The manufacturing cycle efficiency for NUBD Company when the processing time is nine hours and inspection, waiting, and move time are one hour each is: (round-off to 2 decimal places)
Q: It is always possible to balance an assembly line so that it operates at 100% efficiency true or…
A: Assembly line is a manufacturing process in which parts are added as semi-finished moves form…
Q: An assembly line must be designed to produce 40 containers per hour. The following data give the…
A: Given - Desired output= 40 containers per hour Total Operating Time = 1 hour= 60 min ×60 sec = 3600…
Q: Bill builds benches in a small shop and he plans to operate five 8-hour days perweek. Each bench has…
A: Lead Time Lead Time is the time is passed from the inception of the production to the end of it. It…
Q: For each of the following variables, explain the differences (in general) as one movesfrom a work…
A: The throughput time of a product decreases as it moves from a work center environment to the…
Q: The grouping of equipment with respect need layout O a. cellular O b. product O c. fixed-position O…
A: Answe is option(e)
Q: Jsing the Method of Least Squares, calculate the fixed cost of leasing. Round the fixed cost to the…
A: The Least-Squares regression model is a statistical technique. It is used to estimate a linear total…
Q: etters Cabinets, Inc., needs to choose a production method for its new office shelf, the…
A: Given that: Volume of output (Q) = 24000 units Per unit selling price(SP) = $120
Q: In-process inventory is less in product layout. Select one: O a. False b. True
A: True
Q: e) How much total idle time is present each cycle? f ) What is the efficiency of the assembly line…
A: Below is the solution
Q: Evaluate the available data and propose the number of operators that must be arranged to perform…
A: Capacity indicating measurements of the maximum available rate of a production or a process.…
Q: A.J.’s Wildlife Emporium manufactures two unique birdfeed-ers (Deluxe and Super Duper) that are…
A: (a) The production priority will be decided based on the contribution margin of each product.…
Q: Use the process flow diagram below for an assembly line. Station C Station A Station B Station D…
A: A process flow diagram helps to identify the flow of a process through developing the activities and…
Q: The trim line at PW is a small subassembly line that, along with other such lines, feeds into the…
A: Note-We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: The company is developing a new product that will incorporate subassembly C. As part of the…
A: In the above project if a new product is added, requiring extras subassembly C. Now the earliest…
Q: Consider three different techniques to formulating system requirements: the classic approach, the…
A: Note: "We'll answer the first question for you because you've requested many questions. Please…
Q: XYZ is famous for homemade pizzas which are crisp with thin crust and varied toppings giving the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The manufacturing cycle efficiency for NUBD Company when the processing time is seven hours and…
A: Throughput time is the total actual time incurred during the production of the product in an…
Q: The manufacturing cycle efficiency for Sam Company when the processing time is seven hours and…
A: Throughput time is the total actual time incurred during the production of the product in an…
Q: Mr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean…
A: This question is about assembly line balancing, here, There are 10 steps to produce the piece of…
Q: What is the effect of waiting time on a manufacturing process? Why is it good to reduce waiting…
A: Waiting time essentially affects producing measure. The longer the cycle is in pausing, the higher…
Q: A production line with four automatic workstations (the other stations are manual) produces a…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: 1. Calculate the total time it takes to produce a batch of 10 units using the traditional…
A: Instead of grouping work items into batches, continuous flow is a Lean strategy that allows you to…
Q: Dell Computer’s primary consumer business takes orders from customers for specific configurations of…
A: Manufacturing process: The manufacturing process is the sequence of steps that transforms the…
Q: First question in the image Question N0 2: A production line has an hourly throughput rate 6…
A: Given data - Task A Task B Processing time (Min) 9 12 No. of worker 1 1
Q: Explain the term traditional assembly line operations? how are these operations efficient?
A: Managers are in a charge of overseeing the operation and other stages involved in creating a product…
Q: Fair Child Enterprises SAOG is new a garment manufacturing organization designing clothes for school…
A: While considering the production decisions, there are various manufacturing strategies, with each…
Q: Explain why and how a firm measures process capacity
A: Process capacity is the output generated by a machine/worker under expected working conditions and…
Q: Of the following process types, ________ has the lowest output variety, and the highest output…
A: The operations management process can be divided into four groups based on how they are performed.…
Q: A production process consists of a three-step operation. The scrap rate is 10 percent for the…
A: Given that,Scrap rate at step-1 = 10% = 0.10Scrap rate at step-2 = 6% = 0.06Scrap rate at step-3 =…
Q: Can you create a process and value stream map for a house cleaning service?
A: Instructions to Create a Value Stream Map Your organization has as of late changed to the Lean…
Q: A process has 2 steps: Step A and Step B. The stage capacities of the two steps are listed in the…
A: Here the process has 2 steps, step A and step B, for each step, we have the stage capacity, to…
Q: A.J.’s Wildlife Emporium manufactures two unique birdfeed-ers (Deluxe and Super Duper) that are…
A: Bottleneck in a process refers to the input who's limited capacity can reduce the capacity of the…
Q: Fair Child Enterprises SAOG is new a garment manufacturing organization designing clothes for school…
A: The capacity to change production ability to change client needs without expanding fabricating costs…
Q: Assume the processing time of Welding is reduced to 6 minutes, while the times of the other…
A: Instead of grouping work items into batches, continuous flow is a Lean strategy that allows you to…
Q: A manufacturing plant has the process displayed below. The drilling operation occurs separately from…
A: A) Bottleneck Bottleneck is the cycle or a stage that restricts a whole framework's ability to…
Q: a)Provide one relatable and relevant example of five of the eight wastes under Lean systems which…
A: A Lean system involves Lean principles to plan, prioritize, manage, and measures work. The motive…
Q: 1. Aljon, a softdrink dealer, delivers 14 cases on Monday, 10 cases on Tuesday, 12 cases on…
A: No. of cases delivers on Monday =14 No. of cases delivers on Tuesday = 10 No. of cases delivers on…
Q: Compute the cycle time for Sunburn Pharmaceuticals given the following data: set-up time, 2 hours;…
A: Given, Set up time= 2 hours Process time= 10 hours Move time = 80 minutes=1.3 hours Wait time =20…
Q: Purple Swift manufactures birdhouses in lots of 10. Eachbirdhouse takes 45 minutes to paint. After…
A: Utilization = Average Output Rate / Maximum Capacity Utilization = [(Number of lots x Setup Time) +…
Q: Coleman Rich, Ltd., has received the followingorders:Period 1 2 3 4 5 6 7 8 9 10Order size 60 30 10…
A: Given Usable minutes in a week - 2250 minutes Each unit takes 65 minutes to complete
Q: A firm uses a serial assembly system and needs answers to the following:a. An output of 900 units…
A:
Q: What is difference between assembly plant compared to more typical auto assembly plants? Why do you…
A: Below is the solution:-
Q: 3. A production line must produce 2,500 units every 6 hours of operating time. What is its cycle…
A: Cycle time = Total available time / Output
Q: T. Smunt Manufacturing Corp. has the process displayed below. The drilling operation occurs…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: The following diagram describes a manufacture process where products go through four parallel…
A: Bottleneck activity defines as the process that reduces the limited capacity of the whole chain. The…
Q: The trim line at PW is a small subassembly line that, along with other such lines, feeds into the…
A: THE ANSWER IS AS BELOW:
Q: Weekly production requirements of a product are 1000 items. The cycle time of producing one product…
A: Required number of machinery is the proportion between Total machinery hours required to produce…
The manufacturing cycle efficiency for NUBD Company when the processing time is nine hours and inspection, waiting, and move time are one hour each is: (round-off to 2 decimal places)
Step by step
Solved in 2 steps
- The manufacturing cycle efficiency for NUBD Company when the processing time is seven hours and inspection, waiting, and move time are one hour each is: (round-off to 2 decimal places)Guesstimate how much work-in-process inventory they would expect to see in a production line that produces ambulances.C&A Furniture uses a four-step process to make its famous wood table: Processing Time Process Milling Table top Milling Table stand Assembly Finishing The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands. If the batch size is 10, what is the capacity of the process in tables per minute? A) 0.077 B) 0.05 C) 0.067 10 5 15 20 D) 0.048
- TRX company involved with purely manual assembly process is planning to produce 820 units of output per month. The standard time for the product is 115 min per unit. The company is currently employing 6 workers and having a working period of 8 hours per day with 24 days per month.Average salary for each worker is RM1850 per month. Evaluate the available data and propose the number of operators that must be arranged to perform the overtime work daily in order to meet the production output. The overtime is executed 3 hours every day over the 24 days periodUp, Up, and Away is a producer of kites and wind socks.Relevant data on a bottleneck operation in the shop for theupcoming fiscal year are given in the following table:Item Kites Wind SocksDemand forecast 30,000 units/year 12,000 units/yearLot size 20 units 70 unitsStandard processing time 0.3 hour/unit 1.0 hour/unitStandard setup time 3.0 hours/lot 4.0 hours/lotThe shop works two shifts per day, 8 hours per shift, 200 daysper year. Currently, the company operates four machines,and desires a 25 percent capacity cushion. How many ma-chines should be purchased to meet the upcoming year’s de-mand without resorting to any short-term capacity solutions?1. Define and discuss the advantages and disadvantages the following Process Strategies: Make-to-Stock Make-to-Order Assemble-to-Order
- XYZ is famous for homemade pizzas which are crisp with thin crust and varied toppings giving the pizzas fabulous tastes. XYZ· is revamping its order processing and pizza-making process. In order to deliver fresh pizza fast, six work elements must be completed as shown in the table below :Element Description Precedence Time (in min)A Receive order - 2·0B Shape dough A 1·0C Prepare toppings A 2·0D Assemble pizza B, C 3·0E Bake pizza D 3·0F Deliver pizza E 3·0Construct a precedence diagram for the process.If the demand is 120 pizzas per night (5:00pm to 1:00am), compute the cycle time for the process. Compute the lead time for the process.What is the theoretical minimum number of workstations needed to achieve the required production?How will you balance the production line to produce and deliver 120 pizzas per night? What is the actual minimum number of workstations needed?3C * 08 IN HI F. R %24 O 0O #3 w/ Loans are evaluated in a process with two resources. The first resource has a capacity of 30 loans per hour. The capacity of the second resource is 38 loans per hour. Demand for this process is 40 loans per hour. Instruction: Round your answer to three decimal places. minutes What is the cycle time of this process (in minutes)? raw 6 jo 6 I!! Wellington aranormal ESTAURANT As We S Pam & Tommy Stars and Pahkitew Island The Afterparty Restaurant: My 600-lb Life Scissor Seven étv 8,424 MAR LORZ 67 OOO O0O DD F5 F4 & 24 9- %23 5 9 7. 4. } 1 D. K. 71 S. B.A.J.’s Wildlife Emporium manufactures two unique birdfeeders (Deluxe and Super Duper) that are manufactured and assembled in up to three different workstations (X, Y, Z) using a small batch process. Each of the products is produced according to the flowchart in Figure. Additionally, the flowchart indicates each product’s price, weekly demand, and processing times per unit. Batch setup times are negligible.A.J. can make and sell up to the limit of its weekly demand and there are no penalties for not being able to meet all of the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $16 per hour. The plant operates 40 hours per week, with no overtime. Overhead costs are $2,000 per week. Based on the information provided, as well as the information contained in the flowchart, answer the following questions. a. Using the traditional method, which bases decisions solely on a product’s contribution to profits and overhead, what is the…
- Amy Xia's p lant was designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day because of the time needed to change equipment betweenstyles of hammers. What is the utilization?3. A bread-manufacturing line typically produces 150 loaves of bread during an 8-hour shift. On average, there are 30 loaves under processing in the line at any given time. What is the value and what is the L value? What is the average time it takes to produce a loaf of bread from the raw ingredients?The following table shows the process times in minutes (or minutes/unit - how many minutes to process one unit) of a six-station serial production line (1-2-3-4-5-6). Station 1 2 3 4 5 6 Which station(s) is (are) the bottleneck(s)? Station 2 Station 5 Stations 3 and 4 Stations 2 and 5 Process Time (minutes/unit) 8 11 7 7 11 4