Q2) (Project Management) Table given below contains information about an environmental clean-up project. Shorten the project three weeks by finding the minimum- cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity A B C D E F G H I Normal Time (weeks) 7 12 7 6 1 1 3 3 2 Crash Time (weeks) 6 9 6 5 1 1 1 2 2 Cost to Crash ($ per week) 200 250 250 300 200 350 Immediate Predecessor(s) None None A A B C, D D, E F, E G

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Note:-

  • Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
  • Answer completely.
  • You will get up vote for sure.
Q2) (Project Management) Table given below contains information about an
environmental clean-up project. Shorten the project three weeks by finding the minimum-
cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify
activities to crash while minimizing the additional crash costs.
Activity
A
B
CDEFGHI
с
D
G
H
Normal Time
(weeks)
7
12
7
6
1
1
3
3
2
Crash Time
(weeks)
6
9
6
5
1
1
1
22
2
2
Cost to Crash
($ per week)
200
250
250
300
200
350
Immediate
Predecessor(s)
None
None
A
A
B
C, D
D, E
F, E
G
Transcribed Image Text:Q2) (Project Management) Table given below contains information about an environmental clean-up project. Shorten the project three weeks by finding the minimum- cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity A B CDEFGHI с D G H Normal Time (weeks) 7 12 7 6 1 1 3 3 2 Crash Time (weeks) 6 9 6 5 1 1 1 22 2 2 Cost to Crash ($ per week) 200 250 250 300 200 350 Immediate Predecessor(s) None None A A B C, D D, E F, E G
Expert Solution
steps

Step by step

Solved in 5 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.