(b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that he must reduce the build duration by 3 days to complete the treehouse by his son's birthday. He has determined the crash cost and crash time for each task as follows: A B Crash Time (day) | 12 Task C D E F G 9 10 5 6 Crash Cost (RM) 50 170 180 70 95 80 60

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question
answer part b only
Ed is planning to build a treehouse as a present for his son's upcoming 10th birthday. The
details for each task are as follows:
DE F G
AD C,E F
12
Task
A
B
Preceding Task
Duration (day) | 12
A
B
10
12
5
Cost (RM)
50 140 120 60 70
80
60
(a) Obtain the following:
• The number of days it will take for Ed to finish building the treehouse.
• Which tasks are cannot be delayed at all without delaying the whole project.
• The total cost of building the treehouse.
(b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that
he must reduce the build duration by 3 days to complete the treehouse by his son's birthday.
He has determined the crash cost and crash time for each task as follows:
Task
А В С
DE F G
Crash Time (day) | 12 8
9
8 10 5
6
Crash Cost (RM) | 50 170 180 70 95 80 60
Obtain the following:
• All tasks that are crashed and by how much.
• The new total cost for building the treehouse.
Transcribed Image Text:Ed is planning to build a treehouse as a present for his son's upcoming 10th birthday. The details for each task are as follows: DE F G AD C,E F 12 Task A B Preceding Task Duration (day) | 12 A B 10 12 5 Cost (RM) 50 140 120 60 70 80 60 (a) Obtain the following: • The number of days it will take for Ed to finish building the treehouse. • Which tasks are cannot be delayed at all without delaying the whole project. • The total cost of building the treehouse. (b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that he must reduce the build duration by 3 days to complete the treehouse by his son's birthday. He has determined the crash cost and crash time for each task as follows: Task А В С DE F G Crash Time (day) | 12 8 9 8 10 5 6 Crash Cost (RM) | 50 170 180 70 95 80 60 Obtain the following: • All tasks that are crashed and by how much. • The new total cost for building the treehouse.
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Dimensional Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY