Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order.

  Time Required (hours)
Job Mill Drill
216 7   11  
327 6   10  
462 8   4  
519 5   8  
258 3   5  
617 12   15  

Develop a minimum makespan schedule using Johnson's rule.

The schedule using Johnson's rule is - - - - - .

Choose the correct Gantt chart with the minimum makespan schedule.

The correct graph is .

C.
D.
DRILL
Time
Job
MILL
Time
Job
DRILL
Time
Job
MILL
Time
Job
DRILL
Time
Job
0
03 8
7
03 8
HH
258
0
0
258 519 327 216
462
216
8
14
519
8 12
462
16
18
617
327
21
327
20
28 32
462
29
26
617
462 519
216
617
40 45
37 41
258
41
35
462
27 33 38 41
216 327 519 258
216
46
617
617
327
56
56
60
64
519
258
69
Transcribed Image Text:C. D. DRILL Time Job MILL Time Job DRILL Time Job MILL Time Job DRILL Time Job 0 03 8 7 03 8 HH 258 0 0 258 519 327 216 462 216 8 14 519 8 12 462 16 18 617 327 21 327 20 28 32 462 29 26 617 462 519 216 617 40 45 37 41 258 41 35 462 27 33 38 41 216 327 519 258 216 46 617 617 327 56 56 60 64 519 258 69
On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order.
Time Required (hours)
Mill
Drill
7
6
8
5
3
12
Job
216
327
462
519
258
617
Develop a minimum makespan schedule using Johnson's rule.
The schedule using Johnson's rule is -Select-
Choose the correct Gantt chart with the minimum makespan schedule.
The correct graph is -Select- +
A.
B.
MILL
Time
Job
DRILL
Time
Job
MILL
Time
Job
03
8
HH
258 519 327 216
03 8
HH
258
0
7
14
519
13
16
21
327
617
26
21 2629
216 327 462 519 258
-
33
216
-Select- ♦
462
37
617
41
41
617
-Select- +
52 56
462
11
10
4
8
5
15
-Select- ♦
-Select-
+
-Select-
Transcribed Image Text:On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Mill Drill 7 6 8 5 3 12 Job 216 327 462 519 258 617 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is -Select- Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is -Select- + A. B. MILL Time Job DRILL Time Job MILL Time Job 03 8 HH 258 519 327 216 03 8 HH 258 0 7 14 519 13 16 21 327 617 26 21 2629 216 327 462 519 258 - 33 216 -Select- ♦ 462 37 617 41 41 617 -Select- + 52 56 462 11 10 4 8 5 15 -Select- ♦ -Select- + -Select-
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,