The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Duration Budget Actual Cost % D=8 Activity Predecessor (s) (week) (S) ($) Complete 300 400 A 3 100 4 200 180 100 B-4 C 7 250 300 90 D A 8 600 400 50 400 200 E В 40 150 180 F 4 100 G:4 100 200 G 4 40 H D, E 2 500 300 F, G 3 J H, I 1 100 ㅇ CO 요
Q: project one day earlier? (0.5) How much does it cost? (0.5) Show all your work.
A: In order to shorten the project length for one week, we have to crash one of the activity by 1 day…
Q: Normal Completion Crashed Completion time (week) Activity Crashed Cost per Preceding Activity Time…
A: The question is related to Crashing the project duration. The details are given 7 activities from A…
Q: Conduct a forward and backwards pass for the activity network diagram that you have constructed…
A: THE ANSWER IS AS BELOW:
Q: The Advanced Tech Company has a project to design anintegrated information database for a major…
A:
Q: The new director of special events at a large university has decided to completely revamp graduation…
A: Given data is
Q: The activities described by the following table are given for the Howard Corporation in Kansas Time…
A: This question is related to the topic Project Management and This topic falls under Operations…
Q: 1. How is the project performing from a schedule perspective? 2. How is the project performing…
A: For this IT project, we could see that total project duration =6 months, Project team would…
Q: 11-17 The following are the activity times for the project in Problem 11-16. Find the earliest,…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: a) Based on the activity time estimates, the expected times and variance for each of the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8,respectively.…
A:
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: Network diagram:
Q: The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty…
A: A project network diagram is a graphic depiction of a project's process. A network diagram is a…
Q: Consider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network…
A: a)
Q: Project X has the data points below. The schedule performance index (SPI) for task P is .. Task BCWS…
A: Here, we first understand the values given for each task BCWS = Budgeted Cost of work scheduled -…
Q: The chart of the numbers listed in the table below. Find the critical path and the duration of the…
A: Find the Given details below: Activity Duration A 7 B 13 C 11 D 12 E 15 F 8 G 9…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Given data is
Q: A project has four major activities. Activity A precedes activity B, activity C precedes activity D.…
A: THE ANSWER IS AS BELOW:
Q: Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of…
A: Given, Budget at Completion (BAC) of $250,000 Time- 10 months
Q: The estimated times and immediate predecessors for the activities in a project at Howard Umrah's…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: For each of the following network diagrams, determine both the critical path and the expected…
A: b. The possible paths are: 1-2-4-6-8-9: = 5 + 18 + 3 + 4 + 9 2 = 41 weeks 1 - 2 - 5 - 6 - 8 - 9 = 5…
Q: Early Start, Early Finish, Late Start, Late Finish, Duration, Float Below is a project listed in a…
A: Given- Activity Predecessor Duration (Weeks) A None 5 B A 3 C A 8 D C 13 E B 7 F B 9…
Q: 6,8,19 E 3,11,14 5,9,14 F 2,19,38 2.9.14 G Start 1,6,15 2,5,8 Finish K H. 1,8,13 4,8,15 3,7,10 NB:…
A: Hi, we are supposed to answer 3 subparts at a time. Since you have not mentioned which subpart to…
Q: Q4. Answer the following questions (a-h), based on the provided project Gantt Chart. The red line…
A: Note: Since you have posted a question with multiple sub-parts, we will solve first four sub-parts…
Q: 2- A project to develop technology training seminars is 5 days behind schedule at day 65. It had a…
A: From the above given information, The number of planned scheduled days, S =65…
Q: A project requires these activities to be completed and the table below shows the expected time and…
A: It can see that the cost variance is positive. While the scheduled variance is negative. The…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: Given data is Steps for project crashing: Create the network diagram Find the path with the…
Q: A project has eight activities that need to be completed (Activity A to H) and will be completed in…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: I need a detailed explanation and assistance to solve this problem: A company decides to plan a…
A: Drawing the project network as shown in the diagram using AOA convention we represent the activities…
Q: Consider the office renovation project data in Table 7.16. A “zero” time estimate means that the…
A: According to the given information, the critical path is A-C-F. Compute total expected time:
Q: Activities, preceding activities, normal and crashed completion times of each of the activities and…
A: Forward Pass: Early Start (ES) = Maximum EF value from immediate Predecessor(s) Early Finish (EF) =…
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: For Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: Consider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network…
A: PERT/CPM are both network-based of project management processes, which show the flow & series of…
