Klassen Toy Company, Ic., assembles two parts (parts 1 and 2): Part 1 is first processed at workstation A for 12 minutes per unit and then processed at workstation B for 30 minutes per unit. Part 2 is simultaneously processed at workstation C for 20 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are assembled. The time at workstation D is 10 minutes. a) The bottleneck of this process is workstation B , at 30 minutes per unit (enter your response as a whole number). b) The hourly capacity of the process is units (enter your response as a whole number).
Q: give some explanation on how job set-up time is reduced by executing jobs in batches
A: Clump occupations are regularly lined up during working hours, then, at that point executed during…
Q: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 <BUDE" 2 A 3 4…
A: Given data: Job Operation - 1 Operation - 2 A 12 4 B 8 11 C 5 14 D 6 2 E 9 10 F 3 1…
Q: Bill builds benches in a small shop and he plans to operate five 8-hour days perweek. Each bench has…
A: Lead Time Lead Time is the time is passed from the inception of the production to the end of it. It…
Q: A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling…
A: A production process at Kenneth Day Manufacturing is shown in the figure above. Effective capacity…
Q: The Security Life Insurance Company processes all new life insurance policies through three…
A: The given data is As only the hours are given in the project here it is assumed that the processing…
Q: Joe's Twenty-four Seven Laundromat has the following jobs waiting to be processed. The first step of…
A: The sequence of operation is given as First Come First Serve i.e. A-B-C-D-E. Here, the 1st operation…
Q: Consider a process consisting of five resources that are operated 8 hours per day. Theprocess works…
A: Given data is Product A = 40 units per day Product B = 50 units per day Product C = 60 units per day…
Q: The assembly department started the month with 468,000 units in its beginning work in process…
A: Inventory is the raw items, material, and raw parts that a company used to manufacture the products…
Q: Explain briefly five (5) important process scheduling policy factors that must be considered.
A: ANSWER: Planning of schedule Management : The planning for schedule management which outlay the…
Q: department during the month to begin processing in the Assembly Department. There were 34,000 units…
A: Given data •The Assembly Department started the month work in process with 37,000 units •An…
Q: Give a brief explanation of five major process scheduling policy factors.
A: Process scheduling:- The task of the process manager that deals with removing the active process…
Q: A furniture factory makes two types of wooden tables,large and small. See the flowchart…
A: Capacity of a process To be determined by the capacity of its bottleneck process Represents the…
Q: Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken,…
A:
Q: Cycle time is the longest cycle time allowed for each workstation in a line balancing to produce one…
A: The concept used here is understanding manufacturing times such cycle time, lead time, takt time…
Q: SpikLock makes several lines of metal items. The most recent order has been for 1200 door lock units…
A: Given information Resources Knob and plate Lock Key Available Bross Alloy 12 5 1 15000…
Q: What is the impact of waiting time on a production process? Why is waiting time reduced? Will it be…
A: The impact of waiting time on a production process is In a manufacturing process, the…
Q: Why is it required to include an exception in the process scheduling?
A: Process scheduling is the activity of the process overseer that handles the ejection of the running…
Q: For a given process, the raw processing time is 102 sec, the bottleneck cycle time is 20 sec/item,…
A: Given, Raw processing time = 102 seconds. Bottleneck cycle time= 20 seconds per items. Work in…
Q: Which of the following actions does not relate to off-loading the bottleneck?a. Reassigning…
A: The bottleneck is the point of congestion where the business operations and processes get slowed…
Q: As a production supervisor, Joe decides on Friday afternoon how many units of output his employees…
A: Controlling - Controlling is a role of management that supports to check faults in command to take…
Q: XYZ is famous for homemade pizzas which are crisp with thin crust and varied toppings giving the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A company assembles a product that consists of three pieces called AA, BB, and CC. The AA and BB…
A: The total hours which the machine can work in an year: 50 weeks * 5 days * 8 hours = 2000 hours…
Q: Which of the three workstations, W, X, or Y, has the highest aggregate workload, and thus serves as…
A: As per the provided data the information is as follows.
Q: Process D has five activities in a straight line. The cycle time for Activity 1 is 10 seconds,…
A: Given data Cycle time of Activity 1= 10 seconds Activity 2= 35 seconds Activity 3= 30 seconds…
Q: snip
A: Cycle time in a manufacturing unit is the complete duration taken to produce a product. Cycle time…
Q: Petroleum that is produced from crude oil in an oil refinery is an example of O a. Project O b.…
A: The answer is as follows:
Q: Joe’s commercial laundry has contracts to wash bedsheets for hotels. Joe intakes each batch of…
A: Here, the ironing process has the least capacity per hour. Hence, the ironing process is the…
Q: DreamInflate is a balloon manufacturing company. Balloon manufacturing consists of seven work…
A: As per your request, I have solved the last question from the given set of questions. Kindly find…
Q: Explain the Pacesetter(Pacemaker) concept related to scheduling in the manufacturing domain?
A: Any process along a value stream that sets the pace for the entire stream is the pacesetter process.…
Q: What problems not generally found in manufacturing systems do service systems present in termsof…
A: In an organization, when the primary target is customer service and contact and efficiency becomes…
Q: An order for 100 of a product is processed on operation A and operation B. The setuptime on A is 50…
A:
Q: Consider the following three-station production line with a single product that must visit stations…
A: Given data
Q: Using linear programming, determine how many pieces of poloshirts and how many pieces of t-shirts…
A: Using linear programming, determine how many pieces of poloshirts and howmany pieces of t-shirts…
Q: For the sequence using Johnson’s Rule, the Make span =
A: Make span indicating the total time taken to complete all the task associated with the work using…
Q: Show clearly all working explaining detailly each step
A: The paperwork that travels with the material through the production process is called a shop packet…
Q: The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Which operation is the bottleneck of this process? a. Stocking b. Pricing c. Spotting d. Shipping…
A: An operation that takes the maximum time to complete its task in a supply chain for a particular…
Q: Diablo Electronics manufactures four unique products (A, B, C, and D) that are fabricated and…
A: In production and project management, a bottleneck is one process in a chain of processes, with the…
Q: New students who join the university, should visit cer-tain departments in their first day, as part…
A: Note: - Since we only answer up to 3 sub parts, we will answer questions a,b, and c. Please resubmit…
Q: A manufacturing system is used to produce a product. Each unit of product must be processed…
A: Cycle time = Bottleneck time Bottleneck station = Workstation V [ because it has lowest Capacity ]
Q: The table below shows the time for each work element in an manual assembly process, along with the…
A: Given that: Work element A B C D E F G H I J Time (minutes) 0.7 0.4 0.2 0.3 0.5 0.4 0.6 0.5 0.3…
Q: 2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”,…
A: a. The process capacity is directly proportional to the bottleneck. As the process capacity of…
Q: DreamInflate is a balloon manufacturing company. Balloon manufacturing consists of seven work…
A: Given: No. of workers = 5Labor charge = $ 15/ hourSelling cost = $ 6Variable cost = $…
Q: Registration at Southern University has always been a time of emotions, commotions and lines.…
A: When a unit travels into (or off of) a hex of a specific terrain type, the movement cost of that…
Q: Discuss process batches and transfer batches. How might you determine what the sizes should be?
A: A process batch is the number of products or units handled at a work center before the setup of that…
h4q3b
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Esplanade Marine Parts Inc. wants to produce parts in batches of 60 parts. Each part must be processed sequentially from workstation A to B. Processing Workstation Batch Size (Q) Time per Part 40 seconds A B 60 60 15 seconds a. How many seconds are required to produce the batch under the assumptions of batch processing? Round your answer to the nearest whole number. seconds b. How many seconds are required to produce the batch under the assumptions of single-piece flow processing? Round your answer to the nearest whole number. seconds C. Compare the two solutions in terms of time saved. Round your answer to the nearest whole number. Using the assumptions of -Select- processing saves seconds.A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 2.1 units/hr Sawing 5 units/hr Sanding Drilling 5 units/hr Welding 2.5 units/hr a) Sawing is the bottleneck. b) The bottleneck time is 28.57 minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is 89.58 minutes (round your response to two decimal places). Assembly Q 0.8 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hrNatura has to fill 7 orders for its clients. He requires placing the required product in work boxes and subsequently closing them properly so that the product reaches the customer correctly. The process consists of filling the box and later closing it. As the content of each box and the size of these is different, the filling and closing times of each order is different. These times are shown in the table below. Orders Place in box (minutes) Closing Box (minutes) 1 9 6 2 8 5 3 7 7 4 6 3 5 1 2 6 2 6 7 4 7 a) Find the sequence to complete the orders in the shortest time possible. b) Using a Gantt chart, find the total time in which all orders will be completed using the sequence from part a.
