The following activities were identified as being on the critical path of a large project. The project manager wishes to reduce the completion time by three weeks. Which activity should be crashed 2nd? Activity A B C D O C OA a Normal Time (Weeks) 8 8 10 6 Normal Cost $1750 $4200 $4700 $2000 Crash Time (Weeks) 7 4 8 4 Crash Cost $2200 $6600 $5700 $4000
Q: 2. A economic order quantity problem (EOQ) has a daily demand rate = 10 (where demand is over every…
A: Daily demand rate = 10 unitsEconomic Order quantity (EOQ) = 4526 units
Q: The excess cost of an item is the profit you would have made on it. True False
A: Financial management is a significant part of running any association, whether it's a business,…
Q: Southland Corporation's decision to produce a new line of recreational products has resulted in the…
A: Find the given details below:
Q: What strategies would you employ to communicate the need for change in purchasing to the various…
A: The objective of this question is to identify effective strategies for communicating the need for…
Q: Question 1Data Warehouses and Data MartsWrite a one- to two-page (250-500 word) paper that discusses…
A: “Since you have posted multiple questions, we will provide the solution only to the first question…
Q: Topic: Purchasing Strategy Detail: Spartan Heat Exchangers Inc. On June 10, Rick Coyne, materials…
A: An organization's strategy is a blueprint for decisions that outline its goals and objectives,…
Q: product has a fixed dail
A:
Q: Strategok Supply Chain Management Canvas BY JAVIER Plan Efficiency (Eliminate or Reduce) Design…
A: The supply chain is the aspect of production management that is concerned with moving products and…
Q: A quality assistant is currently conducting a control process in battery production by inspecting…
A: The objective of the question is to calculate the Upper Control Limit (UCL) and Lower Control Limit…
Q: Centerville Bikes and Stuff (CBS) sells motorcycles and accessories. The number of helmets sold by…
A: WeekValue 117214315412516615
Q: ABC Company, a well-established tech company, is gearing up for the launch of a new line of…
A: Marketing strategies play an essential role in building the customer base, attracting the attention…
Q: Average Shortest processing time The SPT sequence is 5 Average Flow Time 26.40 Average Earliest due…
A: JobProcessing TimeDue date12322272831326410155513
Q: The product structure for product X is illustrated below. Level 0 + 4 Level 1 + Level 2 + Level 3…
A: Product structure tree- PartLead TimeUnit RequiredB12C11D34H22K32M22N34X31Z42
Q: What services might the internal audit function provide in lieu of performing an assurance…
A: The internal audit function forms a vital component of most governance models applied by…
Q: Change the ordering simulation so that emergency orders are never made. If demand in any week is…
A: An order simulation is a simulation that represents the procedure of ordering products and the…
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements…
A: The average monthly demand is computed as shown below:Average monthly demand = Average of demands…
Q: Distinguish between Store Layout and Store Design.
A: The objective of this question is to differentiate between two key concepts in retail operations…
Q: The optimal assignment of taxis to customers that minimizes the distance is: Customer A
A: The distances, in miles from the waiting taxis to the customers are given below:Here, 1 customer can…
Q: Advanced) In some countries, there are restrictions on the length of a contract to rent an…
A: Business law is the aspect of the law that describe all the rules, regulation, and, laws that are…
Q: A YouTube advertisement has received a CPM of $20. The amount of people that have seen this ad is…
A: CPM stands for Cost per Mille, also known as cost per thousand (CPT). It is a marketing term used to…
Q: Explain the impact of CRM on supply chain optimization and vendor relationship management.
A: Customer Relationship Management (CRM) systems have a significant impact on supply chain management…
Q: Disuss five benefits of corporate social responsibility.
A: The objective of this question is to understand the benefits that a corporation can derive from…
Q: Adham is the HR manager at XYZ Company since 2013. Adham successfully performs various HR activities…
A: Human resource practices are the aspect of the human resource department that deals with the…
Q: For the past month, the plant in Problem S7.1, which ctive capacity of 6,500, has made only 4,500…
A: Effective capacity is the maximum amount of work that an organization is capable of completing in a…
Q: A company produces motor cycle seats. The company has two production lines. The production rate for…
A:
Q: The Carbondale Hospital is considering the purchase of a new ambulance. The decision will rest…
A:
Q: Evaluate a range of approaches to continuous quality improvement.
A: Continuous Quality Improvement (CQI) is a management philosophy that organizations use to reduce…
Q: Ram Roy's firm has developed the following supply, demand, cost, and inventory data. Period 1 2 3…
A: The greatest output that can be reached in the manufacturing of manufactured items is referred to as…
Q: The network diagram and task times for a project are shown below. Task A₁ A2 A₁ A2 A3 Duration…
A: 1. Take the ES of the initial activity as 0. 2. Add duration to this to get EF. 3. This EF will…
Q: 1. Identify and explain four stakeholders and the key role they played in company annual community…
A: The objective of the question is to identify and explain the roles of four key stakeholders in a…
Q: During the recent pandemic, the seaport in Savannah Georgia, the third busiest in the United States,…
A: The objective of the question is to calculate the average number of ships waiting to be unloaded at…
Q: In the following table the activities with their precedence sequence and expected time (days) are…
A: The time span required to complete a certain project is referred to as the project duration. It is a…
Q: The plant manager, Murat Kristal, at York Technologies makes Aircraft Navigation Systems. He expects…
A: Inventory turnover measures how many times a company's inventory is sold and replaced over a…
Q: MS Company is a Trading Company involved in Import and export trade. With various suppliers from…
A: The objective of the question is to provide advice to MS company on the correct procedure for making…
Q: d) Suppose that a second drilling machine is added, and it takes the same time as the original…
A: As per the instruction, I will solve the sub-parts d) and e)The drilling operations happen…
Q: A farmer in Wood County has 730 acres of land. She is going to plant each acre with corn, soybeans,…
A: The information provided is stated in the table below:CornSoyabeanWheatAvailabilityLabor…
Q: How can organizations foster a culture that encourages ongoing planning and adaptability, especially…
A: A key to success in the dynamic field of product management is developing an effective roadmap. It…
Q: Janet's Bouquets stocks fresh-cut flower bouquets on a weekly basis that sell for $60 each and have…
A: 5 demand states are possible-75,80,85,90,95Similarly we can have 5 order quantities=75,80,85,90,95
Q: tives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive,…
A: Determine the given solution CostGeneral purpose equipment (GPE)Flexible manufacturing…
Q: Staffing is a critical component of organizational success, encompassing the identification,…
A: Successive organizations are required by law to be able to ensure long term success through the…
Q: The first, and perhaps most important, step in constraint management is to the most pressing…
A: The query relates to constraint management and highlights the importance of taking the first step in…
Q: Why is it important for project managers to understand the strategy of the organization that uses…
A: Project management is the art and science of co-ordinating and leading people in order that they…
Q: Develop a payoff matrix - Is there a saddle point? - Determine the promotion strategies of firm A…
A: Promotional strategies refer to the various methods and approaches that businesses use to promote…
Q: bank's mortgage department must process the following six jobs to maximize client satisfaction.…
A: JobProcessing TimeDue date12322272831326410155513
Q: Fresco Inc. manufactures sour pops annually which requires 0.4 kilograms of raw material. The…
A: Annual demand of sour pops = 1,600,000 unitsRaw materials required per unit of sour pops = 0.4…
Q: Q.1. a) Explore the security concerns commonly associated with warehousing and inventory…
A: The objective of this question is to identify and discuss the security concerns that are commonly…
Q: What is meant by the connected and automated/ autonomous vehicle (CAV) concept? List some of its…
A: Technology refers to the practical application of scientific knowledge, skills, methods, and…
Q: The following table gives the number of pints of type A blood used at Damascus Hospital in the past…
A: where,
Q: An important application of regression analysis in accounting is in the estimation of cost. By…
A: Production Volume (Units)Total Cost ($)400410045050005505300600590070063007506900
Q: The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table…
A: MRP shows the quantity and timing of materials required for production MRP Table:Consider…
Note:-
- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
- Answer completely.
- You will get up vote for sure.
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 5 images
- Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 44 33 $ 2 comma 100$2,100 $ 2 comma 700$2,700 long dash— B 22 11 $ 2 comma 200$2,200 $ 2 comma 900$2,900 long dash— C 33 33 $ 500$500 $ 500$500 long dash— D 88 44 $ 2 comma 500$2,500 $ 2 comma 820$2,820 A E 66 33 $ 1 comma 000$1,000 $ 1 comma 300$1,300 B F 33 22 $ 3 comma 400$3,400 $ 4 comma 800$4,800 C G 44 22 $ 1 comma 500$1,500 $ 2 comma 000$2,000 D, E Part 2 a) Based on the given information…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 4 3 $2,000 $2,650 — B 2 1 $2,100 $2,900 — C 3 3 $750 $750 — D 8 4 $2,300 $2,620 A E 6 3 $900 $1,275 B F 3 2 $3,200 $4,700 C G 4 2 $1,400 $1,900 D, E I have answers for the frist part of the question: a) Based on the given information regarding the activities for the project, the project length = 16 weeks. b) The total cost required for completing this project on normal time = $12,650. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Activity Time (weeks) Time (weeks) A B с D E F G 4 2 3 8 6 3 4 3 1 3 4 3 2 2 a) Based on the given information regarding the activities for the project, the project length = Normal Cost $2,000 $2,300 $600 $2,300 $900 $3,200 $1,500 weeks. Total Cost with Crashing Immediate Predecessor(s) $2,650 $2,900 $600 $2,600 $1,200 $4,400 $1,900 A B C D, E
- Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 4 3 $2,000 $2,650 — B 2 1 $2,100 $2,900 — C 3 3 $750 $750 — D 8 4 $2,300 $2,620 A E 6 3 $900 $1,275 B F 3 2 $3,200 $4,700 C G 4 2 $1,400 $1,900 D, E a) Based on the given information regarding the activities for the project, the project length = 16 weeks. b) The total cost required for completing this project on normal time = $12,650. c) For reducing the duration of the project by one…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 4 3 $2,100 $2,750 — B 2 1 $2,300 $3,100 — C 3 3 $600 $600 — D 8 4 $2,400 $2,720 A E 6 3 $1,000 $1,450 B F 3 2 $3,000 $4,400 C G 4 2 $1,500 $2,000 D, E a) Based on the given information regarding the activities for the project, the project length = enter your response here weeks. b) The total cost required for completing this project on normal time = $enter your response here. c) For…Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost ABCDEFG 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,100 $2,300 $600 $2,400 $800 $3,400 $1,400 Total Cost with Crashing Immediate Predecessor(s) $2,750 $2,900 $600 $2,680 $1,100 $4,600 $1,900 a) Based on the given information regarding the activities for the project, the project length b) The total cost required for completing this project on normal time = $ 13000. | | A B C D, E = 16 weeks. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 70. d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the…
- Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 4 3 $2,100 $2,800 — B 2 1 $2,300 $3,100 — C 3 3 $600 $600 — D 8 4 $2,400 $2,680 A E 6 3 $1,000 $1,450 B F 3 2 $3,200 $4,600 C G 4 2 $1,400 $2,000 D, E Part 2 a) Based on the given information regarding the activities for the project, the project length = enter your response here weeks.A project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90) a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?
- Paul Silver, owner of Sculptures International, just initiated a new art project. The following data are available for the project: Activity Time (days) Activity ABCDE 43424 Immediate Predecessor(s) | | < C, DDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250 B F 3 2 $3,200 $4,400 C G 4 2 $1,400 $1,800 D, E a) Based on the given information regarding the activities for the project, the project length = _______ weeks ? b) The total cost required for completing this project on normal time = _______ ? c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost? The critical path with the longest length through the project is _______ ? Note:- Do not provide…2:30 PM ě 0.3KB/s 1ll 54 4G+ 00:15:12 Remaining Multiple Choice The primary difference between PERT and CPM is that CPM uses probabilities on the activity times and PERT does not. O. PERT considers activity costs and CPM does not. PERT can assign probabilities to activity times and CPM does not. CPM considers activity costs and PERT does not. 5 of 20 II