[5] A contractor estimates the probabilities for the number of days required to com- plete a certain type of construction project as follows: Time (days) 1 2 3 4 5 Probability 0.05 0.2 0.35 0.3 0.1 a) What is the probability that a randomly chosen project takes less than 3 days to complete? b) Find the expected time to complete the project. c) Find the standard deviation of the time required to complete the project. d) Suppose the contractor's project cost is made of two parts: a fixed cost of $20,000 and $2,000 for each day taken to complete the project. Find the mean and standard deviation of the total project cost. e) If three projects are undertaken, what is the probability that at least two of them will take at least 4 days to complete? Assume that project completion times are independent.
[5] A contractor estimates the probabilities for the number of days required to com- plete a certain type of construction project as follows: Time (days) 1 2 3 4 5 Probability 0.05 0.2 0.35 0.3 0.1 a) What is the probability that a randomly chosen project takes less than 3 days to complete? b) Find the expected time to complete the project. c) Find the standard deviation of the time required to complete the project. d) Suppose the contractor's project cost is made of two parts: a fixed cost of $20,000 and $2,000 for each day taken to complete the project. Find the mean and standard deviation of the total project cost. e) If three projects are undertaken, what is the probability that at least two of them will take at least 4 days to complete? Assume that project completion times are independent.
Managerial Economics: A Problem Solving Approach
5th Edition
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Chapter17: Making Decisions With Uncertainty
Section: Chapter Questions
Problem 17.1IP
Related questions
Question
Show me full answers and steps to part d) and e)
Don’t use R or excel formula. Use expected formula and mean formula to calculate
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 7 steps with 5 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.Recommended textbooks for you
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning