Data has been collected for a machine over a number of weeks and is contained in Table Q6 below. a) Calculate the OEE value for this resource. b) Discuss the results you obtain and suggest the areas where any improvement effort should be focused. • Three shifts of 8 hours, 7 days/week • Breaks of 50 min /shift • 19 breakdowns averaging Shift Pattern Breakdowns 45min. each and • 25 breakdowns averaging 5 min. each Set-ups 32 product changeovers averaging 25 mins each • 400 units produced plus 18 units scrapped and 5 units requiring rework. • Allowed time for products produced by production control = 100 hours. Output Production Rate

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Data has been collected for a machine over a number of weeks and is
contained in Table Q6 below.
a) Calculate the OEE value for this resource.
b) Discuss the results you obtain and suggest the areas where any
improvement effort should be focused.
• Three shifts of 8 hours,
• 7 days/week
Shift Pattern
Breaks of 50 min /shift
Breakdowns
19 breakdowns averaging
45min. each
and
25 breakdowns averaging 5
min. each
• 32 product changeovers
averaging 25 mins each
• 400 units produced plus 18
units scrapped and 5 units
requiring rework.
Allowed time for products
produced by production
control = 100 hours.
Set-ups
Output
Production
Rate
Transcribed Image Text:Data has been collected for a machine over a number of weeks and is contained in Table Q6 below. a) Calculate the OEE value for this resource. b) Discuss the results you obtain and suggest the areas where any improvement effort should be focused. • Three shifts of 8 hours, • 7 days/week Shift Pattern Breaks of 50 min /shift Breakdowns 19 breakdowns averaging 45min. each and 25 breakdowns averaging 5 min. each • 32 product changeovers averaging 25 mins each • 400 units produced plus 18 units scrapped and 5 units requiring rework. Allowed time for products produced by production control = 100 hours. Set-ups Output Production Rate
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.