was variable with a mean of 85 and a OR 12. Lead time was also variable with a mean of 6 weeks and o=2. Riley would like to maintain a 90% service level. What is the recommended safety stock? What is the ROP?
Q: Binary variables are variables whose only possible values are 0 or 1. True or False True False
A: A variable shows an attribute that can be precisely estimated & that can evaluate the distinct…
Q: a. Maximize z = 66x₁ - 22x2 Subject to Primal -X1 + x₂ 0 Pr
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Radovilsky Manufacturing Company, in Hayward, California, makes flashing lights for toys. The…
A: Ordering cost is the cost that incurred during the purchase and maintenance of the raw materials in…
Q: William Beville's computer training school, in Richmond, stocks workbooks with the following…
A: Demand D = 19400 units per year Ordering Cost S = $27 per order Holding Cost H = $5 per unit per…
Q: 3. MAXIMAL FLOW: Find the maximum flow from node 1 to node 5 (no given units) using the Maximal Flow…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Use the following payoff table to complete parts (a) through (j). The probability of event 1 is…
A: Decision-making is influenced by an organization as per the degree of certainty involved in this. In…
Q: The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two…
A: Find the Calculation methods below: Week 1 2 3 4 5 6 7 8 9 10 Gross Requirements 20 10 15…
Q: The Sea Wharf Restaurant would like to determine the best way to allocate a monthly advertising…
A: Decision Variables: Suppose-N be the amount to be allocated for newspaper advertisingR be the amount…
Q: Determinar x1 ,x2 y Min z
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Calculate the Mean Absolute Percentage Error for the following data: Actual 91 86 87 97 Forecast…
A: Mean absolute percentage error is the difference between the actual and forecast and divided by…
Q: A company orders 250 units of a product each time the inventory drops below 175 units. If the…
A: Here, given the data stated below, The order quantity is 250 units the reorder quantity with safety…
Q: Given the following historical data, what is the simple three-period moving average forecast for…
A: A moving average is a running average of a set of numbers or a series. It can be used to calculate…
Q: Q2.2. What reorder point should be?
A: Inventory management is the process of ordering, storing, using, and selling the inventory of the…
Q: Customers arrive at Cochinito Bank according to a Poisson distribution, with a mean of 45 customers…
A: Given data: Average arrival rate (λ) = 45 customers per hour Average service time = 5 minutes Then…
Q: Globalization of the location decision is the result of all EXCEPT which of the following? A.higher…
A: Globalization refers to accelerating global flows or transfers (of people, products and services,…
Q: Which of the following is not an assumption of a maximum flow problem? Multiple Choice All…
A: a) Source is the node from where the network is started or outcomes. b) Transshipment node is the…
Q: (i)Formulate the linear Programming problem to get the maximum Financial returns. Advice…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Discuss FIVE (5) key factors which Walmart had to take into consideration when assessing the…
A: Supplier is the individual or organization who provides the products and services to the customers…
Q: Develop a lot-for-lot solution (enter your responses as whole numbers). Period Gross requirements…
A: Find the Calculation methods below: Project on hand = Project on hand - Gross requirementsNet…
Q: The following table shows the actual demand observed over the last 11 years:…
A: Formulae used: For exponential smoothing:Ft=αAt-1 +(1-α)Ft-1 Where, α =Smoothing constantFt…
Q: Five welding jobs are waiting to be processed. Their processing times and due dates are given below.…
A: Under FCFS rule of dispatching, jobs are processed in the same order as of their arrival. In other…
Q: Product A is an end item and is made from two units of B and four of C. B is made of three units of…
A: Ans) Product Tree:
Q: A PCB assembly process supervisor wants to develop a standard time for a particular station of a new…
A: Find the Calculation methods below: Average Observed Time = Total timeNumber of observationNormal…
Q: What criteria are required for a good package?
A: Packaging is the art, science and the process of enclosing a product to make sure that it is safely…
Q: Using an Xbar Chart, what are the upper and lower control limits?
A: Given The sample mean = 99.73% Standard deviation = 1.13 Z-score corresponding to 99.73% under…
Q: From the following list, select the two vital functions performed by project management software
A: a) Calculating a project's duration and schedule:- Project management software has various tools…
Q: Yost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated…
A: Given data: Demand of Product A = 66 units/week Price = $105 units Demand for Product B= 96…
Q: Instructions There are four parts to this problem. Use Excel to perform the following. a. Use the…
A: using the same formula for EOQ as instructed. a.
Q: Which six sigma statistical tool can be used to evaluate a manufacturing organisation
A: Statistical tools: Statistical tools are very important to all the business process…
Q: . What is Production Cost?
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: Nine observations from a work measurement study using continuous timing are shown below. Allowances…
A: Formulae used: In work Measurement: Standard Time=Normal Time×(1+Allowance Factor) Normal…
Q: Operations management is a process that uses resources to transform inputs into outputs. Explain the…
A: Operations is a very important part of any business. It consists of all the activities related to…
Q: The total cost, excluding normal time labor costs, for Plan A = $. (Enter your response as a whole…
A: Find the Calculation methods below: Output forecast = (Production - Demand) + Subcontract…
Q: Which of the following is not a step in the forecasting process? O look for any potential patterns…
A: Forecasting is a combination of both art and science. An operations manager handles and deals with…
Q: 14. The following is a table of activities associated with a project at Rafay Ishfaq's software…
A: Network diagram of given data:
Q: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units…
A: Product structure- shows the hierarchy-based decomposition of the product, It is generally called…
Q: Omega Manufacturing makes three products. Each product requires manufacturing oper- ations in three…
A: Integer linear programming is an optimization technique where the values of the decision variables…
Q: The Ace Manufacturing Company has orders for three similar products. Product A B C 1 2 Machine 3 A A…
A: (a)
Q: A chart used to accent the size of change is called:
A: Column chart:- The data is shown in the rectangular bars with the height proportionate to the…
Q: What schedule produces the shortest time span in which these orders can be completed? Sequence:…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Amelia Ltd. makes a plastic tricycle that is composed of three major components: a handlebar-front…
A:
Q: Calculate the sales variance in dollars and the sales variance as a percentage given the following…
A: Sales variance: Sales volume variation essentially gauges the sales performance as a result of…
Q: Demand = 1570 per quarter, T (Inventory period) <= 5.4 months, Lead Time weeks, safety stock = 15.…
A: The following information is provided to us: Demand per quarter is 1570, The inventory Period is 5.4…
Q: 1.Network representation? 2.Critical path? 3. Non critical activities?
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: ou have now decided to only engage with one key supplier to provide you with the best quality…
A: Suppliers management is the process of maximizing the value of money that is paid to the suppliers…
Q: Compute the slack time for all non-critical activities. 5) What is the latest possible start…
A: Here, I have been given the table data, and for each activity, I have been given the time data and…
Q: Which projects should be selected? What is the total net present value of these projects
A: Linear programming is a mathematical technique that is also used in operations management…
Q: The university administration would like to add some additional parking locations. To make everyone…
A: Given data is Objective function: Min Z=365x1+410x2+405x3+410x4+355x5+445x6 Subject to constraints:…
Q: Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - -…
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: 18hth must be at least 5 (the number TopLathes plus the number BigPresses must be a 5). All machines…
A: Linear programming is a mathematical technique that is also used in operations management…
Step by step
Solved in 3 steps
- I pt Amy works for an insurance company. Last month, she met with 40 prospects and made 16 sales totaling $52,000. Since she exceeded her monthly sales goal of $25,000, her manager gave her a bonus. What was Amy's conversion rate and her "meeting quota" percentage for the month? O 40%, 48% O 48%, 40% O 48%, 208% O 40%, 208% O 208%, 40% Question 3 DuPont assigned groups comprised of chemists, sales and marketing executives, and regulatory Trowors The product recorded sales of $57 million in its fiModule: Principles of Purchasing & Supplies. Qn: Explain how the Push and Pull factor effect can affect the Purchasing processExercise on EOQ and TAIC: Data: D = 7000 flyers, Q = 500 flyers S = $100, k = 28%, C = $2, number of days/year = 350 days Calculate the total cost and the total inventory cost to see if the company's ordering policy needs to be changed. If yes, how should it be changed? Question 2: This year's forecast for D is 8000 flyers/year. The following price list is given according to quantity: Quantity Price 599- 999 2,5$ 1000- 1999 2$ > 2000 1,5 $ How should the ordering policy be changed? (Note: questions about ordering policies like this require finding two factors: when to order and how much to order each time.)
