In certain cases, experience will indicate the best time to perform certain operations to maintain equipment at the highest level of efficiency. A machine used for cutting materials in a factory has the outputs per hour at various speeds and requires periodic tool regrinding at the intervals cited. Speed Output per Hour Tool Regrinding A 200pcs Every 8 hrs B 250pcs Every 7 hrs C 280pcs Every 5 hrs A set of tools costs P1,800 and can be ground twenty times. Each regrinding costs P18 and the time needed to regrind and change tools is 1 hour. The machine operator is paid P28 per hour, including the time the tool is changed. The tool grinder who also sets the tools to the machine is paid P25 per hour. The hourly rate chargeable against the machine is P54, regardless of machine speed. What is the total cost of Speed B.

EBK HEALTH ECONOMICS AND POLICY
7th Edition
ISBN:9781337668279
Author:Henderson
Publisher:Henderson
Chapter4: Economic Evaluation In Health Care
Section: Chapter Questions
Problem 7QAP
icon
Related questions
Question
In certain cases, experience will indicate the best time to perform certain operations to maintain
equipment at the highest level of efficiency. A machine used for cutting materials in a factory has the ff
outputs per hour at various speeds and requires periodic tool regrinding at the intervals cited.
Speed
Output per Hour
Tool Regrinding
A
200pcs
Every 8 hrs
B
250pcs
Every 7 hrs
C
280pcs
Every 5 hrs
A set of tools costs P1,800 and can be ground twenty times. Each regrinding costs P18 and the
time needed to regrind and change tools is 1 hour. The machine operator is paid P28 per hour,
including the time the tool is changed. The tool grinder who also sets the tools to the machine is
paid P25 per hour. The hourly rate chargeable against the machine is P54, regardless of machine
speed. What is the total cost of Speed B.
Transcribed Image Text:In certain cases, experience will indicate the best time to perform certain operations to maintain equipment at the highest level of efficiency. A machine used for cutting materials in a factory has the ff outputs per hour at various speeds and requires periodic tool regrinding at the intervals cited. Speed Output per Hour Tool Regrinding A 200pcs Every 8 hrs B 250pcs Every 7 hrs C 280pcs Every 5 hrs A set of tools costs P1,800 and can be ground twenty times. Each regrinding costs P18 and the time needed to regrind and change tools is 1 hour. The machine operator is paid P28 per hour, including the time the tool is changed. The tool grinder who also sets the tools to the machine is paid P25 per hour. The hourly rate chargeable against the machine is P54, regardless of machine speed. What is the total cost of Speed B.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Profit Function
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK HEALTH ECONOMICS AND POLICY
EBK HEALTH ECONOMICS AND POLICY
Economics
ISBN:
9781337668279
Author:
Henderson
Publisher:
YUZU