The higher levels of the work breakdown structure (WBS) represent increasing amounts of detail while the lower levels represent broad categories of activities. True or False True False

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The higher levels of the work breakdown structure (WBS) represent increasing amounts of detail while the lower levels represent broad categories of activities. True or False
True
False
 
 
 

Duration is defined as the time from the beginning to the end of an activity. True or False
 
 
 
 
 

A common resource constraint is availability. True or False
 
Group of answer choices
True
False
 
 
 

The _____ schedule is a summary level schedule that encompasses the entire project scope.
 
Group of answer choices
original
milestone
procurement
master
conceptual
 
 
 
Which of the following is NOT true about a master schedule?
 
Group of answer choices
If the project is chosen, a master schedule is created.
It has major events and dates such as starting date, important events, and the completion date.
The master schedule is rarely part of a contract.
Changes to the schedule must be approved using a documented change process with approval by the project sponsor and client.
To execute the schedule, the major activities are broken down into smaller activities and resources are assigned to those activities.
 
 
 

The project work breakdown structure (WBS):
 
Group of answer choices
developed around the functions of the project facilitates the understanding of the amount of work required for each stage of the project.
represents a breakdown of the project into components that encompasses a part of the scope of the project.
size is directly related to the duration of each of the activities of the project.
represents increasing amounts of detail at its highest level while the lower levels represent broad categories.
is a hierarchical listing and grouping of the project activities required to produce the deliverables of the project.
 
 
 

Which of the following is true about a work breakdown structure (WBS)?
 
Group of answer choices
Developing a WBS begins by defining and developing lists of all activities needed to accomplish the work of the project.
The first draft of the WBS includes activities at the low-level.
The first draft of the WBS typically includes the minor activities required to accomplish the deliverables identified in the project scope of work.
The WBS is decomposed to the level that the client needs to control the project.
Typically, smaller and simpler projects require more detailed WBS.
 
 
 

A(n) _____ has no duration or resources, and is simply an indicator of an important point in the project.
 
Group of answer choices
node
milestone
inference
hierarchy
attribute
 
 
 

To consider the availability of team members, consultants, and key pieces of equipment, you can create a(n) _____ which indicates working days and days off for a group or individual.
 
Group of answer choices
resource calendar
project calendar
task calendar
hierarchical calendar
base calendar
 
 
 

The relationship between a predecessor activity and a successor activity is called a(n) _____.
 
Group of answer choices
series
pattern
dependency
association
aggregation
 
 
 

Activities that have predecessor-successor relationships occur _____.
 
Group of answer choices
sequentially
concurrently
intermittently
sporadically
suddenly
 
 
 

 
If activities must begin at the same time, they have a _____ relationship.
 
Group of answer choices
finish-finish
sequential
finish-start
periodic
start-start
 
 
 

Lead time is _____.
 
Group of answer choices
the amount of time that separates the finish of one activity and the beginning of the next activity
greater for concurrent activities that end at the same time
a sequence of activities where the first activity must end before the next activity can begin
the amount of time that the start of the next activity can overlap the finish of its predecessor
lesser for concurrent activities that begin at the same time
 
 
 

The Gantt chart _______________________.
 
Group of answer choices
is usually difficult to read and analyze.
is also called a PERT chart.
is used to indicate duration and relationships between project activities.
illustrates complex relationships well.
is a time-scaled graphic that represents each activity with connected straight line segments.
 
 
 

All of the following are techniques project managers can use to accelerate the project schedule, EXCEPT:
 
Group of answer choices
improving quality.
reassigning resources.
changing the scope.
adding additional resources.
using contingency resources
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Production Plant
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.