A manufacturing company intends to develop an application software for automating its design process. The task details associated to the project are shown in Table 1 below. The duration of each task follows a Beta distribution. Project crashing up to a maximum of 2 days per task is allowed, with the exception of tasks B and J, subject to the crash costs being met. Time (days) |Optimistic Most Pessimistic likely Task Task Details Preceding Task Crash Cost per day ($) High-level analysis. Selection of hardware platform. Installation and commissioning of hardware. Detailed analysis of core 2 Nil 700 B 1500 1500 10 12 D modules. 10 13 1500 Detailed analysis of supporting modules. Programming of core modules. Programming of supporting modules. H. E 10 12 1000 800 10 15 D 10 15 20 E 800 Quality assurance of core modules. 2 1000 Quality assurance (QA) of supporting modules. Core module training. Development and QA of accounting reporting. Development and QA of management reporting. M 2. G 1500 C,H 1500 E 1000 3 8. E 1000 Development of Management Information System. Detailed training. 500 3 8. 3 LJ,K, M 1200 (a) What is the probability of the project to complete in 52 days? What strategy can be used to improve the probability of completion? (b) Assuming that the manufacturing company wishes the project to be completed 5 days earlier than the minimum duration, what will be the additional cost involved? 6.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
A manufacturing company intends to develop an application software for automating
its design process. The task details associated to the project are shown in Table 1 below.
The duration of each task follows a Beta distribution. Project crashing up to a maximum
of 2 days per task is allowed, with the exception of tasks B and J, subject to the crash
costs being met.
Task Task Details
Time (days)
Optimistic Most
likely
Preceding
Task
Crash
Pessimistic
Cost
per
day ($)
A
High-level analysis.
7.
Nil
700
B.
Selection of hardware
platform.
2
1500
C.
Installation and
commissioning of
hardware.
Detailed analysis of core
modules.
1500
10
12
10
13
A
1500
Detailed analysis of
supporting modules.
Programming of core
modules.
E
6.
10
12
1000
F
800
10
15
D
Programming of supporting
modules.
Quality assurance of core
modules.
10
15
20
E
800
7
1000
Quality assurance (QA) of
supporting modules.
Core module training.
Development and QA of
accounting reporting.
L.
8
1500
1
2
C,H
1500
K
2
E
1000
Development and QA of
management reporting.
Development of
Management Information
System.
N Detailed training.
3
8
E
1000
M
500
3
8
L
L J, K, M
1200
3
8.
(a)
What is the probability of the project to complete in 52 days? What strategy can
be used to improve the probability of completion?
(b)
Assuming that the manufacturing company wishes the project to be completed 5
days earlier than the minimum duration, what will be the additional cost
involved?
6.
2.
Transcribed Image Text:A manufacturing company intends to develop an application software for automating its design process. The task details associated to the project are shown in Table 1 below. The duration of each task follows a Beta distribution. Project crashing up to a maximum of 2 days per task is allowed, with the exception of tasks B and J, subject to the crash costs being met. Task Task Details Time (days) Optimistic Most likely Preceding Task Crash Pessimistic Cost per day ($) A High-level analysis. 7. Nil 700 B. Selection of hardware platform. 2 1500 C. Installation and commissioning of hardware. Detailed analysis of core modules. 1500 10 12 10 13 A 1500 Detailed analysis of supporting modules. Programming of core modules. E 6. 10 12 1000 F 800 10 15 D Programming of supporting modules. Quality assurance of core modules. 10 15 20 E 800 7 1000 Quality assurance (QA) of supporting modules. Core module training. Development and QA of accounting reporting. L. 8 1500 1 2 C,H 1500 K 2 E 1000 Development and QA of management reporting. Development of Management Information System. N Detailed training. 3 8 E 1000 M 500 3 8 L L J, K, M 1200 3 8. (a) What is the probability of the project to complete in 52 days? What strategy can be used to improve the probability of completion? (b) Assuming that the manufacturing company wishes the project to be completed 5 days earlier than the minimum duration, what will be the additional cost involved? 6. 2.
Expert Solution
steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.