Fundamentals Of Construction Estimating
4th Edition
ISBN: 9781337399395
Author: Pratt, David J.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 16, Problem 4RQ
Prepare a typical bay estimate based on the following information:
a. Bay size of
b. There are 50 bays in the building.
c. Unit prices:
• Concrete piles: $950.00 each
• Concrete pile caps: $725.00 each
• Slab-on-grade: $12.50 per sq. ft.
• Structural steel frame: $4.90 per sq. ft.
• Roof structure: $10.75 per sq. ft.
• Roofing: $8.20 per sq. ft.
• Plumbing & HVAC: $9.80 per sq. ft.
• Electrical: $6.10 per sq. ft.
• Exterior foundations: $100.00 per linear ft.
• Exterior walls: 728.00 per linear ft.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Note:
Library Live Load = 2.9 KpaOffice = 4. 8 KpaExterior Balconies = 2.9 Kpa
What is pipe piles
how did you get 1.025 for solving the pre consolidation?
Chapter 16 Solutions
Fundamentals Of Construction Estimating
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings. a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390. b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.arrow_forwardHow soil is compressed below the pile toe and dragged down along the sides of a pile during installation?arrow_forwardGiven the mass diagram points and information shown below, what is the total cost of earthwork for this project? Fill the table below: Free haul distance = 0.30 miles, Cost of Excavation = $10/yd3 Max. Overhaul distance = 1 mile, Borrow/Waste = $5/yd3 Overhaul = $1.50/sta.-yd. 3000 1800 2000 1200 1000 1200 1000 1000 1000 50 50 200 -100 O+00 2+00 4+00 6+00 8+00 10+00 12+00 14+00 16+00 18+00 20+00 22+00 24+00 26+00 28+00 30+00 -1200 -1200 1000 -2000 -2500 -2500 -3000 -3000 4000 Distance (stations) Cumulative Volume (yd")arrow_forward
- 4.145 - please show complete solution, thanks!arrow_forward7. Given: A centerline of 250 LF; Anchor Blots @ 48" OC; 2-doors; 8 corners. Calculate the number of anchor blots needed.arrow_forwardDetermine the cost estimate for hundred stories building with a footprint of 150' x 200' each floor. Assume mat foundation 5 feet and all floors slabs are 12" thick. Assume concrete estimationarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License