31) Use the values in the table to calculate activity durations and variances for the project. Which path is critical? How closely should the other path be watched and why? ( Activity Predecessor Optimistic Likely Pessimistic A 6 10 B A 2 5 C A 6 7 D B 9 E C 17 D.E 9 8 9 20 11 19
Q: What are the Network Paths using AON?
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: Based on the following sensitivity report, how much should the firm be willing to pay for 53 more…
A: Given sensitivity report-
Q: time inventory management? A firm minimises the time lags present in the supply chain by…
A: Just in time is a Inventory management technique in which goods are received from suppliers only as…
Q: inda Boardman, Inc., an equipment manufacturer in Boston, has submitted a sample cutoff valve to…
A: Mean (X) = 8.00 Standard Deviation () = 0.04 Lower Specification Limit (LSL) = 8 - (3 * 0.047) =…
Q: A firm is attempting to minimize its shipping costs. The firm has 3 factories and must supply the…
A: The transportation method refers to a special kind of Linear programming Problem (LPP). It is…
Q: Many of a bank’s customers use its automatic teller machine to transact business after normal…
A: Given data is Customers arrival rate: λ=1 customer2 mins×60 mins/hrλ=30 customers/hr Service rate:…
Q: Defy Opens a World Class Warehousing and Distribution Centre in Danskraal, Ladysmith Defy’s new…
A: Today businesses work in a dynamic environment and the Business conditions are extremely diverse,…
Q: sions that were most important.
A: Game hypothesis, the investigation of decision making, unites different teaches like science,…
Q: How does knowing the threats in the market help in the development of the product portfolio?
A: Threats are risks and barriers that can damage a business. Threats obstacles a business in achieving…
Q: Is this statement true or false? And why? “Because strategy informs a tactical plan, operational…
A: Strategy: Strategy is defined as it is an overall direction of the company/business…
Q: three finishers, each of whom works at most 30 hours per week. Each leather model. brings a profit…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: forecasting requirements related to supply chain and logistics
A: Forecasting is a technique used to predict future results on the basis of past data. In businesses…
Q: Explain the trade-offs that inventory managers facewhen they reorder products or supplies. How is…
A: Inventory managers are responsible for making sure that the company has enough of the right products…
Q: locating a process inside an organisation that has room for improvement is the first step. Please…
A: DMAIC has five stages which are; define, measure, analyze, improve and control. This method is used…
Q: Write the Liner programming model used for scheduling the following project. 2 3 5 3 1 4 4 6 5 2 3
A: A network is a graphical representation of a project, depicting the flow as well as the sequence of…
Q: Exercise regular time acceleration time Normal Cost acceleration cost Precedents A 4 3 900 1000 ---…
A: There are three possible paths AD = 4+6 = 10 B = 8 CE = 4+7 = 11 Normal project duration…
Q: Q2: A project manager has a generator construction project that needs to be completed in 1 year and…
A: SPI ans CPI will helps to identify the project performance analysis based on the consideration of…
Q: 1) The PERT method to solve? a) Game theory b) transportation model c) network analysis.
A: The PERT technique helps to calculate the estimated time of each activity from the related…
Q: A firm uses simple exponential smoothing with trend adjustment to forecast demand, "a = 0.6" and…
A: Given, TAF for first month TAF1 = 434 units Actual demand for first period A1= 488 units Trend T1 =…
Q: What is a contract law, specifically focusing on offer and acceptance?
A: A contract is a legally enforceable agreement between two or more parties where each assumes a legal…
Q: Many service organizations in different sectors strive for good quality. However, very few are able…
A: Quality management can be stated as the act of overseeing or supervising all the tasks that must be…
Q: An activity duration estimates for a certain project has the most optimistic time to complete the…
A: The activity duration is the total time taken by the particular activity to complete the whole…
Q: Describe the many kinds of programmes.
A: A computer program is a set of instructions to perform a particular task. A computer program is used…
Q: How impactful were product discounts on customer questions?
