For the following sitution draw a PERT network, and determine the following: Critical path ES,LS,EF,LF and slack time for each activity Activity Immediate  predecessor(s) Optimistic  time Most probabl time Pessimistic  time Crashing cost/day $$ Minimum expected completion time    A   1 1 1 900 1    B A 3 6 8 400 2 C A 4 5 6 700 3 D A 2 3 4 800 3 E A 9 9 15     F B 7 8 8 300 5 G B 4 7 9 500 3 H C 1 3 9 700 3 I D 5 6 7     J F,G,H 3 4 8 1100 2 K H,I 2 3 7 650 3 L H,I 7 7 8 300 4 M D 8 9 15     N M 10 15 17 1400 7 O M 3 6 9 600 4 P D 6 12 13 550 7 Q M 8 9 12 980 4 R P,Q 3 6 7     S O,R 7 8 12     T J,K,L,N 6 7 12 520 5 U J,K 4 5 5     V J,K 2 2 2 100 1 W E,S,T,U,V 5 6 9     X E,S,T,U,V 9 10 10 650 3 Y W 3 4 6 50 2 Z X,Y 7 8 9   4   Probability to complete the project in 8 days plus the calculated expected completion time or less. Given the answers obtained in parts a and b, suppose the project has fixed costs per day of $1000. Also suppose you could reduce the length of the project’s duration by expediting certain activity’s expected time at a given cost shown in the table above to some minimum number of days, what would you recommend?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

For the following sitution draw a PERT network, and determine the following:

  • Critical path
  • ES,LS,EF,LF and slack time for each activity

Activity

Immediate  predecessor(s)

Optimistic

 time

Most probabl time

Pessimistic

 time

Crashing cost/day

$$

Minimum expected completion time

   A

 

1

1

1

900

1

   B

A

3

6

8

400

2

C

A

4

5

6

700

3

D

A

2

3

4

800

3

E

A

9

9

15

 

 

F

B

7

8

8

300

5

G

B

4

7

9

500

3

H

C

1

3

9

700

3

I

D

5

6

7

 

 

J

F,G,H

3

4

8

1100

2

K

H,I

2

3

7

650

3

L

H,I

7

7

8

300

4

M

D

8

9

15

 

 

N

M

10

15

17

1400

7

O

M

3

6

9

600

4

P

D

6

12

13

550

7

Q

M

8

9

12

980

4

R

P,Q

3

6

7

 

 

S

O,R

7

8

12

 

 

T

J,K,L,N

6

7

12

520

5

U

J,K

4

5

5

 

 

V

J,K

2

2

2

100

1

W

E,S,T,U,V

5

6

9

 

 

X

E,S,T,U,V

9

10

10

650

3

Y

W

3

4

6

50

2

Z

X,Y

7

8

9

 

4

 

  • Probability to complete the project in 8 days plus the calculated expected completion time or less.
  • Given the answers obtained in parts a and b, suppose the project has fixed costs per day of $1000. Also suppose you could reduce the length of the project’s duration by expediting certain activity’s expected time at a given cost shown in the table above to some minimum number of days, what would you recommend?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.