Glen Halford has laid out the major steps involved in the engine assembly process for an experimental automobile. the activities are labeled A through D in the following table, which also shows thier project is shown below. Immediate  Time Estimates(weeks) Activity   Predecessor(s)    Optimistic(a)     Most Likely(m)     Pessimistic(b) A                 -                           4                           6                     8 B                -                            8                           10                    12 C               B                           16                          18                     20 D              A,C                            8                        10                       24   Start-----A---------------------------D       ------B------------C---------------D a.For each activity,copute the expected completion time and thevariance of the completion time. the expected completion time : t =(a+4m+b)/6 the variance of the completion: v=((b-a)/6)2 A: t=(4+4(6)+8)/6=6 ,v=((8-4)/6)2                  B: t=10 , v 2.25 C: t=18 , v=2.25 D: t=12, v=7.11 the critical path: B-C-D the expected completion of this project : 40 weeks the expected variance :vp =2.25+2.25+7.11= 11.61 here, I have a question: What is the probability that the project will take less than 42 weeks? (Show work/ explain reasoning to receive full credit.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Glen Halford has laid out the major steps involved in the engine assembly process for an experimental automobile. the activities are labeled A through D in the following table, which also shows thier project is shown below.

Immediate  Time Estimates(weeks)

Activity   Predecessor(s)    Optimistic(a)     Most Likely(m)     Pessimistic(b)

A                 -                           4                           6                     8

B                -                            8                           10                    12

C               B                           16                          18                     20

D              A,C                            8                        10                       24

 

Start-----A---------------------------D

      ------B------------C---------------D

a.For each activity,copute the expected completion time and thevariance of the completion time.

the expected completion time : t =(a+4m+b)/6

the variance of the completion: v=((b-a)/6)2

A: t=(4+4(6)+8)/6=6 ,v=((8-4)/6)2                 

B: t=10 , v 2.25

C: t=18 , v=2.25

D: t=12, v=7.11

the critical path: B-C-D

the expected completion of this project : 40 weeks

the expected variance :vp =2.25+2.25+7.11= 11.61

here, I have a question: What is the probability that the project will take less than 42 weeks? (Show work/ explain reasoning to receive full credit.)

 

                                           -

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.