(f) What is the largest number of weeks allotted to finish the electrical wirings without delaying the project? (g) If there will be a delay in doing the outside plumbing without delaying the entire project, how long should it be?
Q: Let us assume that you are managing the complete food for dinner, and the food will be served at…
A:
Q: Calculate the critical path for this project The Critical path is _______________ and the project…
A: The critical path is the path that takes the longest time to complete the project network.
Q: To keep the project on schedule, Anne requested that she be allowed to assign three programmers from…
A: Since we have an undeniable level of thought of what to remember for our test plan format, we should…
Q: This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c)…
A: Forward pass: Earliest Start (ES) = Maximum of all predecessor activities (ES = 0 for Start…
Q: Imagine that you have been assigned to a team that will be developing an inventory tracking system.…
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: Recently, you were assigned to manage a project to remodelthe seminar room for your company. You…
A: Given data is
Q: 44. What activities make up the critical path? In crashing this project, which activity is the first…
A: Project crashing is the process of reducing the activity duration using additional cost through…
Q: (d) What is the shortest possible time it will take to complete the project?
A: Below is the solution:-
Q: 2. Reduce job 3 by two days. ONo O Yes 3. Reduce job 5 by two days. Yes O No e. What is the…
A: Given Information: Critical Path:- 1-2-5-8-9-11 Expected Completion Time:- 26.5 days
Q: Q1: Draw the allocation of resources chart on the earliest and latest start time for the project…
A: In given network diagram critical path will pass the activities B−E−G−K duration of the…
Q: What is the critical path? By how many weeks are we 90% sure of completing the project (along the…
A: A project network diagram is a graph that shows the sequence in which a project's activities are to…
Q: Gantt and PERT charts are mostly implemented during project phases. They can be used in order to…
A: Project planning is described as a process or means of completing a project within a specified…
Q: What is the relationship between the earliest start time (EST) of an activity and the earliest…
A: EST is early start time. It refers to earliest possible time to start an activity. ECT is early…
Q: 15F - Estimate how long (total time in months from start to finish, not how many months remain -…
A: THE ANSWER IS AS BELOW:
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely…
A: Critical path analysis (CPA) is a project managerial technique that represents identifying each…
Q: What is the total cost of reducing this project by two weeks?
A: Project crashing will helps to reduce the total duration by additional cost and efforts. In each of…
Q: a. Determine the project completion time if no activity is crashed. What would be the total cost of…
A: Below is the solution:-
Q: of the project, the same principles of project management (2) Whatever the apply. (a) quality (b)…
A: Project management: It is the utilization of methodologies, devices, and methods to progressively…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: Why does the project manager do resource leveling?
A: Resource leveling is a resource optimization strategy that determines when a project can be…
Q: What is the definition of the latest completion time (LCT) of a project activity?a. LCT(Ai) =…
A: The latest completion time is referred to as the possible completion time of any activity such that…
Q: O A-B-D-F-G-H O A-C-E-H O A-B-D-E-H O A-C-E-F-G-H c. How many weeks will it take to complete the…
A: The critical path method is a project management tool that is used to help plan and schedule the…
Q: 1- Data for small project are given, determine the following 1- ES for Activity C, E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: A plumber has decided to use the techniques of project management to plan a job. He knew all the…
A: Following ios the network diagram:
Q: a) What is the expected time to complete the project?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: A project to build a new bridge seems to be going very well since the project is well ahead of…
A: Budget cost 1 = $1,420,000 Budget cost 2 = $10,500,000 Budget cost 3 = $8,500,000*50% =$4,250,000…
Q: 1. What underlying problems caused Radia's project managers difficulty in creating the WBS? 2. Is…
A: Summary- Radia Engineering is an association of around 5,000 representatives, gaining practical…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: Nhat is the overall duration of the project (in weeks)? 32 weeks Nhat is the earliest week you could…
A:
Q: Identify the term being described for each of the following: b. The longest time sequence of…
A: b. The critical path is the longest time sequence of activities in a project.
Q: What can the project manager offer to other departments to make the situation a win-win?
A: A project manager is responsible for the smooth execution of the projects but it will be difficult…
Q: Below is the details about a. What is the maximum and minimum human resource that would be required…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Explain how to determine the slack for each activity in aproject. Why is it important for managers…
A: Slack in a project is referred to as the time margin or extent to which a particular activity stated…
Q: 13.42 Activity Ais worth $100, is complete, and actually cost $150. Activity B is worth $500, is 75%…
A:
Q: Who needs to be involved in assessing the cost of a project?
A: To use parametric estimating, first divide a project into units of work. Then, you must determine…
Q: We reduce Activity B to 4 weeks on each of the six houses. What affect will that have on the project…
A: There are 6 identical houses to be built. One house requires 15 weeks and involves 3 activities A,…
Q: Calculate the ES, EF, LS, and LF times and the slack for each activity in t the critical path for…
A: The full form of the term is as follow, ES- Earliest Start Time EF-Earliest Finish Time LS-Latest…
Q: What advantage does EDGE have over other training software when it comes to developing projects?
A: EDGE is in spark contrast to cloud computing, as in cloud computing the storage of the data is…
Q: The project shown within details what is the possibility t finish the project in 38 days? And what's…
A: Given that: Activity a m b 1 to 2 2 7 8 2 to 3 5 6 9 2 to 4 3 7 8 2 to 5 4 5 6 3 to 6…
Q: For companies, knowledgeable foundations followed in a statement, evaluation, and knowledge of the…
A: The purpose of the Statement of business principles is to explain to the employees about the…
Step by step
Solved in 2 steps with 2 images
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?ces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St FChuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of work
- Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A --- 2 3 4 B --- 4 7 10 C A 1 2 3 D B 2 5 8 E B 4 6 8 F C , D 1 1 1 G E 3 4 5 H G , F 3 6 15 1. Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you…3. PERT NETWORK. A companyis faced with the following PERT network situation (time in days): В 1-5-9 Start 2 - 4 - 6 4 -8 - 12 2-6 - 10 A D E 1-3 - 5 C 3 - 4-5 REQUIRED: a. Calculate t,(expected time) for each activity. For each activity, the estimates are t, tm tp, in that order. b. Calculate the total time for eachpath and identify the critical path.21. The following table provides the information necessary to construct a project network and project crash data: Activity (i, j) Activity Predecessor Activity Time (weeks) Normal Crash Activity Cost Normal Crash a (1,2) --- 16 8 $2000 $4400 b (1,3) --- 14 9 1000 1800 c (2,4) a 8 6 500 700 d (2,5) a 5 4 600 1300 e (3,5) b 4 2 1500 3000 f (3,6) b 6 4 800 1600 g (4,6) c 10 7 3000 4500 h (5,6) d, e 15 10 5000 8000 a. Construct the project network b. Manually crash the network to 28 weeks Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.
- Preceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Time (in weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board ------ 1 1 2 B Hire coaches A 4 6 8 C Reserve pool A 2 4 6 D Announce Program B, C 1 2 3 E Meet with Coaches B 2 3 4 F Order Team Suits A 1 2 3 G Register Swimmers D 1 2 3 H Collect Fees G 1 2 3 I Plan first practice E, H, F 1 1 1 a) What is the critical path? b) What is the project expected time? c) What is the probability of completing in 13…The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Time (in weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board ------ 1 1 2 B Hire coaches A 4 6 8 C Reserve pool A 2 4 6 D Announce Program B, C 1 2 3 E Meet with Coaches B 2 3 4 F Order Team Suits A 1 2 3 G Register Swimmers D 1 2 3 H Collect Fees G 1 2 3 I Plan first practice E, H, F 1 1 1 b) What is the project expected time? c) What is the probability of completing in 13 weeks? d) What is the…
- Consider the following data for a project to install a new server at the Northland Pines High School: Activity Time (days) 1 4 5 4 1 7 3 2 3 6 a. Choose the correct network diagram below. O A. Activity A BCDEFGH-. с J Q Immediate Predecessor(s) B. A A B B B, C D, E F F G, H, I Q OUThe manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows. Time (Weeks) Immediate Predecessor Activity Description Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 8 Reserve pool A 4. 6 D Announce program В, с 3 E Meet with coaches B 4 F Order team suits A 1 2 3 G Register swimmers D 2 3 H Collect fees G 1 I Plan first practice Е, Н, F 1 1 1 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Browse. No file selected. (b) Develop an activity schedule. (Round your answers to two decimal places.) Earliest Start Earliest Finish Latest Latest Activity Slack Start Finish A B D E F G H I (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in weeks)? (Round your answer to two decimal…Table below gives estimates in weeks, for forned activity (Durations are PERT. using Activity Duration Preceded Resources Ryan 5 1. 15 Order review 2. Order vender parts 3. Produce standard parts 20 custom parts development Manufacture custom parts 10 4. Design 13 5 18 7. Assemble 10 5 I 1 I 1 4 Carly Ryan Lauren Connor Ryan 2,3,6 Dawn Test 2,5 been engaged to you Assuming that project detalje have indicated festurces), USE CCPM (Critical Chain Project Management) below (Aur Project: to ESTIMATE the project duration by showing Jage of your programming procesa lindicate each and and