a) What is the critical path?   b) What is the project expected time?   c) What is the probability of completing in 19 weeks?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

You are in charge of the new project at work which is scheduled to being on May 1. Your project activities, times and descriptions are listed below:

 

 

 

Time (in weeks)

Activity

Description

Immediate

Predecessor

Optimistic

Most Probable

Pessimistic

A

Meet with board

------

1

3

5

B

Hire staff

A

4

6

8

 

C

Brian storm

A

1

2

3

 

D

Write up proposal

B, C

2

3

4

E

Pitch proposal at meeting

B, C

2

4

6

F

Revise Proposal

A

2

3

4

G

Pitch proposal to Board

D

1

2

3

H

Await Board decision

E, G

2

4

6

 

I

Implement plan

H, F

2

2

2

 

a) What is the critical path?

 

b) What is the project expected time?

 

c) What is the probability of completing in 19 weeks?

 

d) What is the probability of completing in 21 weeks?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

d) What is the probability of completing in 21 weeks?

Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.