Which of the following interpretations would be best for the scenario analysis results shown below? Worst- case PW (18%) -$650,000 IRR 2.10% Most- likely case Best-case $58,000 $2,660,000 14.60% 33% a. Since the most-likely case has a PW < 0, the project should be abandoned immediately b. Since the worst-case has a negative present worth, this project must be rejected. c. Since the average of the three cases is a positive present worth, the project is

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question
Which of the following interpretations would be best for the scenario analysis results shown
below?
Worst-
case
PW (18%) -$650,000
IRR
2.10%
Most-
likely case Best-case
$58,000 $2,660,000
33%
14.60%
a. Since the most-likely case has a PW <0, the project should be abandoned
immediately
b. Since the worst-case has a negative present worth, this project must be rejected.
c. Since the average of the three cases is a positive present worth, the project is
acceptable.
d. Because only one of the scenarios shows the project as profitable, the project
should be considered very risky, and, if accepted, should be subject to greater
scrutiny in its planning and forecasting.
Transcribed Image Text:Which of the following interpretations would be best for the scenario analysis results shown below? Worst- case PW (18%) -$650,000 IRR 2.10% Most- likely case Best-case $58,000 $2,660,000 33% 14.60% a. Since the most-likely case has a PW <0, the project should be abandoned immediately b. Since the worst-case has a negative present worth, this project must be rejected. c. Since the average of the three cases is a positive present worth, the project is acceptable. d. Because only one of the scenarios shows the project as profitable, the project should be considered very risky, and, if accepted, should be subject to greater scrutiny in its planning and forecasting.
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Environmental Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning