O498 Final Case Studies Name Dyson E. Johnson

Instructions:
Your essays will be graded on content to include grammar and spelling. Each case should take 1-2 pages including diagrams. The essay answers for both #2 and #3 should be 500 to 700 words each, in order to completely answer the questions. Please submit as one document.

Assignment:
#1. Forest Point Construction (System Planning)
a. What is the correct total time?

This would take approximately 40 days using a five-day work week. I figured this out by taken each task step by step and adding them together since site preparations will take 3 days, plus setting building footers another 3 days which now equal 6 days. Then I will add the foundation 5 days, plus another 3 …show more content…

What is the critical path?

The critical path would be prepare the site, set building footers, building assembly, interior work, set an appointment for final building inspection, landscaping and driveway paving, painting and arrange the sale.

#2. Atrium Bio-Medical Supply, Inc. (System Analysis)
a. What options does Atrium have for acquiring a new system?

Atrium’s options are either in-house development to using an application service provider. With these two options; in-house development: is where Atrium can develop its own system, or purchase a system, they could also customize it. According to our course book when in house development is chosen it will start in stages or steps starting with the planning, then to analysis, from here one has to decide either make one or purchase one, then we will have an in house system, or commercial software package, with customized software for both of them, and the final stage is implementation (Rosenblatt, 2014, p. 266).

When in-house developing is the option Atrium chose they would be satisfying their uniqueness for their business, or to do less changes to their policies and procedures, and to meet the constraints of their existing systems and technology (Rosenblatt, 2014, p. 268).

Atrium can purchase a software package if they decide not to outsource for reasons like; lower cost, requires less time to implement, they are proven reliability and performance benchmarks, it also requires less technical development