- Klassen Toy Company, Inc., assembles two parts (parts 1 and 2): Part 1 is first processed at workstation A for 10 minutes per unit and then processed at workstation B for 15 minutes per unit. Part 2 is simultaneously processed at workstation C for 20 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are assembled. The time at workstation D is 10 minutes. The hourly capacity of the process? (enter your response as a whole number). 3 units 2 units 4 units 6 units 60 unitsA production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 6 units/hr Sawing 2.5 units/hr Sanding Drilling 1.8 units/hr Welding 7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hrA production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 7 units/hr 5 units/hr Assembly 0.8 units/hr Sawing Sanding Welding Assembly 2.1 units/hr 0.8 units/hr Drilling 2.5 units/hr Assembly 0.8 units/hr a) is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is minutes (round your response to two decimal places).
- A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 1.8 units/hr Sawing 5 units/hr Sanding Drilling 6 units/hr a) Sawing is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). Welding 2.2 units/hr Assembly 0.7 units/hr →→Assembly 0.7 units/hr Assembly 0.7 units/hr QAn enterprising student has set up an internship clearinghouse for business students. Each student who uses the service fills out a form and lists up to 10 companies that he or she would like to have contacted. The clearinghouse has a choice of two methods to use for processing the forms. The traditional method requires about 20 minutes to reviewthe form and arrange the information in the proper order for processing. Once this setup is done, it takes only two minutes per company requested to complete the processing. The other alternative uses an optical scan/retrieve system, which takes only a minute to prepare but requires five minutes per company for completing the processing. If it costsabout the same amount per minute for processing with either of the two methods, when should each be used? (Answer in Appendix D)Canine Kernels Company (CKC) manufactures two differenttypes of dog chew toys (A and B, sold in 1,000-count boxes)that are manufactured and assembled on three differentworkstations (W, X, and Y) using a small-batch process (seeFigure 5.12). Batch setup times are negligible. The flowchartdenotes the path each product follows through the manu-facturing process, and each product’s price, demand perweek, and processing times per unit are indicated as well.Purchased parts and raw materials consumed during pro-duction are represented by inverted triangles. CKC can makeand sell up to the limit of its demand per week; no penaltiesare incurred for not being able to meet all the demand. Eachworkstation is staffed by a worker who is dedicated to workon that workstation alone, and is paid $6 per hour. Totallabor costs per week are fixed. Variable overhead costs are$3,500/week. The plant operates one 8-hour shift per day, or40 hours/week. Which of the three workstations, W, X, or Y,has the highest…
- I already find a. I need help with b Bill's Barbershop has two barbers available to cut customer's hair. Both barbers provide roughly the same experience and skill, but one is just a little bit slower than the other. The process flow below shows that all customers go through steps B1 and B2 and then can be served at either of the two barbers at step B3. The process ends for all customers at step B4. The numbers in parentheses indicate the minutes it takes that activity to process a customer. b. What single activity is the bottleneck for the entire process? B what?A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q a) is the bottleneck. 6 units/hr Sawing 2.4 units/hr Sanding Drilling 2 units/hr Welding 5 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr OUThe diagram below represents a process where two components are made at stations A1 and A2 (one component is made at A1 and the other at A2). These components are then assembled at station B and moved through the rest of the process, where some additional work is completed at stations C, D, and E. Assume that one and only one person is allowed at each station. Assume that the times given below for each station represent the amount of work that needs to be done at that station by that person, with no processing time variation. Assume that inventory is not allowed to build in the system. Al 0.3 min. A2 0.4 min. B 0.75 min. D 0.65 min. 0.60 min. E 0.55 min. What is the average hourly output of the process when it is in normal operation? Average hourly output units