A manufacturing shop is designed to operate most efficiently at an output of 550 units per day. In the past month the plant produced 490 units. What was their capacity utilization rate last month? (Round your answer to 1 decimal place.) Capacity utilization % rate
Q: In December, RMO Manufacturing had Actual Output of 100 units. Its Effective Capacity dropped to 120…
A: Given Data: Actual Output=100units Effective Capacity= 120units Design capacity = 200 units
Q: A seed company has a design capacity of 80 metric tonnes per day. It's effective capacity, However,…
A: Design capacity is 80 metric tonnes per day, effective capacity is 64 metric tonnes per day, and…
Q: If a plant has an effective capacity of 6,400 and an efficiency of 88%, then its actual (planned)…
A: Given data is Effective capacity = 6400 Efficeincy = 88%=0.88
Q: How you see the the company's excess capacity and how to utilize it throughout the year
A: Excess capacity is a state that occurs when the claim for the manufactured goods is reduced compared…
Q: A manufacturing shop is designed to operate most efi ciently at an output of 550 units per day. In…
A: An organization is a group of people who work together to achieve a specific or particular…
Q: Pipes are installed in a process with two resources. The first resource has a capacity of 0.34 pipes…
A: In order to arrive at the capacity of the pipes, first, we need to know the bottleneck. The…
Q: A process currently services an average of 55 customers per day. Observations in recent weeks show…
A: Given- Expected Demand Rate= 85% = 0.85Current service rate= 55 customers/dayCurrent Utilization =…
Q: In a service process such as the checkout counter in a discount store, a good target for capacity…
A: Answer given below:
Q: How important is strategic capacity planning for products and services? Defend your answer
A: Capacity refers to a system's ability to produce products or provide services over a given time…
Q: A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled…
A: Design Capacity = 800 trucks Effective Capacity = 600 trucks Actual Output = 400 trucks
Q: The bathtub theory of operations management is being promoted as the next breakthrough for global…
A: Given Information: Bathtub capacity = 40 gallons of capacity Output = 2 gallons per hour Input = 4…
Q: A company has a factory that is designed so that it is most efficient (average unit cost is…
A: Capacity utilisation = Capacity Used/Best Operatiing Level * 100
Q: Any increase in efficiency also increases utilization. Although the upper limit on efficiency is…
A: An increase in efficiency would increase the utilization. Efficiency is the ratio of actual output…
Q: A process currently services an average of 50 customers perday. Observations in recent weeks show…
A: Capacity requirement is the one which dealt with the amount of services or information which could…
Q: A manufacturing shop is designed to operate most efficiently at an output of 550 units per day In…
A: A product is a tangible substance that is offered in the market to satisfy the desire or requirement…
Q: calculate takt time in seconds
A: Takt time refers to the rate at which a product must be completed for meeting the demand.
Q: Determine the utilization and the efficiency for each of these situations: a. A loan processing…
A: Hence, the efficiency is 87.50% and the utilization is 70%.
Q: If a plant has an effective capacity of 6,500 andan efficiency of 88%, what is the actual (planned)…
A: A product is a tangible substance that is offered in the market to satisfy the desire or requirement…
Q: Identify the process's existing capacity and determining whether the process's present capacity…
A: The capacity of a manufacturing unit can be expressed in terms of the number of quantities…
Q: A company manufactures a product using two machine cells. Each cell has a design capacity of 250…
A:
Q: A manufacturer of printed circuit boards has a designcapacity of 1000 boards per day. Th e eff…
A: Capacity utilization is an indicator of the production process, that is how much capacity of the…
Q: Determine the utilization and the efficiency for each of these situations:a. A loan processing…
A: Calculations: Formula:
Q: A process currently services an average of 41 customers per day. Observations in recent weeks show…
A: Given data: Average customers per day = 41 Current utilisation = 90% = 0.90 The management wants a…
Q: If a workstation can produce 1000 units in 100 hours and the actual workstation efficiency is only…
A: If , the workstation can produce 1000 units in 100 hours, then the standard output rate for 2000…
Q: Manager must decide how many machines of a certain type to purchase. Each machine can process 100…
A: The Break-even point is the point at which the production cost and production revenue are equal for…
Q: A seed company has a design capacity of 80 Metric Tonnes (MT) per day. Its effective capacity,…
A: Given Information: Design Capacity = 80 MT per day Effective Capacity = 64 MT per day Actual Output…
Q: A company has a factory that is designed so that it is most efficient (average unit cost is…
A: Capacity utilization rate is the measure of the proportion of economic output actually realized…
Q: In an essay, suppose you are opening up an an Applesbee's restaurant. describe the capacity…
A: While these things are significant, there is one basic factor missing from this rundown which…
Q: Which capacity strategy would be appropriate for Fitness Plus? Justifyyour answer
A: In operations management, capacity planning plays an important part in the effective and smooth…
Q: If a plant has an effective capacity of 6,400 and an efficiency of 88%, then its actual (planned)…
A: Effective capacity is the maximum measure of work that an association is capable of finishing in a…
Q: Any increase in efficiency also increases utilization. Although the upper limit on efficiency is 100…
A: Production efficiency may be a financial term depicting A level during which an economy or substance…
Q: What are the capacity requirements for the next four years? (Assume that there is no learning.)…
A: Plastic sprinklers:1 machineCapacity 240,0005 workersTotal available capacity = 240,000 * 1 =…
Q: A loan processing operation that processes an average of 8 loans per day. The operation ha design…
A: Efficiency is frequently calculated as a ratio of actual to anticipated production. On the other…
Q: In 2006, Shouldice Hospital admitted 14,965 patients. In 2007, a 20% increase in admissions is…
A: Average Flow time (average stay of an average patient in the hospital) = 8 days Arrival rate =…
Q: Any increase in efficiency also increases utilization. Although the upper limit on efficiency is 100…
A: An increase in efficiency has a limited impact on increase utilization. There are few below ways…
Q: Hoosier Manufacturing operates a production shop that is designed to have the lowest unit production…
A: Find the given details below: Given Details: Designed Capacity (Maximum) 125 Units Per Hour…
Q: A manufacturer of printed circuit boards has a design capacity of 1,000 boards per day. The…
A:
Q: In an essay, suppose you are opening up an an Applebee's restaurant. describe short and long term…
A: Capacity is the greatest measure of work a bookkeeping practice is equipped for finishing in a given…
Q: Hoosier Manufacturing operates a production shop that is designed to have the lowest unit production…
A: Capacity utilization rate is the measure of the proportion of economic output actually realized…
Q: A copy center in an office building prepares bound reports for two clients. The center makes…
A: Given information, Client X Annual Demand = 2000 Standard processing time = 0.5 Average lot size…
Q: In view of capacity planning, define the efficiency and utilization with the examples of each…
A: Capacity planning is generally used to determine the kind of equipment capacities and the labor…
Q: What exactly is a balanced scorecard, and how does it relate to operations
A: A financial viewpoint is nothing other than a framework for translating an organization's strategic…
Q: A manager faces peak (weekly) demand for one of her operations, but is not sure how long the peak…
A:
Q: In December, RMO Manufacturing had Actual Output of 100 units. Its Effective Capacity dropped to…
A: Given, DESIGN CAPACITY = 200 UNITSEFFECTIVE CAPACITY = 120 UNITSACTUAL CAPACITY = 100 UNITS
Q: Capacity decisions should be made on the basis of:a) building sustained competitive advantage.b)…
A: A Small Introduction about Capacity Decision Capacity planning is a long-term decision that…
Q: A manager must decide which type of machine to buy, A, B, or C. Machine costs are as follows:…
A: Find the Given details below: Given details: Machine Cost ($) A 40000 B 30000 C 80000…
Q: Simple regression results from the data of Adriana Corporation are as follows: Equation: Overhead =…
A: Given Information: Regression equation: Overhead = 206469 + 45.83*Machine Hours
Q: A company has a factory that is designed so that it is most efficient (average unit cost is…
A: Given, Actual output = 15,000 units Maximum possible outputs produced in October = 10,925 units
20
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- A manufacturing shop is designed to operate most efficiently at an output of 550 units per day In the past month the plant produced 490 units. What was its capacity utilization rate last month?A manufacturing shop is designed to operate most efi ciently at an output of 550 units per day. In the past month the plant produced 490 units. What was its capacity utilization rate last month?. A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors would you recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain your reasoning.
- A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors should the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain .Show your calculations. Determine the utilization and the efficiency for each of these situations: A car wash operation processes an average of 60 cars per day. The operation has a design capacity of 100 cars per day and an effective capacity of 80 cars per day. A drive through fast food restaurant has been designed to handle 120 customers during lunchtime (12 to 2 PM) each day, but currently averages only 65 drive through customers at that time. Prior to the recession, when lines of customers were long, the restaurant actually handled a maximum of only 90 customers. Would you say that systems that have higher efficiency ratios than other systems will always have higher utilization ratios than those other systems? Explain.A process currently services an average of 49 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 65 percent of the current level in five years and management wants to have a capacity cushion of just 3 percent, what capacity requirement should be planned? The needed capacity requirement is customers per day. (Enter your response rounded up to the next whole number.)
- A process currently services an average of 61 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 70 percent of the current level in five years and management wants to have a capacity cushion of just 5 percent, what capacity requirement should be planned? The needed capacity requirement is nothing customers per day. (Enter your response rounded up to the next whole number.)Explanation of how the capacity analysis reacts to several processes running in simultaneously.Determine the utilization and the efficiency for each of these situations:a. A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day.b. A furnace repair team that services an average of four furnaces a day if the design capacity is six furnaces a day and the effective capacity is five furnaces a day.c. Would you say that systems that have higher efficiency ratios than other systems will always have higher utilization ratios than those other systems? Explain.
- P, Q, R, and S are four work centres in a series that belong to a manufacturing company. The figure below shows each center's individual capacity in units per day. Input Q (300) P (280) (350) (A) Determine the bottle neck centre. (B) Determine the system capacity. (C) Determine the system efficiency. RS (320) Actual Output (250)A company has a factory that is designed so that it is most efficient (average unit cost is minimized) when producing 15.000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant If the factory produces 10.925 units in October, what is the capacity utilization rate in October for this factory?A process currently services an average of 55 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 85 percent of the current level in five years and management wants to have a capacity cushion of just 5 percent, what capacity requirement should be planned? Part 2 The needed capacity requirement is enter your response here customers per day. (Enter your response rounded up to the next whole number.)