Jse the given tasks and predecessors for this problem. The required cycle time is 25 seconds and casks are assigned to workstations using the "longest task time" rule to break any ties. If task A is assigned to Workstation 1, what is the next task that should be assigned to Workstation 1? (slide 28) Task Time (sec) Predecessor(s) A 20 none B 30 10 D 20 В. С O Task B
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: Assembly line helps in assigning each task to each workstation and worker, where no machine can be…
Q: 3- A production process at Kenneth Day Manufacturing is shown in the following Figure The drilling…
A: Given- Sawing operation = 6 units/hrSanding operation = 6 units/hrDrilling operation = 2.4…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: The entries in the table denote the costs of assigning a task to a particular person. The plant…
A: Here, I would apply the Hungarian method to this assignment problem, we could see the cost element…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: b) The cycle time for the production of a chair = 9.23 minutes (round your response to two decimal…
A: Cycle time is the actual time that a worker spends in the workstation to produce an item.
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given that: Task Duration (in mins) A 2.73 B 2.01 C 2.13 D 2 E 2.61 F 2.71 G 2.95
Q: What is the Theory of Constraints? Describe critical chain scheduling as an application of the…
A: Below is the solution:-
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Required cycle time = Available time / No. of units to produce =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: evelop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.…
A: The Precedence Diagram given below: A D F B C…
Q: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of…
A: THE ANSWER IS AS BELOW:
Q: A local toy manufacturer is using a production line that runs hours per day and produces a toy that…
A: The answer is as follows:
Q: This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the…
A:
Q: Francis Johnson's plant needs to design an efficient assembly line to make a new product. The…
A: This Line balancing Problem, it falls under Business- Operations Management, For this problem, I…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Cycle time is 15.14 minutes
Q: The desired daily output for an assembly line is 540 units. This assembly line will operate 720…
A: Line balancing is a process which allocate activity to right workstation based on different…
Q: A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4…
A: Answer: In this mentioned problem, a job has three elemental tasks. Cycle time is the maximum amount…
Q: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of…
A: The FCFS and EDD analysis is as follows:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given - A local toy manufacturer is using a production line that runs 8 hours per day and produces a…
Q: Stanford Rosenberg Computing wants to establish anassembly line for producing a new product, the…
A: Note: As per the Bartleby guidelines, only the first three parts have been answered.
Q: Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that…
A: Required cycle time = Available time / No. of units to produce =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: The answer is below:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the…
A: Given information Task Time Immediate Predecessors A 12 B 15 A C 8 A D 5 B, C E 20…
Q: You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units…
A: Given data is,
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Cycle time is the total actual time spend to produce an item in the production process.
Q: MMS Associates is a telecommunications service provider.Th e company is currently redesigning its…
A: The load-distance technique is a mathematical model for evaluating sites based on their proximity to…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given that: Output= 90 toys Production time = 8 hours per day
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: Compute the cycle time and minimum number of workstations required b- Draw the precedence diagram
A: Note - Since you have posted a question with multiple sub-parts, we will solve first three subparts…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: The answer is as follows:
Q: • A producer of inkjet printers is planning to add a new line of printers, and you have been asked…
A: 1) Predecessor Diagram
Q: A manufacturing company is designing an assembly lineto produce its main product. Th e line should…
A: A bottleneck arises in a production system when workloads exceed the capacity of the manufacturing…
Q: A group of six jobs is to be processed through a two-machine flow shop. The first operation involves…
A:
Q: The desired daily output for an assembly line is 540 units. This assembly line will operate 720…
A: workstation cycle time = Available Production time / Customer Demand Available Production time =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using:Cycle time = Available time / Desired output
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Francis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in th following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME (MINUTES) IMMEDIATE PREDECESSOR rint TASK A 2.0 B 2.0 3.0 1.0 А, В, с 3.0 2.0 G 3.0 b. What is the workstation cycle time required to produce 15 units per hour? (Round your answer to 1 decimal place.) Workstation cycle time minutes d. Balance the line to use the fewest possible workstations to meet the cycle time found in part b. Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part b? (Round your answer to 1 decimal place.)d. What is the efficiency of your line balance? Use the theoretical minimum number of workstations in your calculation. (Round your answer to 1 decimal place.) Efficiency
- The Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation. The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 3,000 bottles of this product. TASK TIME (MINUTES) PRECEDING TASK 1 0.1 — 2 0.1 1 3 0.1 2 4 0.2 2 5 0.1 2 6 0.2 3, 4, 5 7 0.1 1 8 0.1 7 9 0.2 8 10 0.1 9 11 0.2 6 12 0.2 10, 11 13 0.1 12 Using the following data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria. Note: Round your answer to the nearest whole percent.The project manager of the gas station project shown inFigure 7.3 needs to change the project’s WBS so that itcan be compared with cost and productivity informationcollected by the company. Level II should be changedto General Field Administration, Earthwork, ConcreteWork, Masonry Work, Metal Work, Carpentry, and Others.Complete the WBS of this project using this new arrangementfor Level II.Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?
- If the cycle time is 65.4 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A? Task Task Time (seconds) Tasks That Must Precede Other Tasks Number of Following Tasks A 28 - 7 B 13 - 8 C 35 B 7 D 11 A 6 E 20 C 6 F 6 D, E 5 G 23 F 3 H 25 F 2 I 37 G 1 J 11 G, H 1 K 27 I, J 0 Total 236 a. 26.9 minutes b. 37.4 seconds c. 28.5 seconds d. 31.6 seconds e. 57.6 secondsI need the last two questions which is the quarter 2 one and the last question in the other picture2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”, and “inspect”. If the capacity of activity “cook” determines the process capacity, which of the following statements are true? a- Activity “cook” is a bottleneck activity. b- The activity time of all the other five activities is shorter than activity "cook". c- Cycle time of the process of making hotdogs is equal=1/capacity of activity “cook”. d- Increasing the capacity of activity “grind” can increase the capacity of the process of making hotdogs. All statements are correct Only statement 'b' is correct Only statements 'a' and 'b' are correct Only statements 'a', 'b' and 'c' are correct Only statement 'a' is correct Only statement 'd' is correct
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: Activity Break down both machines A Clean machine 1 Clean machine 2 Re-set machine 1 Re-set machine 2 Re-calibrate both machines F Final test 13 days 12 days Designation Immediate Predecessor Time in Days None O 11 days O 10 days ABCDEFG A ABCDF 9 days D and E Using CPM, what is the latest finish time for the last activity in this project (i.e.. the total time to complete the project)? 333 N 2 1 2 1