For the sequence using Johnson’s Rule, the Make span =

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

Find the value of X in the following Flow Shop data consisting of 5 jobs which are to be processed on two machines M1 & M2 in that order.

Jobs

M1

M2

A

 

13

21

B

 

8

16

C

 

30

25

D

 

11

27

E

 

15

25

 

For the sequence using Johnson’s Rule, the Make span =    X