A: Based on the parameters you specify, a Product Discount pertains to something like a specific…
Q: New Accounts Period New Accounts Period 200 6 232 11 214 248 12 3 211 250 13 4 228 253 14 235 10 267…
A: Given data is
Q: XYZ Steel Company manufactures two kinds of wrought-iron rails: Model E, the elegant, and Model D,…
A: Given data is Cost Selling price Profit Model D $90 $99 99-90=$9 Model E $81 $88 88-81=$7…
Q: why creativity is important for organisations (e.g., because it enables them to create new…
A: Creativity is needed in every organization and plays an important role in the growth and expansion…
Q: Explain all options A primary activity of an organization according to the value chain is that of…
A: The value chain includes all the activities that are performed to make the product reach to the…
Q: Aldiscuss Three important Hazard Identification processes are. AND Why non a) Audits conducted by…
A: Occupational Safety and Health Administration often called OSHA can be stated as the main federal…
Q: Cakes, the shop includes different areas for mixing, baking, decorating, and packaging. This…
A: Option C is correct. At Jill's Custom Cakes, the shop includes different areas for mixing, baking,…
Q: Dags pe t the local farmers' market. shelled pecans for $7, and of an unshelled pecan. It requ…
A: Based on given information have to determine the decision variables: X1=Pies X2=Batches of one dozen…
Q: Auto sales at Carmen's Chevrolet are shown below. Using a 3-week weighted moving average (w₁-0.5,…
A: Forecasting is a technique used to predict future outcomes on the basis of past data. In businesses…
Q: Which of the following would be the ideal way for an analyst to identify peer companies?: Select…
A: Peer companies can be defined as those companies that operate in similar industries or divisions.…
Q: Sunblessed Juice Company sells bags of oranges and cartons of orange juice. Sunblessed grades…
A: Revenue and variable cost: Grades of oranges available: Average quality of oranges required
Q: Required: a. Solve the model formulated for Southern Sporting Goods Company using the computer. b.…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Focusing on your organization or a Caribbean company/organization of your choice within your…
A: A PESTEL study, also referred as a Pestel methodology, is a methodology or method for analysing and…
Q: a. Minimin b. Minimax C. Equal likelihood
A: Mathematic models of decision-making help businesses take the correct decision for their operational…
Q: ILLUSTRATE THE VARIOUS COST CLASSIFICATIONS. (PLEASE INCLUDE PHOTOS OR TEXT FOR THE EXPLANATION)…
A: Cost can be understood as the price which is being paid for acquiring a specific resource such as…
Q: Discuss The DMAIC methodology that used to incorporate Six Sigma and Lean tools to improve processes…
A: Six sigma can be broadly defined as a data driven methodology that is used to reduce the number of…
Q: al monitoring and evaluation system components
A: Conventional monitoring: he executives measure, targets and execution markers set by site or…
Q: hich statement below is True, and which one is False? For the False ones explain why they are…
A: 3-1) The process imperfections or the imperfect process are the outcome of the waste in the process.…
Q: Question 4: What is the new multifactor productivity? O 0.02145 crates per Php 0.01971 crates per…
A:
Q: a. Create a set of linear equations to describe the objective function and the constraints. b. Use…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Consider the following payoff table for three product decisions (A, B, and C) and three future…
A: Given data is
Q: name and explain THREE modes of transport that can create valuable links between regions and…
A: Transportation is the process of traveling people and goods from one location to another. It helps…
Q: If the maximum daily demand for enamel paint is at 2 tons, determine the production output that…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: In comparing two procCesses, say Process A and Process B, we say that Process A is more efficient…
A: a. Process A better supports specification limit verification:- This will make the process more…
Q: By doing research on the company, you may identify a company that has moved beyond the realm of…
A: E-business is the lead of online business processes on the web, web, extranet or a blend thereof.…
Q: What are the importance of thorough guests screening in the reservation procedures prior to final…
A: Guest screening is the process of evaluating a reservation's risk level by investigating the guest’s…
Q: Discusses the Norming stage of team development with relates to a supermarket, specifically noting…
A: Norming You will know your team has entered the norming stage when small conflicts occur less…
5
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- Analyze the characteristics of a project that calls for a predictive approach to the SDLC, and the one that calls for adaptive approach.Kimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.Evaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk Management
- c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Project completion time d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4 decimal places.) Probability 10 00 days 09994The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?
- Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: example Activity A B C D Get more help. E Time Estimates (days) Most Likely Optimistic 4 5 4 1 3 8 8 5 4 8 Pessimistic 12 12 7 5 a. What is the expected completion time of the project? The expected completion time is 19 days. (Enter your response as an integer.) b. What is the probability of completing the project in 21 days? Refer to the standard normal table. The probability of completing the project in 21 days is 9 MacBook Pro Start (Enter your response rounded to four decimal places.) 0 Finish Q Q Clear all Check answerUsing your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeksUsing PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- Slove the quation: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks. The quation is ; Develop a response strategy for one of the negative risks and one of the positive risks. Enter the information in the risk register.Is forecasting important in a planning of a project? why? why not?Project Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected process