You have a project to be completed in 12 months, and the budget of the project is R100, 000. 6 months have passed, and R60, 000 has been spent., but on closer view you find that only 40% of work has been completed so far. Given in question : Actual cost (AC) =R60 000 Earned Value (EV) =40% of R100 000 =R40 000 Find the project's cost varience (CV) and determine if you are under budget or over budget.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
icon
Concept explainers
Topic Video
Question

IT PROJECT MANAGEMENT:EX

2.4 You have a project to be completed in 12 months, and the budget of the project is R100, 000. 6 months have passed, and R60, 000 has been spent., but on closer view you find that only 40% of work has been completed so far.

Given in question :

Actual cost (AC) =R60 000

Earned Value (EV) =40% of R100 000

=R40 000

Find the project's cost varience (CV) and determine if you are under budget or over budget.

Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,