A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the LAST Workstation? a. 0.57 b. 1.17 О с. 0.47 O d. None is the correct answer е. 0.27
Q: At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the…
A: Given data: Job Due time Duration A 8 1.85 B 4.5 0.25 C 6.5 1.2 D 7 1.55 E 6 1.3 F…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data; Output = 60 units Available time = 8 hrs or 8*60 = 480 min
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand = 100 units Time available = 8×60= 480 minutes
Q: a. Determine the number of followers for each task. (Please answer number of tasks following…
A: Assigning each task to a workstation within an assembly line to fulfill the necessary production…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: The entries in the table denote the costs of assigning a task to a particular person. The plant…
A: Here, I would apply the Hungarian method to this assignment problem, we could see the cost element…
Q: snip
A: Given that: Task duration of A: 1 day Task duration of B: 1 day Task duration of C: 1 day Task…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F…
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its…
A: Given data is
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its…
A: Given - Job Time Since Order Arrived(days ago) Processing Time (days) Due Date (days…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: Glaudious is 45 years old university internship coordinator. He is handling 80 interns and he would…
A: Task analysis is a way to break down a task or a process into its subcomponents, subparts,…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Formula to be used; Cycle time = Available time / Output
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: 8 hours per day = 28800 seconds and want to produce 100 units/ day cycle time = 28800/100 = 288…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: A workstation appraisal limits dangers to DSE clients by guaranteeing workstations are hazard…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: Six jobs are to be processed through a two-step opera- tion. The first operation involves sanding,…
A: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 10 5 B 7 4 C 5 7 D…
Q: The Earliest Due date (EDD) rule for sequencing a given set of jobs usually ____________ Select…
A: Scheduling is a technique for allocating precious computational resources typically processor time,…
Q: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of…
A: THE ANSWER IS AS BELOW:
Q: The times required to complete each of eight jobs in a two-machine flow shop are shown in thetable…
A: A)
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data is Demand = 80units/day Working hours = 8
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Assembly line balancing is the process of assigning each task to a workstation in order to meet the…
Q: A merchant wants to cut a group of pieces of cloth, each of more than 5 meters long, into small…
A: A map of operations is the visual description of the workflow of a project which describes the…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Find the Given details below: Given details: Task Immediate Predecessors Time(mins) A - 2.4…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The efficiency can be determined as follows: Efficiency = Sum of total task timesNumber of…
Q: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of…
A: The FCFS and EDD analysis is as follows:
Q: Dan is a member of a four person sales team in a gourmet kitchen shop. All of the sales team members…
A: Working in a team is like working together on the same goal and work collaboratively in order to…
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: Given, SUIT CUT AND SEW DELIVER 1 7 2 2 4 3 3 5 6
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: Consider a project with seven tasks. Three tasks - tasks 3, 4, and 5 - require a specific resource…
A:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The flow diagram for the product is shown below.
Q: In a school, there are four teachers X1,X2,X3,X4 and five batches Y1,Y2,Y3,Y4,Y5. Given that teacher…
A: The given question is of an unbalanced minimization problem of assignment. In order to slove the…
Q: Homework help starts here! ASK AN EXPERT CHAT MATH SOLVER Question Question A business is…
A: Given data is
Q: requirements specification
A: Requirement specification helps in creating an outline of the assigned task.
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data; Output per day = 70 units per day Available time = 8 hrs or 8*60 = 480min
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Machine Idleness is the time frame during which a machine isn't being utilized. This is comparative…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: To utilize the product layout, the complete work to be performed should be dividable into little…
Q: How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its…
A: Given, Job Time Since Order Arrived (days ago) Processing Time (days) Due Date…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Total Working hours=8 hour or 480 minutes Total Task =7 task Daily Demand= 120 toys Total task time…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: Show your step-by-step process using the SPECIAL PURPOSE LINEAR PROGRAMMING: ASSIGNMENT METHOD to…
A: Linear programming, often known as linear optimization, is a method for obtaining the best result…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given information Task Time A 2.8 B 2.1 C 0.9 D 1 E 1.2 F 1.8 G 4.7 Task…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: Question: Balance this line using the longest task time heuristic.
A: The longest-time heuristic method ensures that the most difficult tasks to fit into a station are…
Step by step
Solved in 4 steps with 3 images
- A manutacturer is designing a product layout for a new product production. It plans to use a production line for B hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 lasks in total. These tasks are namely, A, 8, CD, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed Starting tasks Cneeds, the tack B to be completed. Also, starting task D needed task B to be completed Task E can only start upon completion of Task C. Whescas starting lask F needs the completion of both the tasks D and E Finally, starting task G needed, task Fto be completed. 1the processing times for tasks, A BC D, E F, andG are 28, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks nule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one OaAB, and C ODAB Oc None…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks Cneeds, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task Fneeds the completion of both the tasks Dand E. Finally,. starting task G needed, task F to be completed. The processing times for tasks. A, B. C, D, E, F. and G are 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the mostremaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What is the idleness in percentage? a None is the correct answer O b. 81.82 O c. 32.5 O…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C D E F and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed, Starting tasks needs the task to be completed. Also starting task D, needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 28.2.1,0.9, 10, 1.2.1.8 are 4.7 minutes respectively. How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5 please I neef answer along with the formula don't put it on excel
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D. E. F. and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FOURTH Workstation? O a. 1.0 O b. 1.4 C. 0.9 O…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely. A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task Fneeds the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are Select one: a. D, E,…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? Select one: Oa. 4.5 Ob. 0.9 Oc. None is the correct answer O d. 6.0 Oe. 4.4 Next pa nd Windows
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: a. None is the correct answer b. 5 C. 6 d. 3 e. 1A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? O a. 4.8 Ob. 4.4 None is the correct answer O d. 0.9 O e. 4.5A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: O a.2 O b. None is the correct answer O c.6 O d. 8 O e. 4
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are Select one: Oa. B and…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are: a. B,C and D b. C…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are O a. A, B, and C Ob. None…