ACTIVITY PREDECESSOR DURATION (DAYS) A B C A, B D C E C, D 5 F D, E 6 1. Use the information provided in the table below to draw a PERT chart using the examples you have seen in class. 2. Find the Critical Path for this project. 3. Find the duration of this project. 4. Find the FS FF IS LE for activities in the project LO 5 6 4 LO 5 LO

Information Technology Project Management
9th Edition
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Kathy Schwalbe
Chapter5: Project Scope Management
Section: Chapter Questions
Problem 5E
icon
Related questions
Question

6

ACTIVITY PREDECESSOR DURATION (DAYS)
A
B
C
A, B
D
с
E
C, D
5
F
D, E
6
1. Use the information provided in the table below to draw a PERT chart
using the examples you have seen in class.
2. Find the Critical Path for this project.
3. Find the duration of this project.
4. Find the ES, EF, LS, LF for activities in the project.
5. Find the slack of each activity
LO
5
6
4
LO
5
LO
Transcribed Image Text:ACTIVITY PREDECESSOR DURATION (DAYS) A B C A, B D с E C, D 5 F D, E 6 1. Use the information provided in the table below to draw a PERT chart using the examples you have seen in class. 2. Find the Critical Path for this project. 3. Find the duration of this project. 4. Find the ES, EF, LS, LF for activities in the project. 5. Find the slack of each activity LO 5 6 4 LO 5 LO
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Project Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning