Q54 ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the prominent consultation company this company required to provide excellent service to meet customer demand. Table QŠ shows the planning for the new product development project received recently by this company. Table Q5 Activity Actions Preceding |activities Time (weeks) Product Conception Material Selection Process Conception Production System Design Prototype tests Procurement Tool and machine | acquisition Product installation | and testing A 4 3 А, В F D E,F H G a. Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS), early finish (EF) and late finish (LF) in the diagram. b. Find the critical path in the network diagram

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

engeenring managament 

answer please

Q54
ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the
prominent consultation company this company required to provide excellent service to meet
customer demand. Table Q5 shows the planning for the new product development project
received recently by this company.
Table Q5
Activity
Preceding
activities
Actions
Time (weeks)
A
Product Conception
4
В
Material Selection
3
Process Conception
Production System
Design
Prototype tests
Procurement
Tool and machine
C
А, В
5
1
E
F
E,F
H
acquisition
Product installation
G
and testing
a. Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS),
early finish (EF) and late finish (LF) in the diagram.
b. Find the critical path in the network diagram
Transcribed Image Text:Q54 ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the prominent consultation company this company required to provide excellent service to meet customer demand. Table Q5 shows the planning for the new product development project received recently by this company. Table Q5 Activity Preceding activities Actions Time (weeks) A Product Conception 4 В Material Selection 3 Process Conception Production System Design Prototype tests Procurement Tool and machine C А, В 5 1 E F E,F H acquisition Product installation G and testing a. Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS), early finish (EF) and late finish (LF) in the diagram. b. Find the critical path in the network diagram
Expert Solution
steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.