Find the optimum duration and cost for the projects of a 11 activities, the indirect cost = 150 $ for each day ??? Normal Crashed Minimum Normal Crash Crash Change in Cost per Day( cost slope) Cost Duration Cost Duration Range 500 4 750 3 100 4 300 2 200 2 200 2 600 5 760 4 700 6 830 5 200 300 3 170 200 5 200 300 2 80 80 2 100 100 1 600 670 6 3450 2 4 5 Activity 1-2 2-3 2-4 2-5 3-6 4-8 5-7 6-9 7-8 8-9 9-10 Total cost 1 4 7 4 2 1 7 3
Q: Joe's Twenty-four Seven Laundromat has the following jobs waiting to be processed. The first step of…
A: The sequence of operation is given as First Come First Serve i.e. A-B-C-D-E. Here, the 1st operation…
Q: A toy manufacturer uses 48,000 rubber wheels per year for its dump truck. The trucks are assembled…
A:
Q: International managers also need to be aware of how government policy decisions can impact strategic…
A: Foreign direct investment is a kind of investment in which a business based in one country buys a…
Q: 5. Is it possible for an assignment problem to have no optimal solution? Justify your answer.
A: Assignment problems are all over the place, but as it turns out, not all of them can have an optimal…
Q: Differentiate between private warehouses and public warehouses.
A: Though there are many similarities between the private and public warehouses, there are also some…
Q: AlwaysRain Irrigation, Inc. would like to determine capacity requirements for the next four years.…
A:
Q: A small firm uses 3,400 lbs of chemical dye a year. Currently the firm purchases 300 lbs per order…
A: Given data is Demand(D) = 3400 lbs Order cost(S) = $100 Holding cost(H) = $0.51
Q: The original weight given is 1.00, whereas the finished product is 1.25. So what is the final…
A: Given, Finished product weight = 1.25 Original weight= 1.00 Product yield = Finished product…
Q: identify types of Risks cosmetic business face
A: If and when a gamble turns into a reality, a good to go business can limit the effect on profit,…
Q: Please describe experimental design, and how it would benefit the organization in terms of improving…
A: Experimental design is a tool used to evaluate the effect of a single or multiple changes to any…
Q: Construct an organizational chart for an international company with divisions in Europe, South…
A: An organization chart, at times known as an "org chart," is undoubtedly a graphic that shows a…
Q: Given below rating
A: Normal Time = 8 minutes Performance rating table Skill +0.15 Effort +0.10
Q: 3. The manager for a manufacturing company must recommend whether to construct a large plant,…
A: Given data:
Q: Identify the ten supply chain risks. Next, select two that you think are of greater risk than some…
A: A supply chain shows the operating activities to deliver finished goods to the customers. A supply…
Q: Use a diagram to show and explain the concept of supply chain management
A: Supply Chain Management A supply chain is a system of retailers, wholesalers, transporters,…
Q: sion questions 4. Describe the key stages of integrating total quality into the strategy of an…
A: Total quality management is used in an organization to create quality planning, controlling quality…
Q: Q3: A firm is operating at fixed cost of $400000 a revenue of $11 per unit a variable cost of $6 per…
A: Break-even analysis is one of the methods that are commonly and widely used in manufacturing…
Q: Construct the control charts for the mean and the range, using the original 15 samples. t up the…
A: Control charts are also known as process-behavior charts. It is a statistical process that helps in…
Q: Frank Johnson was outbound logistics manager for sudsy Soap.Inc. He had held the job for the past…
A: As per the case, The Sudsy soaps is a soap manufacturing business, The Sudsy soaps facing a…
Q: Why is it essential to collect data on a consistent basis?
A: Data should be collected consistently, here, we would take the data from different sites or…
Q: JNR Corporation makes wheels for toy cars. The company operates its production facility 300 days per…
A:
Q: a. Write the information given in the question in a tabular format. b. Write the problem in a linear…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Highlight the importance of supply chain management within a business context. Highlight the role…
A: Supply chain management would be critical to a company's success. The route from each and every…
Q: Q5 d) Briefly state what you understand by: i) The articles of association ii) Memorandum of…
A: Agreement is an arrangement between parties of coming into a mutual decision. In an agreement one…
Q: What is responsible marketing, responsible supply chain and operations management?
A: Responsible marketing, responsible supply chain and operations management all have one thing in…
Q: Defy Opens a World Class Warehousing and Distribution Centre in Danskraal, Ladysmith Defy’s new…
A: Today businesses work in a dynamic environment and the Business conditions are extremely diverse,…
Q: Briefly and exactly explain how does the inventory management impacts the performance of the supply…
A: To be determined: Explain how does the inventory management impacts the performance of the supply…
Q: The table below contains data for the installation of new equipment in a manufacturing process at…
A: a. answer = 11 weeks
Q: Activity Immediate predecessor(S) Normal Time Normal Cost($) Crash Time (Weeks) A none 10 16000 8 B…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: a) Determine the seasonal variation each of the b) Hence calculate the average seasonal variation…
A: Time series is a technique used to predict future outcomes on the basis of past data. This technique…
Q: ABC Company placed an order on December 1. It normally receives the order after 9 days. If the…
A: The reorder point is the level reached at which the order is placed to replenish the inventory…
Q: Sunrise is planning its purchases of ingredients for bread production. If bread demand had been…
A: Exponential smoothing could be a statistic statement technique for univariate information that may…
Q: Explain the Cost of Poor Quality (COPQ), the outcomes of poor quality, and why organizations find…
A: Cost of Poor Quality (COPQ) is the cost associated with providing poor quality products or services…
Q: What are the important factors in Total Quality Management?
A: Total Quality Management is a collaborative, systematic way to planning and conducting a continuous…
Q: in a small pharmacy how would you count that pharmacy's inventory?
A: Managing the inventory for pharmacies is one of the challenging tasks. Effective management of the…
Q: What are the most significant benefits and drawbacks associated with standardization?
A: The Standardization process refer to maintain uniformness and consistency among different of any…
Q: Al-Haidari Catering Company planned to purchase its needs from one of the materials involved in its…
A: Economic Order Quantity is that level of inventory at which ordering cost and carrying cost are…
Q: Transportation Rate (S/cwt) Weight/day
A: Given: The supplier can ship everyday, every other day, every third day There is a penalty of…
Q: 35. Suntrek, a global apparel company, is adding a new supplier for denim fabric that it uses to…
A: Minimax regret: Determine worst regret for each alternative and chose alternate with best worst.…
Q: A linear programming computer package is needed. The employee credit union at State University is…
A: Given data is Loan type Annual return Automobile loans 0.7 Furniture loans 0.9 Other…
Q: How important is it to align process capabilities to product requirements?
A: Process Capability: Process capability is denoted by the ability of the process…
Q: 8. Mary Catacutan and Pedro Perez are considering the possibility of teaching swimming to kids…
A:
Q: 18. All airplane passengers at the Lake City Regional Airport must pass through a security screening…
A: Given data: Service rate μ= 3 passengers per minuteArrival rate λ = 5.4 passengers per minute
Q: 27. Six Sigma is a well-recognized quality management system that employs improvement projects to…
A: P1 = Decision related to the selection of project 1. If the value of P1 = 1, select project 1. If…
Q: IMMEDIATE ACTIVITY PREDECESSORS D a) Choose the corect network to rep OA 08 b) Which activities are…
A: Find the Given details below: Activity ImmediatePredecessors Time(Weeks) A - 4 B - 3 C A 3…
Q: Mixing Company manufactured 2,500 units of its only product during 2022. The inputs for this…
A: The proportion of output to input is referred to as productivity. Productivity is essential to small…
Q: Explain the trade-offs that inventory managers facewhen they reorder products or supplies. How is…
A: Inventory managers are responsible for making sure that the company has enough of the right products…
Q: 2 Discuss inventory management policies for supply chain and logistics.
A: Keeping track of your inventory can be tricky in today’s constantly changing business world.…
Q: importance of strategic location
A: To be considered for in a business site decision, places must firstly fulfill particular…
Q: please answer all parts of the question within 30 minutes with detailed explanation. Make sure the…
A: Breakeven point is that level of sales at which there is no profit no loss. In other words at…
Step by step
Solved in 3 steps with 2 images
- Th e dean of the business school wants to start off eringthis program starting 32 weeks from now. Using the informationprovided in Problem 15,(a) Calculate the probability of the program starting ontime.(b) If the dean needs a 95 percent probability of being doneon time, how long can the expected project duration be?Given the data for a project in table Q3, using the following assumptions: 1. 8 hours as working day 2. The company will work all days. 3. Maximum number of workers available per day is 6 4. Activities cannot be break down 5. Budget will distributed equally per day, except for activities (B, H and L), the payment will be after two days of working: means that the first payment will be at the end of day2, then day four and so on. 6. They estimate that the work will starts on the first of November 2017 Develop a report containing the followings: Date of finish BAD O GYEK 1. 2. Early start and Slack time for each activity 3. Resource histogram 4. Cumulative Budget baseline curve 5. Interpret the final report co Table Q3 Duration (Hrs) No of Workers Budget Activity predecessor A None 48 12000 64 32000 C 16 10000 32 4. 12000 B,C 32 8000 B,C 16 6000 G B,C 16 4 10000 H. 64 16000 3. 16 4000 32 1 12000 K 32 3 16000 H. 48 1 12000 Total Budget of RM150000Exercise regular time acceleration time Normal Cost acceleration cost Precedents A 4 3 900 1000 --- B. 8 6 300 400 --- C 4 3 500 650 --- D 6 4 900 1200 A AND 7 4 1000 1600 C a. The duration of the project in normal time and without acceleration is Response days . b. The minimum cost to accelerate the project in 2 days is Response .
- B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?A project with total budget cost of 30 cr. is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given: Budgeted cost of work performed = 17 cr. Actual Cost of work performed = 19 cr. Budgeted cost of work scheduled = 21 cr. What is the cost performance index? A.0.895 B.0.81 C.0.90 D.1.12
- You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)← Consider the following crash data for a project. Times are given in weeks. ACTIVITY A B C D E F How many week(s) of crashing are available for activity E in the table above? Activity E has sweeks of crashing available. What will be the cost of activity E if it is completed in 3 weeks? The cost will be $ NORMAL TIME 4 7 8 3 7 6 CRASH TIME 4 5 3 1 1 3 NORMAL COST ($) 1,400 5,000 5,700 2,400 1,100 2,800 CRASH COST ($) 1,400 6,200 8,700 3,800 5,900 5,200 (s) po Time
- You have been assigned a project and in your preliminary planning you have developed table 2 below, it outlines eight activities (A to H) that must be completed. For each activity you have obtained the estimated duration, cost per day and the prior task(s). Activity A B с D E F G H Z Duration (days) 3 4 12 6 16 15 Cost/week ($) 2500 6000 3000 10000 15000 10000 7 8 0 Prior Tasks None B, D C, E E, F,G 0 All *Assume that there are five (5) workdays in each week Table 2 2000 2500 A A, B A, B D Using the information provided: a) Create a network diagram for the project. b) Construct a Gantt Chart for the project. c) Determine the minimum time in which the project can be completed. 15 What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? D Normal Crash Time Normal Activity Time (days) (days) Cost A 6 $900 5 8 6 $300 4 3 $500 5 3 $900 8 5 $1,000 BUDE C Adi... Total Cost Immediate with Crashing Predecessor(s) $1,000 $400 $600 $1,200 $1,600 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Laval Each Activity Should be Reduced BY A CA project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Optimistic Time (hr) Most Probable Time (hr) 4 4 0.5 2 3 5 5 Сл 1 3 7.5 Pessimistic Time (hr) 6 6 1.5 10 9 Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. (a) Construct the PERT/CPM network for this problem.