- 4) Rane Brake Linings gathered information for its brake lining components as presented in the table below. How would the firm classify these items according to an ABC classification system? Initial Information Part # Unit Cost Annual Demand 10 10 200 11 30 125 12 9 100 13 12 5000 14 50 195 15 6 300 16 100 7014 To calculate Economic Order Quantity (EOQ =sqrt(D*k/h)Taylor Products distributes two premium kid chairs-Hayden Recliner and Hadley Rocking. Fixed expenses total $390,000 per month. Sales Contribution Margin Ratio Hayden Recliner Hadley Rocking $600,000 $300,000 75% 45% Based on the current sales mix, what is the break-even point in dollar sales for Hayden Reclin O $400,000 $450,000 O $387,000 O $415,000 $392,000
- Average daily demand (d) 130 cases Demand Standard deviation (σd) 20 cases Service level 94.0% Service level alternative 86.0% Lead tme, LT 6 days 1. What is the standard deviation of demand during lead time? Round your answer to one decimal place. _______ cases 2. What is the required safety stock at a 94 percent service level? Round your answer to the nearest whole number. _______ cases 3. What is the reorder point? Round your answer to the nearest whole number. _______ cases 4.What is the required safety stock at a 86 percent service level? Round your answer to the nearest whole number. _______ cases 5. What is the safety stock reduction? Round your answer to the nearest whole number. _______ casesBlack Instrument Company replenishes highly specialized replacement (service) parts based on statistical reorder point. One part is a 40-mm thumbscrew. Relevant data for the thumbscrew are: Planned stock out frequency= Six per year. Planned lead time = 2 weeks Forecast for next week= 300 Batch size = 400 Standard deviation of demand = 20 (per week) What is the reorder point? What would be the effect on the ROP if lead time were five weeks instead of two? What other factors might impact your decision on when to reorder parts?Demand for portable music players for joggers has caused Nancy Industries (Nancy) to grow almost 50 percent over the past year. The number of joggers continues to expand, so Nancy expects demand for music player to also expand, because, as yet, no safety laws have been passed to prevent joggers from wearing them. Demands for the players for last year was as follows : Month Demand (units) Jan 4200 Feb 4300 Mar 4000 Apr 4400 May 5000 Jun 4700 Jul 5300 Aug 4900 Sep 5400 Oct 5700 Nov 6300 Dec 6000 Question : From the choice of simple moving average, weighted moving average, exponential smoothing, and linear regression analysis, which forecasting technique would you consider the most accurate to Nancy Industries? Why?
- One of the items you and your MBA buddie produce in your new business is sambocade cheesecake wild cherry based on an ancient recipe. One of the ingredients, we will call it açúcar, is the major component in the mixture. The demand for this item is very stable at 120 bags a day. However, the delivery lead times vary and has an average of 8 days and a standard deviation of two days. Tina, your other MBA buddie, suggested a 95% (Z = 1.65) service level for this product. What would be the appropriate reorder point for this item? 2,160 1,356 1,044 1,060 960 396 Not possible to calculate o o o o oRound Tree Manor is a hotel that provides two types of rooms with three rental classes: Super Saver, Deluxe, and Business. The profit per night for each type of room and rental class is as follows: Room Rental Class Super Saver Deluxe Business $30 $30 Type I Type II Type I rooms do not have high-speed wireless Internet access and are not available for the Business rental class. Round Tree's management makes a forecast of the demand by rental class for each night in the future. A linear programming model developed to maximize profit is used to determine how many reservations to accept for each rental class. The demand forecast for a particular night is 120 rentals in the Super Saver class, 55 in the Deluxe class, and 50 in the Business class. Round Tree has 90 Type I rooms and 120 Type II rooms. $25 $20 $40 (a) Formulate and solve a linear program to determine how many reservations to accept in each rental class and how the reservations should be allocated to room types. Rental Class…Q4// A company producing compressors, decided to make a particular item in batches. The following information is available: • Receiving and inspecting = 10$ per order Verifying and payment of bill = 10$ per order • Other ordering and set up cost = 25$ per order • Consumption rate of item = 65 item per month %3D • Insurance = 3 $ per item in year • Storage and handling cost = 2$ per item in year • Taxes = 3 $ per item in year • Other inventory carrying cost = 4$ per item in year • Item cost = 5$ per item Calculate the Economic Batch Quantity, the number of lots, the total cost of one year requirement and what is the cycle time of order.