Q: You are the project manager working for Mack's Pool Co. Your project consists of installing a new…
A: Please find the network diagram as below
Q: PROJECT PLANNING & SCHEDULING WITH GANNT CHART Given the activities of a project, their time…
A: Note: - Since, we can answer only up to 3 questions, we will answer questions a, b, and c for your…
Q: By using Bar chart planning method, find the following: - Total duration for the project activities…
A: ANSWER IS GIVEN BELOW:
Q: A project has 7 activities P, Q, R, S, T, U, and V. Three time estimates (optimistic, most-likely,…
A: Let Optimistic time be a Most-likely time be m and Pessimistic time be b
Q: The following is a table of activities associated with a project at Rafay Ishfaq's software firm in…
A: Given data is
Q: By using Bar chart planning method, find the following: - Total duration for the project activities…
A: Find the Bar Chart below: Activities early Start calculated by adding previous activities duration…
Q: The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first…
A: The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. (a)…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The cost slope will be calculated for each activity with the…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The Critical path activity having the least Cost slope will be…
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: Network diagram: Critical path: B-E-G Project completion time: 21 weeks
Q: PROJECT PLANNING & SCHEDULING WITH GANNT CHART Given the activities of a project, their time…
A: The network diagram of the given case
Q: Project Management In the below Precedence Diagram ( The activities durations are in weeks ) If…
A: Here, in the question, we have Network diagram, for each activity node, I have following data like…
Q: Given the network plan that follows, compute the early, late, and slack times. What is the project…
A:
Q: Table 1: Activities and Predecessors Activity Immediate Predecessors Duration A 7 B A 6 C A D В.С 12…
A: Given Information:
Q: The project manager of a task force planning the construction of a domed stadium had hopedto be able…
A: To solve this question let's first draw the activity diagram and identify the critical path for…
Q: The data below represent a project that can be completed at normal cost in 15 days. The project can…
A: Find the Given details below: Activity Predecessor Normal Time (NT) (Days) Crash Time (CT) (Days)…
Q: A simple CPM network has three activities, N, O, and P. N is an immediate predecessor of O and of P.…
A: ANSWER IS AS FOLLOW:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95. The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project? A. $80000 B. $84,210 C. $59,210 D. $109,210++ Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: Table 2 No 1 2 3 Type Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) TOTAL RM 64,000 68,000 54,000 100,000 Percentage 64.0 68.0 54.0 100.0 a) With the aid of a typical S-curve diagram, draw and explain the four cost-related measures such as TBC, CBC, CAC and CEV to analyses the overall project cost performance.Analyze the characteristics of a project that calls for a predictive approach to the SDLC, and the one that calls for adaptive approach.
- A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.Evaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk ManagementCreate a risk matrix for this project:Event Cost ($000) ProbabilityEquipment breakdown 40 .20Vendor is late with key segment 200 .60Subcontractor has labor issues 140 .30Weather problems 15 UnknownFunding delays 50 .40 to .60Testing delays 20 .40Explain your reasoning for your placement of the events Weather problems and Funding delays.
- The decision was made by JMP management that a certain critical development in the overall project will be subcontracted-out to a vendor. JMP has issued a six-month cost plus fixed fee contract for that development, and you are the vendor's project manager. The approved JMP budget for your development is $500,000. A recent Earned Value Analysis that your firm (the vendor) has done shows that you will complete the project four weeks ahead of time, thus depriving your firm of $80,000 of billable time. Among your options are: 1. Since it was the approved budget, go ahead and bill JMP for the entire $500.000. 2. Inform JMP of the project status and completion date, and ask if they'd like to add any features to account for the monies spent. 3. Inform JMP of the project status and completion date. 4. Bill JMP for the $500,000 by adding more work at the end of the project.The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10Estimate the number of sales personnel needed for an XYZ company having a forecast for FY 21 as ₹6,00,00,000. According to XYZ company’s past records, the average revenue generated per sales personnel is ₹10,00,000. The estimated % of annual salesforce turnover is 1.6%. 61 55 45 49
- Give an explanation of how earned value management (EVM) may be used to keep expenses under control and monitor the overall effectiveness of a project, and then hypothesise as to why it is not utilised more often. How can one determine if the data for cost variation, schedule variance, cost performance index, and schedule performance index are healthy or unhealthy? What are some basic rules of thumb?The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeks