Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Total Cost Activity A с D E Immediate Normal Time Crash Time Normal (weeks) Cost Crashing Predecessor(s) 3 $2,100 $2.700 1 $2,900 3 $2,300 $500 $2,300 $500 $1,000 $2,620 $1,300 $4,600 $3,200 $1,400 $2,000 4 3 2 D. E 1) Based on the given information regarding the activities for the project, the project length= weeks. 2) The total cost required for completing this project on normal time= $______ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity _______. 4) The cost of the project based on the first activity selected for crashing will increase by S______. 5) The maximum weeks by which the project can be reduced by crashing=______ weeks.
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Total Cost Activity A с D E Immediate Normal Time Crash Time Normal (weeks) Cost Crashing Predecessor(s) 3 $2,100 $2.700 1 $2,900 3 $2,300 $500 $2,300 $500 $1,000 $2,620 $1,300 $4,600 $3,200 $1,400 $2,000 4 3 2 D. E 1) Based on the given information regarding the activities for the project, the project length= weeks. 2) The total cost required for completing this project on normal time= $______ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity _______. 4) The cost of the project based on the first activity selected for crashing will increase by S______. 5) The maximum weeks by which the project can be reduced by crashing=______ weeks.
Information Technology Project Management
9th Edition
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Kathy Schwalbe
Chapter5: Project Scope Management
Section: Chapter Questions
Problem 4E
Related questions
Question
7
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 6 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Recommended textbooks for you
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:
9781305082168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781305971776
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:
9781305082168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781305971776
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Enhanced Discovering Computers 2017 (Shelly Cashm…
Computer Science
ISBN:
9781305657458
Author:
Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:
Cengage Learning