Duration 49 52 75 63 94 56 57 What is the shortest path and what is the shortest possible time to travel from A to Z? (Round your answer to the nearest whole number.) Shortest path Shortest duration
Q: Define the term Slack-Time?
A: Project management can be termed as the application of knowledge, techniques, tools, skills, and…
Q: Activity Duration Predecessors A 3 | A 7 D 3 В, С E F D G H E, F, G 5.
A: A project activity network is a graphical depiction showing the sequence for the completion of a…
Q: (a) Project Quality Management
A: A Small Introduction to Quality Management Quality management is the demonstration of supervising…
Q: Ctivity Description Predecessor Optimistic Most Pessimistic Activity Likely a Drain Oil 3.5 ---…
A: Network Diagram :
Q: A В C E 1 2 Activities Predecessor Duration 3 4 A 5 5 8 C A 10 7 В E C 4 F C 3 10 G 4 H G 9. 11 12 I…
A: The question is related to Crtical Path Method. The path having the longest duration is the…
Q: Question 2…
A: Note: - Since we can answer only up to three subparts, we will answer the first three subparts(1, 2,…
Q: QUESTION 2 The Human Resources Department is considering a project to upgrade its current payre…
A: Activity on Node diagram: Following format used for network diagram: Early Start(ES) Duration…
Q: 43 EST 43 С. ? A, ? F. ? 50 LST 50 E, 8 В, 15 15 D, 20 15 35 35 a) i) Explain what is meant by the…
A: Note: - Since the exact question that has to be answered is not specified we will answer the first…
Q: Question 37 How much slack is there in task A? Your Answer: Your Answer Question 38 If the crash…
A: Slack is the available time in a activity for delaying the project without affecting the total…
Q: PM.66 Real estate developer Russell Call was working with a few contractors to make a number of…
A: Possible path Duration Maximum Critical A-D-G 3+7+4 = 14 weeks Yes Yes B-E-G 2+6+4 = 12 weeks…
Q: What time should be allowed such that there is a 95% chance of completion within that time?
A: ANSWER IS AS FOLLOWS:
Q: Q6. Can you determine the absolute shortest time to finish this project (i.e., after having…
A: A - 5 10 3 20 B A 3 15 2 23 C B 6 25 3 31 D C 3 20 1 24 E C 7 30 4 45 F C, E 2 5 1 10 G…
Q: [Chapter 14. Managing Projects] The US Defense Department has planned to develop an intelligent…
A: a.) The following is a list of possible risks and problems that could arise as the new warfighting…
Q: Activity Time estimate (days) Succeeding Activity A 4 D A E F 11 C G H D,E,F 7 G
A: Network Diagram :
Q: As a project management student, where do you think project management can be used. Give examples
A: Project management is the application of knowledge, skills, tools, and techniques to project…
Q: Task number Predecessor Duration (day 3 2 14 3 2 3 3 2 4 3 6. 2 7 6 8 8 7 2 9 8 3 10 9. 4 11 6,10 6
A: Edge Node1 → Node2 1 1→2 1 1→29 2 2→3 d 2→29 3 3→4 4 4→5 5 5→6 6 6→7 7 7→8 d…
Q: Question 1 ACTIVITY PREDECESSORS DURATION (DAYS) A 3 В A 4 A 2 E F 2 D,E 4 H F,G You are required to…
A: Find the Given details below: Activity Predecessors Duration(Days) A - 3 B A 4 C A 2 D B…
Q: PM.66 Real estate developer Russell Call was working with a few contractors to make a number of…
A: Project crashing is a process which reduces the total duration of the project using additional costs…
Q: 1. of all the paths through a network , the critical path has the a. Maximum actual time b.…
A: Project network is the graphical representation that shows the project activities as well as their…
Q: ). (a) What is the earliest time that the new product can be introduced to the market? (b) If the…
A: As per the Bartely guidlines only the first three parts have been answered: For launching the…
Q: Time Task Precedence Tasks Task (sec (s ЕЗ D6 D7 D8 J2 D9 J3 C1 K4, K9 K9, J1 B3 B5 J2 B7 25
A: Calculate the cycle time based on the goal is to produce 1000 bicycles per standard 40hour week…
Q: Activity A B Ꭰ E F G H Crashed Activity Time 0.25 0.5 1 0.25 2 1 2 0.5 Cost ($) Normal Cras hing 750…
A: Activity Crashed activity time Normal cost Crashing cost A 0.25 750 1000 B 0.5 250 750 C 1 750…
Q: project management question: The project you are managing as expecting it's first shipment of…
A: This question is related to the topic -Project Management and this topic falls under the operations…
Q: Activities Duration (days) Preceding activities A 5 3 7 E B F A.C 6 A.C,E 5 A,C,E 2 D. K 7 D. L…
A:
Q: Question 3: The following bar chart shows the activities to complete a project in 6 months (each…
A: Planned value (PV), Earned value (EV) and Actual costs are different values which helps to identify…
Q: What is the shortest path and what is the shortest possible time to travel from A to Z? (Round yo…
A: Below is the solution:-
Q: Q. A few relationships between activities can be applied in precedence network. From Table 1,…
A: Given Details: Gantt Chart (Model) : This Gantt chart (Manual) prepared for understanding purpose.
Q: Activity Predecessor Duration 2 Days 3 Days 8 Days 1 Day 1 Day 4 Days 3 Days A None В A В, Е A E F E…
A: A project network (also known as a project activity network) is a graphical representation (akin to…
Q: QUESTION 2: Identify the different stages of a project job cycle
A: A project management life cycle is a process with different stages like initiating, planning,…
Q: Question 6 Each descending level represents an increasingly detailed definition of the project…
A: WBS or work breakdown structure identifies all the tasks that have to be completed to build the…
Q: 8-The critical path time is All options are incorrect O 8 17
A: The critical path method is a method in which the path with the longest duration is identified to…
Q: Define schedule activity lag
A: The process of schedule development includes: - 1.Identification of all activities, 2. Sequencing…
Q: Task ID Task Predecessor Original Duration Original Cost Crashed Duration Crashed Cost 1 2…
A: Find the Given details below: Task ID Activity Predecessor Original duration (NT) (Days) Original…
Q: As the project management team responsible for the successful implementation of the youth…
A: Note: “Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: What are the issues confronting Thomas in this case? How well is Thomas dealing with these issues?…
A: BUSINESS MANAGEMENT: This is the process of handling and managing the business operations so that…
Q: partment Transportati project section of interstate highway near Wahington, DC. The project includes…
A: Project scheduling with uncertain activity times (Optimistic, Most likely, Pessimistic) a - 1 2 2…
Q: Develop the Project quality Management Plan
A: Under Project management, the entire process of project development is overseen, ensuring the goals…
Q: QUESTION #5 a. Draw the network corresponding to the following information. b. Identify the critical…
A:
Q: Activity Pre-act. A B D A,B E F F,C H B H,E H,E D,I, F,C K K
A:
Q: PM.66 Real estate developer Russell Call was working with a few contractors to make a number of…
A: Given-
Q: Question Direction: Determine the statement of the problem, solution to the problem and conlusion…
A: A lot of project management issues or circumstances are complicated, involving a lot of…
Q: ubsidiary plans below: (d) Project Quality Management ( e) Stakeholders Management/Engagement plan
A: subsidiary plan is a derivation plan which are made in the management for the different plan or the…
Q: Title A: Practical HRM in Aviation Instruction: Select an airline and cover the following aspects:…
A: RAPID GLOBAL BUSINESS SOLUTIONS INDIA PVT. LTD. Founded in 1997, RGBSI began with the strength of…
Q: What is the mean tardiness (in days) for all jobs? What is the mean completion time in days for…
A: Below is the solution:-
Step by step
Solved in 2 steps with 1 images
- Proctoring Enabled: Chapter 6 Network Optimization Pro.. 0 Saved Help Save & Exit 1 A minimum-cost flow problem has 4 supply nodes, O transshipment nodes, and 5 demand nodes. If each supply node can ship to every demand node, how many arcs will be included In the model? Number of arcs Mc Graw Hill HUAWEI Esc FI F2 F3 IDI PrtSc Ins F4 FS F6 F7 FB Del F9 F10 F12 #3 & 2 3 4. 6 7 8 9 W E Tab T Y U Caps A D G K Shift C V Fn Alt Alt CtrlPROBLEMS10 Section Assigned Problems 5.1 5.2 5-1 to 5-13 5-14 to 5-21 5.3.1 5-22 5.3.2 5-23 to 5-29 5.3.3 5-30 to 5-31 5.4.1 5-32 to 5-38 5-1. True or False? (a) To balance a transportation model, it is necessary to add a dummy source or a dummy destination bur never both. (b) The amounts shipped to a dummy destination represent surplus at the shipping source. (c) The amounts shipped from a dummy source represent shortages at the receiving destinations.! Required information The Childfair Company has three plants producing child push chairs that are to be shipped to four distribution centers. Plants 1, 2, and 3 produce 12, 17, and 11 shipments per month, respec- tively. Each distribution center needs to receive 10 shipments per month. The distance from each plant to the respective distributing centers is given below: Distance Plant 1 2 3 1 1150 1450 950 Distribution Center. 2 3 1650 750 1750 950 1550 1150 4 1050 1350 1250 The freight cost for each shipment is $100 plus 50 cents per mile. Obtain an optimal solution, and determine the total cost. Total Cost = $ 27300
- Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s)A 6 8 12 - G 2 3 4 C, EB 1 9 24 A H 2 2 2 FC 8 14 16 A I 7 7 7 FD 4 7 10 A J 6 7 12 D, G, HE 1 2 4 B K 1 1 4 I, JF 6 9 20 C, E a) The expected (estimated) time for activity C is 13.33weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.78weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A - C - F - H - J - K . d) The estimated time for the critical path is [ ? ] enter your response here weeks. (Round your response to two…Mailings Review View me E E • E = AaBbCcDc Aa AaBbCcDdEe AaBbCcDdEe Normal No Spacing Heading 1 Paint Window Install Sills (2) Windows (2) Remove Siding Add New Siding Paint Exterior (2) (4) (2) 1 Install Interior (2) Remove Floor (1) 4 Install New Floor (4) Instructions: The network diagram above (activity on arrow) shows the activities needed to complete a project to remodel a storage shed. The activities are listed as well as the time (in days) it will take to complete them. Use this information to find the following values for each of these activities: early start time, early finish time, late start time, late finish time (Probably best to do in an Excel file). Based on this, find the slack time for each activity and identify the critical path. 2.Fast pls i will give u like for sure solve this question correctly in 5 min pls Solve for NOVEMBER and DECEMBER PLZ !!!!!!
- Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 150 hours will be required to complete the project. The firm's three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at least 40% of the total number of hours assigned to the two senior designers. To provide label designing experience for Sarah, the junior designer must be assigned at least 15% of the total project time. However, the number of hours assigned to Sarah must not exceed 25% of the total number of hours assigned to the two senior designers. Due to other project commitments, Lisa has a maximum of 50 hours available to work on this project. Hourly wage rates are $30 for Lisa, $26 for David, and $18 for Sarah. (a)…Problem 13-11 (Algo) The state and local police departments are trying to analyze crime rates so they can shift their patrols from decreasing-rate areas to areas where rates are increasing. The city and county have been geographically segmented into areas containing 5,650 residences. The police recognize that not all crimes and offenses are reported: people do not want to become involved, consider the offenses too small to report, are too embarrassed to make a police report, or do not take the time, among other reasons. Every month, because of this, the police are contacting by phone a random sample of 1,170 of the 5,650 residences for data on crime. (Respondents are guaranteed anonymity.) Here are the data collected for the past 12 months for one area: CRIME MONTH SAMPLE SIZE CRIME RATE INCIDENCE January February March 9 1,170 1,170 1,170 1,170 1,170 1,170 1,170 1,170 1,170 1,170 1,170 11 April May 9 9 June 11 July August September October 9 12 10 13 November 13 December 10 1,170 a.…1. ART Contractors must locate an equipment staging area to serve three construction sites, located at coordinates (2, 2), (1, 4), and (5, 5). Noteshaper Quick Start Question #14) a. If traffic between the staging area and the first two construction sites (2,2) and (1,4) is 50 trips per week and the traffic between the staging area and the construction area at (5,5) is 20 trips per week, what is the best coordinates for theequipment staging area?
- Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Activity A B C D E F a 6 2 9 4 1 6 m 8 8 12 7 3 8 b 12 23 16 10 4 21 Immediate Predecessor(s) A A A B C, E Activity G H J K a 3 2 5 4 1 Time (weeks) m 3 2 5 8 1 a) The expected (estimated) time for activity C is b) The variance for activity C is weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is b 4 2 5 12 4 weeks. (Round your response to two decimal places.) D Immediate Predecessor(s) C, E F F D, G, H I, J d) The estimated time for the critical path is weeks. (Round your response to two decimal places.) e) The activity variance along the critical path is weeks. (Round your response to two decimal places.) f) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 36 weeks or less is (Enter as a…elbtronics Firmware Engineer Campus 2024 Y 1. Analytical Ability and Problem... Question 8 2 5 6 1 B Attempted 6710 Revisit Later Select an opti A jeweller uses different coloured beads to make a necklace. He first threads five beads of different colours and places them in a line before tying a knot to make the necklace. The red bead is to the immediate right of the blue one. The blue bead is not adjacent to the yellow bead. The green bead is to the immediate left of the pink bead and is at one end of the string. Which bead is to the immediate night of the pink bead?BUS 517 WK 11 Final ExamMultiple Choice Questions1. Information to develop a project network is collected from the A. Organization breakdown structureB. Work breakdown structureC. BudgetD. Project proposalE. Responsibility matrix2. Which of the following represents an activity on an AON project network? A. An arrowB. A lineC. A nodeD. Both A and B are correctE. A, B, and C are all correct3. Arrows on an AON project network represent: A. An activityB. Project flowC. DependencyD. Both B and C are correctE. Both A and B are correct4. When translated into a project network, a work package will become A. A single activityB. One or more activitiesC. A milestoneD. A critical pathE. An arrow5. Which of the following is provided by a project network but not by the work breakdown structure? A. DependenciesB. SequencingC. InterrelationshipsD. Both A and B are correctE. A, B, and C are all correct6. On a project network, the activity times are derived from the A. Organization breakdown structureB.…