Exercises Days 1. Use the following information to compress one time unit per move using the least- cost method. Reduce the schedule until you reach the crash point of the network... For each move identify what activity or activities were crashed and the adjusted total cost. Note: The correct normal project duration, critical path, and total direct cost are provided. 1211098 Act. A TMODRY B C F A B 3 Crash Cost (slope) 50 100 60 60 70 0 Indirect Cost ($) 500 425 350 275 200 B 3 с D 3 E 4 Maximum Crash Time 1 1 2 2 1 0 The question is missing the indirect cost, here are the indirect cost for the project F 8 1x Normal Time 3 3 Initial project duration: 12 4 3 4 Normal Cost 150 100 200 200 200 150 Total direct cost: $1,000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Exercises
Days
1. Use the following information to compress one time unit per move using the least-
cost method. Reduce the schedule until you reach the crash point of the network.
For each move identify what activity or activities were crashed and the adjusted
total cost.
O 12
11
10
9
8
Act.
A
В
BLOWF
Note: The correct normal project duration, critical path, and total direct cost are
provided.
A
B
3
Crash Cost (slope)
50
100
60
60
70
0
B
88
3
Indirect
Cost ($)
500
425
350
275
200
C
4
D
3
Maximum Crash Time
E
4
2
2
1
0
The question is missing the indirect cost,
here are the indirect cost for the project
F
1x
Normal Time
3
3
4
3
4
Initial
project duration: 12
1
Total direct cost: $1,000
Normal Cost
150
100
200
200
200
150
Focus
=
Transcribed Image Text:Exercises Days 1. Use the following information to compress one time unit per move using the least- cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total cost. O 12 11 10 9 8 Act. A В BLOWF Note: The correct normal project duration, critical path, and total direct cost are provided. A B 3 Crash Cost (slope) 50 100 60 60 70 0 B 88 3 Indirect Cost ($) 500 425 350 275 200 C 4 D 3 Maximum Crash Time E 4 2 2 1 0 The question is missing the indirect cost, here are the indirect cost for the project F 1x Normal Time 3 3 4 3 4 Initial project duration: 12 1 Total direct cost: $1,000 Normal Cost 150 100 200 200 200 150 Focus =
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.