In a CPM network, the critical path has five activities. Their durations are tabulated next. Duration Activity Optimistic (To) Most Likely (Tm) Pessimistic (Tp) A 2 5 9 B 3 4 8 C 4 6 9 D 5 10 20 E 3 5 9     Compute the following: The probability that the project will finish by the end of day 32 The probability that the project will finish by the end of day 34 The probability that the project will finish before day 30

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
  1. In a CPM network, the critical path has five activities. Their durations are

tabulated next.

Duration

Activity

Optimistic (To)

Most Likely (Tm)

Pessimistic (Tp)

A

2

5

9

B

3

4

8

C

4

6

9

D

5

10

20

E

3

5

9

 

 

Compute the following:

  1. The probability that the project will finish by the end of day 32
  2. The probability that the project will finish by the end of day 34
  3. The probability that the project will finish before day 30
  4. The probability that the project will finish on day 32
  5. The probability that the project will finish no later than day35
  6. The probability that the project will finish at least 2 days early
  7. The probability that the project will finish at least 2 days late
  8. The probability that the project will finish on day 32 ±1 day
  9. The completion date with at least a 90% confidence level
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Cost control
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning